An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CITY OF POLOKWANE

  2. Funding • Total cost estimated QS =R 864 659 644 • Received tender price = R 1 245 236 999

  3. Funding • Funding from National Government R 696 776 897.00 • OC TT cost estimated submitted to DG 2010 R 812 000 000.00

  4. Estimated Shortfall and Progress to date • Estimated shortfall before process re-engineering R 576 299 520.00 • Estimated shortfall after process re-engineering R 476 299 520.00 • Tender closed 14/12/2006 received 3 tenders out of 5 • Negotiation took place on 16/01/2007 with bidders to reduce cost • Final prices to be received on 23/01/2007. • Only be in a position to have the final shortfall on the 26/01/2006

  5. Prose's re-engineering • Omit aluminum facade and replace with hand-railing • Downgrading of some specifications • Reducing number of lifts • Change in seating specifications • Requested contractors to re-look at tender amounts and offering potential savings and alternatives to reduce tender price

  6. Process re-engineering (continue) • Reducing the number of electronic equipment • Alternative construction guarantees in order to reduce price • Possible saving by extending the contract period

  7. Approach to development of Stadium • Investigation to upgrade existing stadium • Old stadium upgrade extra cost to project R 48 000 000.00 • Income lost of R 750 000 per year if old stadium was demolish.

  8. Stadium Designing • Design be done in accordance with FIFA requirements • Use of elements that is maintenance free • Plans submitted to OC TT team for approval • Taking environmental aspect in consideration

  9. Treasury view point on Escalation • National Treasury will express their view point on escalation • According to newspapers report Steel increased by 20% Labour cost increase 20% Copper cost increase by 84%

  10. Reason for increasing of Tender Price • Material shortages • Skilled labour shortages • Shortage of skilled personnel in management positions • Pant and equipment shortages • Concurrent construction of stadiums • Importing of some material • Media reporting

  11. Constrains MFMA • Funds on the budget before awarding the tender • Follow the MFMA guidelines for procuring the tender

  12. THANKS