Follow the renovation progress of the junior dormitory toilets up to January 11, 2009, with skim coating, wall plastering, tile installation, and more. Updates from S.Thomas’.College.Gurutalawa.Old.Boys.Association.
E N D
S.Thomas’ College GurutalawaOLD BOYS ASSOCIATION 2008/09 JUNIOR DORMITORY TOILET PROJECT
Progress up to 11th January 2009 1). Plastered toilet walls with skim coating in progress. S.Thomas’ College Gurutalawa Old Boys Association
2). Inside of building - View from entrance S.Thomas’ College Gurutalawa Old Boys Association
3). Mahen & supervisor (appointed by Ex-Co) inspecting the work. S.Thomas’ College Gurutalawa Old Boys Association
4). Walls being skim coated. S.Thomas’ College Gurutalawa Old Boys Association
5). Drain positions for wash basins and gullies. S.Thomas’ College Gurutalawa Old Boys Association
6). Inside of building, - View from changing room end. S.Thomas’ College Gurutalawa Old Boys Association
7). Inside of toilet with concrete louvre. S.Thomas’ College Gurutalawa Old Boys Association
8). Outside wall showing pipe laying area with embankment supporting the old retaining wall. S.Thomas’ College Gurutalawa Old Boys Association
9). View showing the changing room end. S.Thomas’ College Gurutalawa Old Boys Association
10). Back of Read Junior night toilet, which was part of the old toilet building, showing the deteriorated condition. S.Thomas’ College Gurutalawa Old Boys Association
11). Completed structure - View from swimming pool side. S.Thomas’ College Gurutalawa Old Boys Association
12). Sanitary fittings and tiles stored inside Read Junior Dorm. S.Thomas’ College Gurutalawa Old Boys Association
13). Partly re-constructed wall of Read Junior (far left side). S.Thomas’ College Gurutalawa Old Boys Association
14). Corridor between new toilet building and Read Junior Dorm. S.Thomas’ College Gurutalawa Old Boys Association
15). New wall of Read Junior Dorm (from corridor side). S.Thomas’ College Gurutalawa Old Boys Association
16). Entrance to toilet building (roof partly covered with the cover sheet over concrete mixing area) S.Thomas’ College Gurutalawa Old Boys Association
17). Concrete louvres of toilets. S.Thomas’ College Gurutalawa Old Boys Association
18). Caved in roof of Read Junior Dorm (Even though it does not look too bad here, timber is in a bad condition). S.Thomas’ College Gurutalawa Old Boys Association
Progress up to 18th January 2009 19). Completed tiling of a toilet. S.Thomas’ College Gurutalawa Old Boys Association
20). Tiled toilet showing pipe connections. S.Thomas’ College Gurutalawa Old Boys Association
21). Internal piping in toilet walls. S.Thomas’ College Gurutalawa Old Boys Association
22). Embankment being filled. S.Thomas’ College Gurutalawa Old Boys Association
23). Lighting being completed. S.Thomas’ College Gurutalawa Old Boys Association
24). Existing sewer manhole for connecting the new sewer line. S.Thomas’ College Gurutalawa Old Boys Association
25). Badly damaged existing sewer line of Read/Garnier Dorm night toilets. (to be replaced) S.Thomas’ College Gurutalawa Old Boys Association
26). Tiling in progress. S.Thomas’ College Gurutalawa Old Boys Association
27). Swimming pool being filled with fresh water after emptying dirty water and cleaning. S.Thomas’ College Gurutalawa Old Boys Association
Well… that’s all for now.THANK YOU! S.Thomas’ College Gurutalawa Old Boys Association