1 / 18

Detailed Undulator System Status and Schedule at SLAC

This document provides a detailed overview of the activities, calibration, integration, and installation schedule of the Undulator System at SLAC. It includes information on magnet calibration, undulator tuning and fiducialization, alignment engineering, and more.

dianneg
Download Presentation

Detailed Undulator System Status and Schedule at SLAC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Detailed Undulator System Status and Schedule at SLAC Rodd Pope, SLAC

  2. SLAC Activities (1) • Magnet Calibration • Undulator Tuning & Fiducialization • Quadrupole Measurement & Fiducialization • Alignment Diagnostic System (ADS) • Hydrostatic Level System (HLS) • Wire Position Monitor System (WPM) • Alignment Engineering • Component Fiducialization • Tunnel Mapping and Monitoring • Sub-system, In-tunnel Positioning

  3. SLAC Activities (2) • Assembly, Material Handling, Storage • Kits, Sub-assemblies, Assemblies • Girder Rough Assembly (pre-CMM precision) • Girder Precision Assembly • Cam Mover Assembly and Calibration • Fixed Support Assembly • Storage Space • Installation • Alignment Network • Cable Pull, Termination, Connection • Fixed Supports • Girders • Alignment Diagnostic System • Vacuum System

  4. SLAC Activities (3) • Integration • LTU – Undulator • Undulator – E-Beam Dump • Undulator – Conventional Facilities • Undulator – Controls • Software, Cables, Power • ANL Undulator Efforts – SLAC Undulator Efforts • Hardware, Controls, Product Data, Production Data • Commissioning • First Light

  5. Summary Schedule – Source P3

  6. Budget Summary

  7. Magnet Calibration (1) • Process Development • Undulator Tuning • Undulator Fiducialization and Normalization • Quadrupole Measurement and Fiducialization • Instrument Specification • Rough Tuning Bench • Fine Tuning Bench • Fiducialization CMM • Quadrupole Measurement & Fiducialization Station • Pulsed Wire Test Stand

  8. Magnet Calibration (2) • MMF Population and Startup • 3 months late - $1M over-budget • Work will be completed October 2006 • Exception: Assembly and Installation Equipment (separate WO) • MMF Beneficial Occupancy – May 2006 • Startup Issues • Temperature – Solved with New Valve in September • Power – Solved with 100% Lug Inspection in September • Compressed Air – Temporary and Permanent Solutions • Temporary Solution with Second Compressor • Permanent Solution with New Compressor of Adequate Pressure • Kugler Bench (Fine Tuning) • Delivered – June 2006 • First measurement – August 2006 • Production measurements – November 2006

  9. Magnet Calibration (3) • MMF Population and Startup • Dover Bench (Rough Tuning) • Installed – June 2006 • Production measurements – September 2006 • Kugler Bench (Fine Tuning) • Delivered – June 2006 • First measurement – August 2006 • Production measurements – November 2006 • Leitz CMM • Delivered - July 2006 • Operational on Accelerator Sections – August 2006 • Undulator Fiducialization Production – December 2006 • Quadrupole Test Stand • Pulsed Wire tested on Permanent Magnet • Stage to be sized for Electro-magnet Design

  10. Magnet Calibration (4) • Production Operations • Undulator Magnet - $735k • 1st Undulator RFI – January 2006 • Production schedule has 170 days float • 1 per week in production • Quadrupole – $127k • 1st Quadrupole RFI – August 2007 • Production schedule has 57 days float • 4 per week in production

  11. Alignment Diagnostic System (WPM/HLS) • Scope • Design, fabricate and commission the HLS and WPM systems • Franz Peters, WPM and Georg Gassner, HLS for Robert Ruland • Status • PDR completed August 2006. • ESD completed October 2006. • HLS sensor order placed, WPM electronics order placed • Budget (includes Alignment Engineering Setup) • SPI = .92, CPI = 1.01 • 25% Complete: $672k of $2,694k • Schedule • Assembly onto the Girders starts August 2007 • Installation in the Tunnel is February 2008

  12. Alignment Engineering • Scope • Component Fiducialization • Tunnel Mapping and Monitoring • Sub-system, In-tunnel Positioning • Status • Supporting Magnet Calibration • Supporting Design Reviews • Will be finalizing individual processes as designs are released • Budget & Schedule • Included in ADS SPI & CPI

  13. Assembly, Material Handling, Storage • Scope • Kits, Sub-assemblies, Assemblies • Girder Rough Assembly (pre-CMM precision) • Girder Precision Assembly • Cam Mover Assembly and Calibration • Fixed Support Assembly • Storage Space • Status • Storage and Assembly Space Secured in B750 • Process Travelers Drafted • Equipment Specification, Design, and Fabrication has begun • Working Production Control with ANL and within SLAC • Budget & Schedule • Assembly runs August 2007 January 2008 • Assembly = $511k, Material Handling/Storage = ~$250k

  14. Installation • Scope • Alignment Network • Cable Pull, Termination, Connection • Fixed Supports • Girders • Alignment Diagnostic System • Vacuum System • Status • Installation drawings waiting for Fixed Support drawing release • Reviewing Tunnel specifications for integration • Preliminary installation plan incorporated into ETC • Developing equipment • Budget – 1.4.6 • Work at SLAC has yet to begin • Schedule • Begin November 2007 at “Co-availability” date • On Undulator Critical Path

  15. Integration • Scope • LTU – Undulator • Undulator – E-Beam Dump • Undulator – Conventional Facilities • Undulator – Controls • Software, Cables, Power • ANL Undulator Efforts – SLAC Undulator Efforts • Hardware, Controls, Product Data, Production Data • Status • Documentation Transfer Process in Place • Member of Integration Management Team lead by Richard Boyce • Revising Interface Control Documents • Managing the Flows of Information, Facilitating Decisions • Budget & Schedule • 2 FTE – % of System Manager, Mechanical Designer, Area Manager

  16. Next Six Months • Production Control Communication • Geoff Pile is developing a tool. • Release document transfer process is in place. • Exact Statement of Work content will solidify scope of SLAC work. • WPM mockup operational in B750. • Material handling equipment in place. • 50% of Undulators RFI. • Component deliveries beginning.

  17. Next Six Months (2) • HLS/WPM Final Design Review – 1/07 • HLS/WPM Procurements Placed • Girder Assembly and Component Fiducialization • Plan complete • Tooling designed and ordered • Production Drawings and SOW’s archived at SLAC • Cable Plant Preliminary Design Review Complete – Long Lead Procurement Placed • Pedestal installation Statement of Work out for bid

  18. End of Presentation

More Related