190 likes | 334 Views
TEC Mechanics and Integration. 25. 1. 2005 Lutz Feld, RWTH Aachen. 1 TEC = 8 sectors = 16 towers. 1 sector = 2 towers = 9 front petals +9 back petals = 9 control loops = 4 cooling loops. 1 tower = 9 front petals or 9 back petals = 2 cooling loops. Overview. DAQ test.
E N D
TEC Mechanicsand Integration 25. 1. 2005 Lutz Feld, RWTH Aachen
1 TEC = 8 sectors = 16 towers 1 sector = 2 towers = 9 front petals +9 back petals = 9 control loops = 4 cooling loops 1 tower = 9 front petals or 9 back petals = 2 cooling loops Lutz Feld, RWTH Aachen
Overview DAQ test Lutz Feld, RWTH Aachen
DAQ test note that some months are suppressed for the purpose of this table integration of 2 sectors in parallel Lutz Feld, RWTH Aachen
TEC Integration • team: • Aachen Ib: Richard Brauer, Berthold Debye, Lutz Feld, Waclaw Karpinski,Katja Klein, Martin Weber, Michael Wlochal + 3 technicians • Lyon: Gaelle Boudoul, Didier Contardo, Nick Lumb, Laurent Mirabito+ n technicians • documentation: • “Integration of the Tracker End-Caps of the CMS Silicon Strip Tracker” • written by Aachen Ib and Lyon • fairly advanced draft, will be made available after additions from Lyon are implemented Lutz Feld, RWTH Aachen
Components of a TEC before integration • Nine disks, which will carry the petals • The front disk • The back disk, consisting itself of the disk 10 and the alignment ring • The bulk head • Alignment system components, in particular the 16 beam splitters that are located on disk 6, plus the optical • fibers attached to them • Eight service channels filled with optical fibres. These will be provided by Karlsruhe • 16 sets of cooling pipes (one per tower). Each set consists of four main pipes plus the connections to the petal manifolds, as well as the multi-service cables (MS cables) and control power cables necessary to power one tower of petals. Fully tested assemblies of cooling pipes with cables will be received from Lyon • 144 fiber connector holders screwed onto the disks • Grounding and shielding elements • The inner tube • The outer enclosure • The slide-in mechanics Lutz Feld, RWTH Aachen
Components for TEC Integration • petals are integrated into TEC sector-by-sector PICs need to deliver petal types such that one sector can be filled after the other Lutz Feld, RWTH Aachen
Reception of TEC Structure • TEC structure is receivedin its transport and rotation cradle Lutz Feld, RWTH Aachen
Petal reception • PICs deliver known good petals to TEC integration sites • first 18 petals to Lyon for DAQ test • then 144 petals to Aachen for TEC+ • then 126 petals to CERN for TEC- • each petal will be inspected upon arrival at TEC integration site • a read-out test will check basic functionality • details in the document • this is NOT a full test like at the PICs • read-out electronics in hand, qualification of set-ups to be done • capacity of petal reception: 2 petals per day • storage capacity at TEC integration site for at least 40 petals Lutz Feld, RWTH Aachen
Petal Acceptance Criteria • criteria will be matched to petal quality criteria applied at PICs (which do not yet exist) • the decision whether a petal passes the acceptance will be based on the following criteria: • optical inspection • all optical fibers working (connectivity scan) • all chips (except DCU) accessible via I²C • all modules can be read out in all modes,all sensors (temperature, humidity) work properly • leakage current per high voltage channel must not exceed the respective value measured (under comparable circumstances) during the petal assembly by more than 20%. • mean per APV of the noise after common mode subtraction is required to be below a certain threshold • RMS per APV of the noise after common mode subtraction must be below a certain threshold • number of bad strips based on the noise below a threshold (to be decided)exchange module if number of bad strips >2% (?) Lutz Feld, RWTH Aachen
Petal Repair • only 5-7 spare petals per type • need to attempt repair of any faulty petal • repair centers: Aachen IIIb and Lyon/CERN • rely on very good quality of petals from PICs Lutz Feld, RWTH Aachen
TEC Integration • sector by sector, starting at the 3 o’clock and 9 o’clock positions • integration and test of one sector takes 15 working days: Lutz Feld, RWTH Aachen
TEC Integration Work Plan Lutz Feld, RWTH Aachen
TEC Sector Test 1. Bare connectivity and cabling check: connectivity scan 2. Basic commissioning of the sector: Timing alignment run Adjustment of laser gain and bias settings 3. Pedestal runs: 10000 events in peak mode 10000 events in deconvolution mode 4. Data taking of cosmic events: Commissioning of the particle trigger 100000 events per module in peak mode 100000 events per module in deconvolution mode 5. Laser alignment run 6. Cold test: TEC+ first sector in Aachen, full TEC+ and any sector in TEC- in Lyon cold room (at CERN ) Lutz Feld, RWTH Aachen
Hardware for TEC Sector Test • nothing in hand today+ cooling unit (to be delivered soon) + interlock system (July 05 ?) Lutz Feld, RWTH Aachen
Sector Acceptance Criteria • all optical links working ok • all chips (except DCUs) accessible via I²C • all modules can be read out in all modes • no module has more than 5% (?) bad strips • stable HV operation up to 450V Lutz Feld, RWTH Aachen
Tests before insertion into TK tube • metrology check • optical survey by CERN metrology group • details to be defined • cold read-out test • using Lyon cold room • procedure and criteria (probably) very similar to sector test Lutz Feld, RWTH Aachen
Main Open Issues • when can we expect the first production petals? • current planning assumes: • early petals for DAQ test in Lyon ASAP • first 18 production petals for TEC+ ready latest in June 05 • petal logistics • transports • quality of petals • we need to achieve a very low repair rate at the TEC integration sites • delivery of read-out components and DCS for sector test • facilities at CERN (+manpower) • integration of TEC- at CERN needs to be prepared(including a PIC at CERN, at least for petal repair) • reception and test of TEC+ Lutz Feld, RWTH Aachen