1 / 32

SHMS Design, Engineering & Construction Status for Hall C Users meeting

SHMS Design, Engineering & Construction Status for Hall C Users meeting. Paul Brindza January 2010. Hall C SHMS 11 GeV/c Super Conducting Spectrometer. Removable Roof & side wall. Concrete Detector Shield House. DC Supplies. SHMS Steel Support Structure. Dipole.

dena
Download Presentation

SHMS Design, Engineering & Construction Status for Hall C Users meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SHMS Design, Engineering & Construction Status for Hall C Users meeting Paul Brindza January 2010

  2. Hall C SHMS 11 GeV/c Super Conducting Spectrometer Removable Roof & side wall Concrete Detector Shield House DC Supplies SHMS Steel Support Structure Dipole Cryogenics Transfer Line Q3 Q2 Q1 HB Hall C Pivot

  3. SHMS Design, Engineering& Construction • Status of SHMS overall • Status of SHMS SC Magnets • Status of JLAB supplied SC Magnet Systems • Status of SHMS Support Structure and Shield House (SS/SH) • Conclusions

  4. SHMS Magnet DesignsMagnetic Properties at 11 GeV/c jlabgrp\wbs\6\mjf\hall_c\lassiter\SHMS\SHMS Magnets Design 2009.pptx

  5. SHMS SC Magnet System Plan CryogenicControlReservoir Meyer Tool Magnet Control System JLAB design started DC Power System Bids in Fabricate CryostatedMagnet Q1 underway RFPFixed Price Procurements Q1 awarded On Site Integration & Assembly Acceptance Testing Ship to JLAB Conductor Processing HB & Q1 complete Q23D TBD Warm Iron Yoke Magnet Support & Alignment Testing at BNL Complete SC Cable (SSC surplus)

  6. SHMS Design, Engineering& ConstructionHB 3.1 Tesla Dipole SC Magnet • MOU for HB Collaboration with MSU/NSCL • Reference Design completed Feb 09 • Design reviews (Oct 06, April 08, Feb 09) • JLAB Tech Spec complete - reviewed June 09 • Sole Source RFP to MSU/NSCL June 09 • HB Proposal/Bid for Construction Aug/Dec 09 • Final Negotiations with MSU/NSCL underway

  7. HB SC MagnetHB Reference Design Review Successful Feb 09 • Superferric “C” magnet • 2.7 Tesla • 35cm x 36cm bore • 0.756 M EFL • 1.93 TM • 17.7 % design margin • 290 KJ stored Energy

  8. Q1 9 Tesla/meter SC Quad Magnet • Construction Contract Awarded for the Q1 SC quad magnet to Scientific Magnetics(SMI) July 2009 for delivery in Dec 2011.(D1 Milestone) • Conductor acceptance by SMI( F1 Milestone) • First Q1 design review Oct 09(D2 milestone) • Conductor insulated at SMI (F2 milestone) • Magnetic analysis by SMI (D7 milestone) • Instrumentation Design (D13 milestone)

  9. Q1 SC Magnet JLAB Cold Iron Design ( clone of HMS Q1) • 11 GeV/c performance • 8.3 T/M Gradient • 40 cm warm bore • 1.9 M EFL • 14.75 (T/M)M Int. Grad. • 510 KJ Stored Energy • 26 % design margin

  10. SHMS Design, Engineering& ConstructionQ2 Q3 & Dipole cosine type SC Magnets • Bid/RFP released March 2009 • Bids in July 7th 2009 “too few & too high” • Rebid in Jan 2010 with revised requirements • Split procurement of dipole and quads • Lower current more turns(more temp. margin) • Revised coil winding design(even more turns) • Larger bidders list • Bids due in April 2010

  11. Q2/Q3 SC Cosine(2Θ)Magnets • Q2 12.4 T/M SC Quad • 60 cm. warm bore • 1.61 EFL • 16 % design margin • 8.0 MJ stored Energy • Q3 identical to Q2 but runs at 8 T/M

  12. SHMS SC Dipolecryogenically stabilized design • 4 Tesla Cosine(Θ)dipole • 60 cm warm bore • 2.85 M EFL • 11.2 TM Integral B.dL • 18 % design margin • 16.5 MJ stored Energy • 11 GeV/c

  13. SHMS Design, Engineering & ConstructionSC Magnet Components & Systems I • SHMS Superconductor- Design complete • All SHMS SC Cable Tested at BNL 07/08 • SC Cable reshaping for HB,Q1 complete 2007 • SC Copper Extrusion- Bids in • Award Copper Feb 2010 &extrusion April 2010 • SC wave soldering- Bids In • Planned Award April 2010

  14. SHMS Design, Engineering& ConstructionSC Magnet Components & Systems II • Cryo-Control Reservoir(CCR) Design complete • CCR Bids in Aug 10- under evaluation • Awarded to Meyer Tool December 2009 • First CCR delivery May 2010 • Burnout Resistant Current Leads(BRCL) Design Complete( clone of G0 magnet leads) • BRCL pair built and tested by AMI in 2006 • Award to AMI in Oct. 09-delivery Feb 2010

  15. CCR cut away view

  16. SHMS Design, Engineering& ConstructionSC Magnet Components & Systems III • DC Power Systems- Design complete • Bids in Jan 2010- planned award April 2010 • SC Magnet Instrument & Control Clone of HMS System - Fabrication at JLAB 2010-2011 • Yoke steel- Design complete awaiting final SC magnet design to finalize bid in 2011-Fabrication 2011/2012

  17. Support Structure and Shield House (SS/SH) • SS/SH Reference Design review Dec 2008 • 3D CAD of Structure and Shield House • Assembly Plan of structure • Drawings of SS/SH & Wheel Bogey redesign • Shielding and detector access design • FEA of steel structure by JLAB • Fab. Drawings and Construction Support for SHMS SS/SH- RFP in Preparation(2010) • Steel Components Fabrication 4Q 2011/2012

  18. SHMS Steel Structure 200 tons of Steel Prefabricated Sections Assembly in Hall C

  19. SHMS Shielding • Concrete shield house structural & neutron Thermalization and absorption of primary radiation • Inner wall of “Stucco” made from Boron Carbide(B4C) to absorb thermal neutrons • 2 inch lead layer to absorb gamma’s • Studies of dry packed B4C complete • B4C Stucco tests underway

  20. 2 in lead on front and beam side walls

  21. Conclusions • SHMS SC Magnet designs 100 % complete Q1 contract awarded, HB in Evaluation Q2Q3 and Dipole rebid • SS/SH Reference Design complete & RFP for fabrication drawings and construction support underway • Magnet systems by JLAB well along • Beam line, SHMS vacuum , cryo supply TBD • Detector support well along-SHMS lead glass support complete

More Related