An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Metaldyne Korea Business review for operation the first half of 2013 Aug 27, 2013

  2. Table of contents 1/10 1. Production Status 2. Productivity 3. Production Plan 4. Materials & Supplier 5. Logistic cost 6. Delivery & Inventory 7. Improving R-Pallet 8. Maintenance 9. New business in 2014

  3. 1. Operation- Production (Calendar day) 2/10 Production status PCS Plan Vs Actual for Theta BSM Plan Vs Actual for R-BSM Plan Vs Actual for FEMA ※ Theta BSM exceed the target about 24%, R BSM meets the target but Tau FEMA didn’t meet the target due to decreasing of customer demand.

  4. 2. Operation - Productivity 3/10 Actual QPPLH for Q2, 2013 QPPLH Target Target 2.62 5.7% ※ QPPLH didn’t meet our target which was 2.62 and recorded 2.55 during first half year for these reason. - Hired extra worker because of the high turn over rate and an unexpected increasing production volume. ※ Extra works : Inspection for Tight turn (2 workers / April 8~ July 19, about 3 months) Rework for Tight turn (2 workers / January 2 ~March 30, about 3months) Asan plant inspection (2 workers / March 4~June 15, about 4 months) - Try to achieve QPPLH goal even though production volume decrease in the second half year.

  5. 3. Operation – Production Plan 4/10 3.5-Shift 3-Shift - Theta MPI Demand will drastically decrease about 30% compared to first half year. - Glovis Back order was cleared in August. - MKL has been operating 3.5 shifts for Theta Line from last week (August. 19) - There will be 3 shifts in October (※ 4 shifts – 104 worker, 3.5 shifts – 91 worker, 3 shifts– 81 worker)

  6. 4. Operation – Materials & Supplier 5/10 1. Local suppliers 2. Overseas suppliers % of Material Cost against Sales - SEOUL INDUSTRY 9,648 include raw material cost of KONEC and WONTAE

  7. 5. Operation - Logistic cost 6/10 Domestic Delivery Cost It’s cheaper using regular freight than using expedited freight. - If there happens to deliver small amount, it’s better use 1 ton truck instead 5 ton truck (Our contractor) [ Cost Comparison ] 1-ton : 280,000 won (expedited truck) 5-ton : 780,000 won (regular truck) Air Freight Cost Most of all air freight cost result from sending & receiving SAMPLES. Material cost result from East coast Port strike in US. (---> No choice but air)

  8. 6. Operation - Delivery & Inventory 7/10

  9. 7. Operation - Improving R-Pallet 8/10 Background Continually got the customer’s requirement to improve R-BSM pallets which are too old might occur safety problems. Proposal (185 won / ea) We can recoup our initial investment in the second year if we choose the case-B even though it need much initial investment cost than case-A.

  10. 8. Operation – Maintenance Status 9/10 96 Million KRW Total maintenance cost The portion of SW M/C maintenance cost up to July 2013 216 Mil Won Total 473Million KRW Maintenance issues • One big concern is increasing maintenance cost and downtime of SW M/C. • Rearranged spare parts room for the easy inventory management • Plan to repair SW machines for Theta-line. • Rerun the second back up SW M/C instead of repairing 1st SW M/C, which has serious hydraulic system problems

  11. 9. Operation – New business in 2014 10/10 Schedules for New Programs -. GM 2.8L XLDE Balance Shaft Module -. Doosan G2 D34 Mass Balance Shaft ※ We are planning to set-up the production line flexibly to use both program.