This document provides an overview of the integration of the Intelligent Mobility Cane subsystem, including customer feedback, risk management, project plan and budget, and lessons learned.
E N D
MSD IISubsystem Integration P15044 – Intelligent Mobility Cane 3/19/2015
Agenda • Customer Feedback & Integration • Subsystem Overview • Subsystem Integration Overview • Risk Management • Project Plan & Budget • Looking Forward- 3 week plans • Peer Reviews & Lessons Learned
Haptic Feedback • ABVI User Testing • Hard to distinguish individual vibrations • Designing motor pulsing to mitigate • Test rig being implemented
Length of Cane • Testing indicated extended length not desirable • Cost • Redesign time
Cost Drivers Even with design changes, we meet the required cost of <$125
Electrical Current State • First Revision boards assembled • All electrical hardware has been debugged • Second Revision boards ordered and shipped (3/18/2015)
Software Current State • All code is written. • Waiting for new board revision for debug. • 4/9/2015 – start debug
Validation Matrix Link to the Validation Matrix in EDGE
3 Week Plans 3 Week Plans
ImagineRIT Obstacle Course Featured Obstacles: 5 ft Overhang 5 ft Wall 6 in Step(s) 6 in Ramp/Drop Off
Planned vs Actual Budget We are on track to be under our budget of $1000.
Lessons Learned • Check test equipment before performing test • Be as critical as necessary during Peer Reviews