The F acility for A ntiproton and I on R esearch in Europe. FAIR @ Darmstadt. Member States. All numbers in 2005 € ( e scalation until 2018 ca. +50%) Spain expected to join soon ( with 11.87 M€ ) Negotiation with the UK on Associate FAIR Member status
E N D
The Facility for Antiprotonand Ion Research in Europe NuPECC, Sevilla, 5/10/12
FAIR @ Darmstadt NuPECC, Sevilla, 5/10/12
Member States • All numbers in 2005 € • (escalationuntil 2018 ca. +50%) • Spain expectedtojoinsoon (with 11.87 M€) • NegotiationwiththeUK on Associate FAIR Member status • Talks withChina on Associate FAIR Member status • Contributiontoexperiments(6.6 M€) NuPECC, Sevilla, 5/10/12
Modularised Start Version M0 M3 M1 M3 M2 CBM/HADES APPA PANDA Experiments M1: APPA M1: CBM/HADES M2: NuSTAR M3: PANDA NuSTAR NuPECC, Sevilla, 5/10/12
July 2012 • 526 M€ German contribution to civil construction • largest BMBF grant ever NuPECC, Sevilla, 5/10/12
Further CC Planning NuPECC, Sevilla, 5/10/12
CC Licensing 14.09.12 NuPECC, Sevilla, 5/10/12
CC CurrentPreparatory Work NuPECC, Sevilla, 5/10/12
CC TenderingandContracting NuPECC, Sevilla, 5/10/12
Experimental Site NuPECC, Copenhagen, 15/6/12
Accelerators • SIS100 magnets are being built. • Contracts/tenders for many other parts of SIS100 and CR in preparation. • HESR grant allocated to FAIR; ready for being built/tendered by FZJ and FAIR. • IKRB meeting on 9/10/12. • MAC meeting on 26-27/11/12. Compact & cost effective Fast cycling superconducting magnetsdB/dt ~ 4T/s NuPECC, Sevilla, 5/10/12
Experiments • Project • structure defined • staff in place • Experiment Coordinators • employed • Expert Committee Experiments • First meeting19 Nov. 2012 • Resources Review Boards • First mtgs. beginning of 2013 NuPECC, Sevilla, 5/10/12
Status • Technical Design Reports on experiments • Required by most funding agencies • Currently • NUSTAR: 4 approved + 3 review in progress • PANDA: 2 approved + 3 review in progress • APPA: 1 review in progress • CBM: submission 2013 • Risk assessment experiments • first one completed • In preparation • Detailed common timelines • Construction Memoranda of Understanding NuPECC, Sevilla, 5/10/12
Timeline 2011 2012 2013 2014 2015 2016 2017 2018 2019 12 9 11 6 7 8 10 Building permits Site preparation Civil construction contracts Building of accelerator & detector components Completion of civil construction work Installation & commissioning of accelerators and detectors Start Data taking 10 6 7 12 8 9 NuPECC, Sevilla, 5/10/12 11