AGA Best Practices Kick Off Meeting Los Angeles January 17, 2012. Lisa Kallberg Principle Pipeline Compliance Consultant. Key Performance Indicators within Gas Operations. Leak sheet audit process Compliance assessment - corrective actions Faulty material process Emergency response.
E N D
AGA Best Practices Kick Off MeetingLos AngelesJanuary 17, 2012 Lisa Kallberg Principle Pipeline Compliance Consultant
Key Performance Indicators within Gas Operations • Leak sheet audit process • Compliance assessment - corrective actions • Faulty material process • Emergency response
Leak Sheet Audit Process • Developed after several regulatory enforcement actions • Steps • Crew completes form • Reviewed by Supervisor • Sends to auditor • Auditor approves or sends back to Supervisor • Supervisor sends back to auditor • Final version and audit form kept in local office • Pilot in St Paul area in October 2011 • Moved to NSPM in spring 2012
Leak Sheet Audit Process • Total reviewed • Total correct • Total forms returned • Total # of errors • Compliance • Total % forms returned • Total % forms correct • Average # of days date created – date reviewed by Supervisor • Average # of days date created – date returned to Supervisor
Compliance Assessment - Corrective Actions • Conducted prior to regulatory inspections • Colorado • MN, WI, MI, ND • Review and document corrective plans • In place within 45 days of completion
Compliance Assessment - Corrective Actions • 2013 upgrading equipment to allow for electronic forms when doing assessments • Advantages of electronic over older paper forms • Report the assessment findings to different levels • Report trends and areas of concern • Update assessment form company wide so all use same version
Faulty Material Process • Gas Faulty Material Analysis Form (Originator completes) • Originator: • Date received from OpCo: • Originator’s Phone #: • Material description: • Operating Area: • Cat ID: • Was faulty material removed? YES NO • Manufacturer: Lot #: • Address where faulty material was installed: • Description of defect: • Did this faulty material cause an injury? YES NO • Date Received by PC&S: • Assign Faulty Material Log #
z Faulty Material 8D Process • 1. Identify team • 2. Define problem • 3. Containment action • 4. Identify root cause • 5. Formulate corrective and preventative action • 6/7. Implement action plan • 8. Closure
Faulty Material 8D Process • Material investigation & analysis cycle time • 85% processed within 90 days • Communicated internally and with material supplier • Some cases with regulatory agencies
Time Interval Definition • Dispatch • Response • Repair crew • Gas shut off • Line repaired
Emergency Response MN only • Reported to the Minnesota Office of Pipeline Safety 30 days after 60 day reporting timeframe • January – February report in March… • November – December report in January next calendar year
Emergency Response at Xcel Energy • Gas Operations scorecard • % ≤ 30 minutes • Required number of drills • CO • MN, ND, WI, MI • 45 days to review and publish results including corrective action plans