1 / 21

VAR WG – 06/16/05 Aleks Mitreski

VAR Testing of G enerators providing Service under Section II of the ISO-NE Tariff (Schedule 2 - VARs). VAR WG – 06/16/05 Aleks Mitreski. Generator VAR Testing. Background of the Program Compensation Eligibility Timeframe Preparation Steps Correct Configuration and Data Collection

Download Presentation

VAR WG – 06/16/05 Aleks Mitreski

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. VAR Testing of Generators providing Service under Section II of the ISO-NE Tariff(Schedule 2 - VARs) VAR WG – 06/16/05 Aleks Mitreski

  2. Generator VAR Testing • Background of the Program • Compensation Eligibility • Timeframe • Preparation Steps • Correct Configuration and Data Collection • Failure to Conduct a Test - What Happens? (Waivers) • Local Control Center (LCC) and ISO-NE Contacts • Supporting Documents

  3. Background Information • Validates basis for generator compensation for Capacity Cost (CC) under Schedule 2 • Program started in August 2001 • VAR testing is only for single point lagging capability • Schedule 2 and the Reactive Supply and Voltage Control from Generation Sources Service Business Procedure state that the VAR demonstration test will include multi-point (MW output) tests of both lagging and leading VAR capability in 2008.

  4. Compensation Eligibility • Generator must be in the ISO-NE Market • Generator must have a valid NX-12D form (OP14) and NX-9B database (OP16) on file with the ISO-NE • VAR compensation requires RC approval • Compensation pursuant to Schedule 2 and the Reactive Supply and Voltage Control from Generation Sources Service Business Procedure

  5. Generator Testing • VAR testing period June 1st – September 15th (On peak hours 07:00 –23:00) • All generators must perform an initial single point full lagging VAR demonstration test • New generators eligible for exemption from a demonstration test, not to exceed two Summer-Seasonal Claimed Capability (S-SCC) Audit periods following the date of commercial operation • After the initial test, the generator must test every 5 years • In the event of overhaul or any other factors potentially impacting the reactive capability of the generator, a new test will be required within 120 days • Starting with 2008, a multi-point (MW output) test of both lagging and leading VAR capability will be required

  6. Generator Testing - Preparation • Generator must submit a completed Reactive Test Request Form to the LCC at least 5 days in advance • Reactive Test Request Form: http://www.iso-ne.com/Generator_VAR_Capability/2%29_Forms/Reactive_Test_Request_%20Form_2004.doc • At discretion of ISO-NE and the LCC, shorter request times may be accepted • Approval/denial of request will be issued 48 hours prior to 00:01 of the day of the test • If denied, an explanation and suggestion for more appropriate timing will be provided

  7. Generator Testing – Preparation • If request approved – the generator must contact the LCC for final permission to ramp VAR output • Voltage dispatch received from the LCC • VAR test requires that generator be at S-SCC output for at least 60 consecutive minutes • Generator obligation to submit offers to the ISO-NE markets that will allow for S-SCC dispatch • Self-Scheduling of generator will help to ensure dispatch to S-SCC for required duration as well as cover market position • Convenient to run VAR test at the same time as S-SCC test

  8. Generator Testing – Data • Even if VAR testing, all dispatch instructions from the LCC must be followed • Following the test, generator completes test form “Reactive Capability Test Data Recording Form” with 5-minute values of generator, step-up transformer and station data • VARs delivered to high side of the generator step-up (GSU) are eligible for compensation • If full S-SCC cannot be sustained for 60-minutes, the test will be canceled • A new testing request and VAR test is required

  9. Generator Testing - Configuration

  10. Generator Testing - Configuration

  11. Generator Testing - Success • Generator must be at the S-SCC MW output for at least 60 consecutive minutes • The average VAR achieved over the test will determine the qualified payment • After completion of testing: • LCC must be contacted • “Reactive Capability Test Data Recording Form” must be submitted no later than 2 days after the completion of the test

  12. Generator Testing – Data Recording Form

  13. Generator Testing - Success • Data reviewed by ISO-NE (EMS data) • Discrepancies discussed with Generator • Revised NX-12D form may be required • Final values are entered by ISO-NE for VAR settlement • Reminder - if any factor impacts reactive capability (e.g., overhaul), generator must perform new VAR test within 120 days

  14. Generator Testing - Waivers • Generators may request a waiver • LCCs or ISO-NE may identify conditions that qualify for a waiver • Evaluation of generator waiver requests will identify cases where a waiver applies: • Non-Dispatchable Base Load Generators • Certain limited-dispatch generators (e.g., Nuclear) are exempt from multi-point lagging and leading tests. • Following initial single point test, will only need only re-demonstrate at a single point maximum lagging and leading capability at five-year intervals. • Contingency Conditions • Certain limited situations in which a generator would not be allowed to conduct a reactive demonstration test at the level that the generator could legitimately deliver because of concerns regarding system reliability.

  15. Generator Testing – Waivers cont. • Small Generators • Small generators that would be very difficult to monitor in real-time (because of limited reactive and voltage metering in the general area) yet are capable of contributing to local voltage support may be exempt from VAR testing.  Eligible Capability will then be based on the data submitted through the NX-12D forms and NX-9B data. • Daily Hydro Facilities • Due to their limited storage capability and dependency on river flow, Daily Hydro Facilities are allowed to achieve the VAR curve data supplied in the NX-12D corresponding with the MW level tested (which doesn’t have to be its S-SCC) but this may cause its NX-12D curve to be adjusted.  • New Generators • Are eligible for exemption from a demonstration test, not to exceed two S-SCC Audit periods following the date of commercial operation

  16. After the Testing Period • The ISO will monitor all requests for a test • After September 15th, ISO will evaluate each Generator’s status in the program. • Generators that satisfied test requirements (through demonstration, historical data or waiver) will be established in the program for five years. • Generators that attempted a test on several occasions, yet through circumstances beyond their control (system conditions or LCC/ISO limitations) were unable to complete a test, will continue to be compensated based on the NX-12D and NX9B data submitted until they demonstrate during the next Audit Season.

  17. Local Control CenterContact Info • CONVEX Transmission Coordinator Tel 860-665-4943 Fax 860-665-6610 • Maine Control Room Supervisor Tel 207-626-9884 Fax 207-621-6522 • New Hampshire System Ops. Cord. Tel 603-634-3586 Fax 603-634-3571 • REMVEC Operations Tel 508-389-2241 Fax 508-389-3910

  18. ISO-NE Contact Info Mailing Address: Email: mvarcaptest@iso-ne.com ISO New England Fax: 413-535-4343 One Sullivan Rd Phone: 413-535-4367 Holyoke, MA 01040 Attn: Aleks Mitreski • Aleks Mitreski (Process): 413-535-4367; amitreski@iso-ne.com • Sima Bykhovskaya (Studies): 413-535-4195; sbykhovskaya@iso-ne.com

  19. Supporting Documents • ISO-NE Open Access Transmission Tariff - Schedule 2. • http://www.iso-ne.com/FERC/filings/tariff/ • Reactive Supply and Voltage Control From Generation Sources Service Business Procedure • http://www.iso-ne.com/Generator_VAR_Capability/1%29_Procedures/Schedule_2_VAR_Billing_Procedure_SMD.doc • Reactive Capability Demonstration Web Site • http://www.iso-ne.com/Generator_VAR_Capability

  20. Summary of VAR Testing • Testing period June 1st – Sept 15th (On peak Hours 07-23) • Single point full lagging capability testing • Must coordinate with Local Control Centers • Submit Testing Request Form at least 5 days in advance • During testing must be at S-SCC for 60 minutes • After testing submit results within 2 days • To receive compensation generator must be approved by the RC • Testing is every 5 years, waivers may be received/applied • A multi point lagging and leading test will start in 2008

  21. Questions / Additional Discussion

More Related