Integrated Capacity Analysis Working Group - June 9, 2016

This is the agenda for the Integrated Capacity Analysis (ICA) Working Group meeting on June 9, 2016. The meeting aims to refine ICA methodologies, authorize demonstration projects, ensure balance and coordination, and facilitate stakeholder engagement.

donalds
Download Presentation

Integrated Capacity Analysis Working Group - June 9, 2016

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Integrated Capacity Analysis Working Group June 9, 2016 9 am – 12 pm CPUC Golden Gate Hearing Room drpwg.org

  2. Agenda 2

  3. ICA Working Group Background • ICA WG PURPOSE- Pursuant to the May 2, 2016, Assigned Commissioner’s Ruling (ACR) in DRP proceeding (R.14-08-013), the Joint Utilities are required to convene the ICA WG to: • Refine Integration Capacity Analysis Methodologies and Requirements • Authorize Demonstration Project A • CPUC Energy Division role • Oversight to ensure balance and achievement of State objective • Coordination with both related CPUC activities and activities in other agencies (CEC, CAISO) • Steward WG agreements into CPUC decisions when necessary • More Than Smart role • Engaged by Joint Utilities to facilitate both the ICA & LBNA working groups. This leverages the previous work of MTS facilitating stakeholder discussions on ICA and LBNA topics. 3

  4. ICA Working Group Schedule To Date • May 2nd, 2016 - Assigned Commissioner Ruling on ICA • May 12th, 2016 – First Joint Utility meeting on ICA and LNBA • May 18th, 2016 – Joint Utility meeting seeking input on (1) use of abstraction analysis or power flow analysis, and (2) level of granularity desired • June 1, 2016 – First in person meeting to get input on: proposed Joint WG Recommendation for Demonstration A; input into ICA Implementation plans; discuss Comparative Analysis • June 9, 2016 (today) – In person meeting to discuss ICA Plans before submittal • June 16, 2016 – Joint Utilities file 3 separate ICA plans to CPUC • July, 2016 – Q2, 2017 – Monthly ICA WG meetings re/ICA implementation • Q4, 2016 – Final Demo A report due • Q4, 2016 – Long-term ICA refinement intermediate status report due • Q2, 2017 – Utilities submit long-term ICA refinement final report due 3

  5. ICA WG Schedule - May 2nd CPUC ruling Short Term: May 2nd–end of Q4 2016 • Update schedule for Demo A Results • Recommend methods for evaluation of hosting capacity for 1) DER bundles or portfolios, responding to CAISO dispatch; and 2) Facilities using smart inverters • Recommend format for ICA maps to be consistent and readable to all CA stakeholders • Evaluate and recommend new methods that may improve computational efficiency of ICA tools and process • Evaluate ORA’s recommendation to require establishment of reference circuits and reference use cases for comparative analyses of Demo Project A results • Establish method for use of customer load data to develop more localized load shapes • Establish definite timelines for future achievement of ICA milestones Long Term: May 2nd-end of Q2 2017 • Suggested topics include, but are not limited to: expansion to single phase feeders; data sharing; interactive ICA maps; market sensitive information; method for reflecting effect of load modifying resources; independent verification of ICA results; quality assurance and control measures • Ongoing discussion in parallel with short term WG activities 3

  6. Proposed schedule for ICA WG topics Ongoing monthly discussion on continued refinement of ICA methodology 3

  7. ICA Working Group Participation • How will the Working Group provide ongoing input into Demo Project A development and ICA methodology? • IOU ongoing solicitation and incorporation of feedback • Stakeholder submitted comments • Consensus recommendations to CPUC • How should Working Group participants continue to stay engaged between monthly meetings? • Do you have comments/suggestions on proposed schedule of monthly ICA WG topics for discussion? Today’s attendance list will be available online at http://www.drpwg.org 3