340 likes | 352 Views
Undulator Cavity BPM Status. Design Review Outline. BPM System Design Overview Cavity Design Electronics and ADC Current status for phase I prototype testing Planning phase II prototype test First article and production. LTU and Undulator BPM System Specification.
E N D
Design Review Outline • BPM System Design Overview • Cavity Design • Electronics and ADC • Current status for phase I prototype testing • Planning phase II prototype test • First article and production
X-Band Cavity BPM Design • Each BPM has position cavity and reference cavity • SLAC selective coupling design utilized to reduce monopole mode • Iris couplers are precisely EDM into Solid Copper Body • Waveguide transition brazed to body
Cold Test Prototype • Non-vacuum cold test prototype • Accelerated design verification and cold test development • Removable end caps • Presently used to verify tuning effects and test fixture development
Baseline Design for Phase I PrototypeMiteq X-Band Low Noise Receiver • Existing product line • WR 75 Waveguide Interface • Low Noise Figure (2.7 dB) • Budgetary price for (3 channels) $6500.00
Prototype X-Band Low Noise Receivers • Conversion gain 28 dB • Over 60 dB dynamic range • Noise Figure 2.5 dB • IF bandwidth 40-80 MHz • Receiver noise floor -88 dBm assuming 20 MHz IF bandwidth • Cavity BPM Sensitivity: -54 dBm/0.2nC/1m
Phase I Injector Test Stand ITS Install single X-Band Cavity and modified off-the-shelf down converter receiver Mount BPM on two-axis translation stage Phase II LEUTL test with PC gun Install three X-Band Cavities BPMs Mount all 3 BPMs together on a two-axis translation stage BPM System Test Approach
Injector Test Stand (ITS) Beam Parameters • Charge- 1 nC single-bunch • Bunch length- ~ 3 - 4 ps FWHM for ps laser • Spot size on final screen at 5.5 MeV ~ 0.75 mm rms, ps laser
(Phase I) ITS BPM Test Results • BPM setup on X/Y translation stage • Aligned BPM Pitch and Yaw to < 25 m • Initial beam spot size 2-3 mm rms at low charge (0.05 nC) at faraday cup before adding new focusing magnetsto reduce to 200 um rms • Beam stability limited to 50 m rms. Laser improvements ongoing
ITS Data Processing Development • Cavity BPM and electronics tested using ITS beam line • First raw cavity voltage outputs captured on scope 6/9/06 • Mover system calibration • Testing is on-going following Aug/Sep shut-down Hor. Ref. Vert.
Waveforms acquired with sampling scope and processed via Epics
(Phase II) 3 BPM Test Schedule Milestones • Refine design and develop First Article Cavity BPM and support hardware • August 06 • Start 3 BPMs • October 06 • First unit with accelerated delivery • October 06 • Install 3 cavity BPMs into APS LEUTL and Test • December 06
Dipole Cavity Design • Beam pipe radius = 5 mm • Cavity radius = 14.937 mm (14.888 mm) • Cavity gap = 3 mm • Distance beam axis to bottom of wg = 9.5 mm (10.5 mm) • Waveguide= 19.05 x 3 mm
Monopole Cavity Design • Beam pipe radius = 5 mm • Cavity radius = 11.738 mm (11.477 mm) • Cavity gap = 2 mm (3 mm) • Coupling Slot = 2 x 4 mm (2.5 x 4 mm) • Tangent to surface of cavity opening to bottom of waveguide=1.734 mm (3.75 mm) • Waveguide= 19.05 x 3 mm
Tuning Pins Tuning Pins Feature Added • Tuning pins prototyped and tested in lab • Tuning pin simulations verify lab measurements • Tuning pins will improve performance and production yield
Design Development First Article Design ITS Test Unit Cold Test Unit
Receiver Design Changes • Packaged 3 channel receiver • High/Low gain feature (28/0dB) to extend dynamic range. • Add a simple CW tone self-test feature
Receiver Packaging Design • Receiver enclosure 12.5 wide by 11 deep by 2.5 thick (inches) with radiation shield cover • Houses input filters local oscillator and down-converter • 3-WR75 Inputs, 3-type “N” outputs, LO ref. input Type “N”, power and control cable
SLAC ADC Development • The PAD (Phase and Amplitude Detector) being considered for Cavity BPM ADC • Linear Technologies LTC2208 16 bit digitizer chip specified to run up to 130MHz
Phase II Data Acquisition Design Approach • Instrument three BPMs with SLAC Built 16-bit, 130 MSPS digitizers (PAD) • Epics driver available • Synchronize ADC clock with 119 MHz • Digitize horizontal, vertical position and Intensity 0 to 1 volt range • Digital down convert 40 MHz IF decaying exponentials
Phase II Testing Objectives 3 BPM Test • Test three BPM separated by fixed distance to determine single-shot • Evaluate First Article Prototypes • Complete test matrix to prove compliance to specification
System Layout and Planning Beam X-band receiver LRU
Production Phase • Production of 2 BPMs for LTU 04/07 • Production of 6 BPMs for undulator 04/07 • Production of 9 BPMs for undulator 06/07 • Production of 9 BPMs for undulator 08/07 • Production of 10 BPMs for undulator 10/07 • Spares 12/07
Summary • X-Band Cavity BPM development ongoing • Bolt-together prototype (non-vacuum) complete • ITS prototype testing ongoing • 3 BPM test prototype design enhancements ongoing • Receiver Prototype Development • First Prototype installed in ITS with good results • 3 BPM test prototype design incorporates high/low gain, self-test and final packaging • Data Acquisition and Test • Collaborating with SLAC to use the same ADC as SLAC LINAC BPM upgrade