This document outlines the facilities master plan and capitalization program for Southwestern Community College District, including information on current projects, future priorities, and procurement processes.
E N D
SouthwesternCommunity CollegeDistrict FacilitiesMasterPlanand CapitalizationProgram November13, 2013 JohnR.Brown,P.E. Director ofFacilities, Operations,and Planning MarkClaussen ConsultingProgramManager PropR CapitalProgram
SouthwesternCommunity CollegeDistrict • Oneof 72CaliforniaCommunityCollege “TheJaguars” Districts • • Annualoperatingbudget ~ $90million Servicearea Citiesof: – ChulaVista,NationalCity,SanDiego,ImperialBeach,Coronado,SanYsidro • • • • Five Campuses -156acres@900OtayLakesRoad,ChulaVista Students WSCH Academic 17,504day enrollment 214,121 (forecastFall 2012) (Fall 2012) (Fall 2012) Staff FTE 518
SouthwesternCommunityCollege District Proposition R approved November2008 $389Millionin authority Currently $165Millionsold andavailable Approximately $100 Millionexpensed or obligated Programming bulkof available cash $65 Millioninnext 6months • • • • •
ChulaVistaCampus Primarylocation ForCapitalProgram Bulkof structures CIPfrom1970 Two otherprojects at HECNationalCity HECOtayMesa FacilitiesMasterPlan (FMP)outlinesfuture
SWCCD Priorities Transparency SupportStudentSuccess Efficient and effective execution Leverage capitaldollarsto support operational costs Total Costof ownership Sustainability • • • • reduced • •
Procurement Proposition R
ProfessionalServicesRFPDates • Planning –Executive/MasterArchitect Design (Prequalified) –Architects Completed • • • • WellnessCenter/ Gym MathandScience Bldg. Performing Arts/ CulturalCenter Now Feb2014 Feb2014 Now 2014 2014 • • • DSAInspection Geo-technicalServices Infrastructure/ Civil
Support/ ConstructionServices • • • • • Geo-technical Services Infrastructure/ Civil HazmatSurvey /Inspection 2014 2014 2014 2014 Now M CM (mostlikely)atRiskList Photovoltaic DesignBuild –3.5MWgenerationupto$13.6 • Furniture Fixtures & Equipment Now
Project Schedule ProjectName 2013 2014 2015 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 FieldHouseClassroomBuilding CentralPlant MaintenancePeriod TurfFields EmergencyBlueLight LotOBioSwale/Entrance/ADAUpgrade SolarInitiative WellnessCenter/GymnasiumBuildings Feasibility WellnessCenter/GymInfrastructure PerformingArtsCulturalCenter Feasibility EnergyLoopBuildingConnections MathandScienceBuilding H.E.C.NationalCityPhaseII OtayFire/PoliceAcademyInfrastructure FFE-StandardsandProcurement TechnologyProject StudentUnionComplex Planetarium/ExhibitHall LEGEND SouthwesternCollege Planning Design 2013-2015PropositionR DSAReview Bid/Award Construction/Close-out Equipment Procurement/Install DataDate-6/03/2013 10 10
Points of Contact Steve Crow,VicePresidentof Business and • FinancialAffairs scrow@swccd.edu • John R. Brown,P.E. Director of Facilities, Operations, andPlanning jbrown@swccd.edu Procurement, Management • Priya Jerome, Director of Central Services,andRisk pjerome@swccd.edu • MarkClaussenConsultantProgramManager mclaussen@swccd.edu
Information http://www.swccd.edu/ • – – LookforFacilitiesMasterPlan LinktoFMP http://www.swccd.edu/modules/showdocument.aspx?documentid=4868 LinktoPROPR http://www.swccd.edu/index.aspx?page=2649 LinktoCBOChttp://www.swccd.edu/index.aspx?page=2431 – – - ProGroup http://www.southwesterncollegeproprplanroom.com
Q & A