Organics Waste Processing Facility Construction Progress Update December 15, 2010. Organics Waste Processing Facility Construction Progress Update December 15, 2010. Masonry and structural steel work in administration building area (November 15, 2010).
E N D
Organics Waste Processing Facility Construction Progress UpdateDecember 15, 2010
Organics Waste Processing Facility Construction Progress UpdateDecember 15, 2010 Masonry and structural steel work in administration building area (November 15, 2010)
Organics Waste Processing Facility Construction Progress UpdateDecember 15, 2010 Tunnel 7 spigot piping and Granular A backfilling (November 16, 2010)
Organics Waste Processing Facility Construction Progress UpdateDecember 15, 2010 Backfilling and compaction in biofilter cells (November 22, 2010)
Organics Waste Processing Facility Construction Progress UpdateDecember 15, 2010 Concrete pour for tunnel wall along Gridline 4 (November 24, 2010
Organics Waste Processing Facility Construction Progress UpdateDecember 15, 2010 Precast hollow core slab installation in administration building (November 25, 2010)
Organics Waste Processing Facility Construction Progress UpdateDecember 15, 2010 Precast hollow core slab installed over tunnel 7 (November 26, 2010)