Barrel integration status

Barrel integration status. Jun 28 – 1 st module installed July 21 – all but 2 type 1 modules installed 1 cooling sleeve problem 1 HV problem (M1.35) Aug. 2 – type 1 complete Fixed cooling sleeve Gave up M1.35, use M1.26

Download Presentation

Barrel integration status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Barrel integration status

  2. Jun 28 – 1st module installed July 21 – all but 2 type 1 modules installed 1 cooling sleeve problem 1 HV problem (M1.35) Aug. 2 – type 1 complete Fixed cooling sleeve Gave up M1.35, use M1.26 Aug. 6 – 1st type 1 electronics installed, complete with readout & LV/cooling interlock. Aug. 11 – 1st type 2 installed Aug. 31 M1.26 removed, to be replaced with M1.35 Sep. 2 snap shot: Type 1 - Waiting for M1.35 Type 2 - 21 modules installed, 7 more in SR being prepared. Type 3 - 4 modules in SR being prepared. Recent Time line

  3. Evenly distribute dead channels … Observe constrains or preferences on HV feeding side due to anomaly in HV kapton. Module placement in BSS

  4. Capacitor installation (~1-2 days/module) Insert capacitors Check capacitor connectivity Check HV traces HV test: caps + wires Seal capacitors Pre-insertion prep. (6 modules/day/2 person) Check ground wire Check cooling sleeve Check mounting holes Active gas fittings, custom made for each module: connection & leak test Glue purging gas gasket Tape HV kapton for protection Glue thermal sensors as needed (4 modules each type) Module preparation

  5. Procedures & tests Fold HV kapton and cover with protection plates Insert module & fix one corner Set module z position to middle of BSS Fix module 2nd corner & attach set screws Check purging gas flow Type 1 1.5 L/min < 10% loss Type 1+2 1.5 L/min < 15% loss Type 1+2+3 0.5 L/min < 20% loss Unfold HV kapton & check traces Attach & glue active gas fittings Plug & seal unused active gas inlets. Leak test active gas volume (1mB/B/min) Install protection boards HV test Check active gas path for obstruction (flow rate test) Module installation

  6. Components modification Peek tubes for module cooling reduced from 0.123”-0.127”  0.116”-0.120” (done) De-magnetization of active gas inlet plugs (started on type 2 modules) Fuse box brackets dimension change Fuse box screws changing from Nylon to Ultem Module repair: Wire removal (2 bad wires + some retroactive decisions from acceptance group) HV trace repair (1) Cooling sleeve replacement (3) Re-glue detached shell & divider (1) Tension plate socket replacement (2) Non-routine module work

  7. Beyond modules • Data Base: Access data base in use for progress tracking. • MTF: Migration in progress. Preliminary tree structure available for review. • Upgrade for space frame bracing (needed for type 3 installation): In progress, some components ready to be installed. • Outer cylinder is yet to be copper shielded. • Gas/Cooling manifold: Expect to have drawings reviewed and submitted for fabrication this month.

  8. Protection boards - 21 type 1 modules installed. 6000 more boards coming. FE assembly – P1.29 installed. 17+ more being prepared DCS : HV, LV, thermal sensors, cooling interlock (CIL) … operational. Electronics installation

  9. Summary • More than half of the modules have been installed! • Procedures are understood and becoming routine. • Module installation expect to finish by the end of the year • Electronics installation has begun.