An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Test Results Thermo- mechanical prototype Consolidate design Consolidate design produce drawings Xmas closure • Mechanical • components • order CE07 parts • fabricate special parts • prepare pipework / • feedthroughs • (incl. leak test) • fabricate interface • card flanges • fabricate pot hats • (Vacuum Praha) • follow-up / reception conceptual tests Geometrical precision test Temperature Cycling of thermomechanical prototype Internal Review • Tooling • gluing tools • bonding tools • detector assembly tools • pipework bending/testing tools availability sensors (tested) availability interface card (tested) availability hybrid PCB/VFAT (tested) Full Integrated Module (10 planes + complete electronics). Extended lab tests. Beam test ? Preparation work area holiday period • Hybrid • lamination • Chip • mounting/ • bonding • Testing detectorpot insertion tool • Sensor • mounting/ • bonding • Testing • Detector • assembly • Metrology • Integration • in pots • Testing • (incl. cooling) • beam ? end of installation in tunnel • Installation • in zone

  2. DT2 D Test Results Thermo- mechanical prototype Consolidate design Consolidate design produce drawings X-mas closure DT2 D DT2 D/T • Mechanical • components • order CE07 parts • fabricate special parts • prepare pipework / • feedthroughs • (incl. leak test) • fabricate interface • card flanges • fabricate pot hats • (Vacuum Praha) • follow-up / reception conceptual tests Geometrical precision test Temperature Cycling of thermomechanical prototype TOTEM Internal Review TOTEM DT2 D/T TOTEM • Tooling • gluing tools • bonding tools • detector assembly tools • pipework bending/testing tools availability sensors (tested) availability interface card (tested) availability hybrid PCB/VFAT (tested) DT2 2T Full Integrated Module (10 planes + complete electronics). Extended lab tests. Beam test ? TOTEM Preparation work area Bondlab TOTEM holiday period DT2 T • Hybrid • lamination • Chip • mounting/ • bonding • Testing detectorpot insertion tool • Sensor • mounting/ • bonding • Testing 1D, 1T • Detector • assembly • Metrology • Integration • in pots • Testing • (incl. cooling) • beam ? end of access to underground areas TS/DEM • Installation • in zone Bondlab Bondlab TOTEM 2T TOTEM TOTEM 2T TOTEM 2T

  3. Consolidate design produce drawings Internal Review • optimize alignment pins • optimize detector mounting • optimize guidance blades • optimize cooling pipe routing • interface card flange • Kapton cable, connectors • drawings for tooling (gluing, bonding, assembly)

  4. conceptual tests • insertion procedure of detector assembly into pot • (requires to build a transparent dummy pot)

  5. Geometrical precision test • provide components • n x CE07 parts • n x Kapton PCB • n x Si sensors • finalize tooling • laminate Kapton on substrate  PCB • glue Si sensor  decide on glue ! • glue PCB on side bars using 3D-CMM • assemble planes to module • perform metrology test • perform temperature cycling (-30 / + 50ºC, env. test chamber) • redo metrology

  6. Full Integrated Module (10 planes + complete electronics). Extended lab tests. Beam test ? • provide components • 10 x CE07 parts • 10 x Kapton PCB • 10 x VFAT chip set • 10 x Si sensors • motherboard • readout system • dummy pot • DAQ system • test under vacuum ?  cooling required ! • assemble full module, with maximum precision (to be defined in detail) • Lab tests (source ?) • Beam test ? • temperature cycling (env. test chamber)

  7. Preparation work area • semi clean area SCA (~50 m2) • temp. / humidity restrictions ? Not severe. • safe storage compartments • safe transport boxes • protective and other equipment (gloves, masks, coats, alcohol, tools, …) • test benches (VFAT, IV-curve, Roman Pot, cooling) • organize logistics: TS-DEM  Bondlab  SCA  Bondlab  SCA …