Linac Coherent Light Source Overview25 January 2005 • Safety • Department of Energy: Validation, Reviews • Experiments • Doing Business • What’s Next • What’s After What’s Next
Consequences • Injured electrician has gone home for re-hab • SLAC Site Office Management Changed • Bob Wunderlich interim SSO Manager • SLAC Site Engineering/Maintenance Dept • Removed from Technical Division • Combined with Experimental Facilities Department; now both are headed by John Wiesend • Wiesend → Steve Williams → J. Dorfan
Consequences • Stanford U. “Blue Ribbon Panel” • Chuck Shank, chair • SLAC Director to organize a “red team” review of entire SLAC safety management system • “Blue Ribbon” review to be completed in ? • SLAC ISM program to be re-validated by DOE in August
Consequences • Accelerator re-start plan • SPEAR goes first • SPEAR re-start plan reviewed by external committee • Linac, PEP-II re-start plan still in preparation • No tolerance for another incident • This should appear explicitly in the RMP
Consequences • Revised shutdown schedule for PEP-II • No shutdown summer 2005 • 1-2 month shutdown winter 2005 • ~6 month shutdown starts July 2006 • Summer 2007 Shutdown- probably- • PEP-II will run through FY2008
Department of Energy • Support for LCLS funding profile is solid • EIR validation letter • Revised conventional construction (1.9) baseline still under review – New findings 25 January • Keep working the original EIR corrective action plan • CD-3A in hand- “go” for long-lead procurements
Department of Energy • BES, Office of Science placing significant emphasis on integration of LCLS into SLAC • 26 January James Decker visit • 7-8 February BES visit • ?? April business planning meeting, Washington • 8-10 June Lehman Review • breakout for lab management • Breakout for LCLS experiments • ?? June On-site review
LCLS Experiments – Major Item of Equipment • Build-out of experiment stations in 6 hutches • A hutch will house more than one station • CD-0, Project planning underway • An SSRL project • Jerry Hastings, SSRL Assistant Director for LCLS Science • John Arthur, MIE Project Director
Efficiencies of Shared Resources for LCLS, MIE LCLS Galayda Reichanadter SSRL Hodgson Hastings Poor Old John Arthur LCLS Endstation Systems XRTOD Experiments MIE
Slower-than-Optimum MIE Funds Profile • 2006 2007 2008 2009 Total $1.5M $1.5M $2.0M >>> >>> >$60M • High Energy Density Physics unlikely to be funded by DOE • Tough to get 2-3 stations on the floor by mid-2009!
Thrust areas: SSRL/LCLS Contact (1) Coherent scattering at G.B. Stephenson* S. Brennan the nanoscale K. Ludwig (2) Pump/probe diffraction K. Gaffney* A. Lindenberg dynamics D. Reis J. Larsson (3) High energy density R. Lee* J. B. Hastings (HED) physics P. Heimann (4) Nano-particle/single J. Hajdu* J. Arthur molecule(non-periodic) J. Miao imaging H. Chapman (5) Atomic, molecular, L. DiMauro* J. B. Hastings and optical science N. Berrah * Team leader
Doing Business • Facts of LCLS Life • LCLS is the most visible project in the Office of Science • It is guaranteed we will be carefully scrutinized • Inspector General • OECM – IER might continue to ∞ • Safety • Be prepared
Doing Business • Major procurements this year • GET THE FORMAL ASPECTS RIGHT • Physics Requirements Documents • Engineering Specifications Documents • Advance Procurement Plans • QA • Vendor surveillance • Acceptance criteria • Documentation of inspections, handling histories • Project-wide standards • Controls • Vacuum • Cabling • etc. • Safety • Job Hazard Analysis • Area Hazard Analysis • Accelerator Safety - - designed-in hazard controls and mitigations
What’s Next • Events Calendar • APS April Meeting 16-19 April Tampa • DESY XFEL Commiss. 17-22 April Zeuthen • PAC2005 16-20 May Knoxville • DESY XFEL Undulators 6-8 June Hamburg • FEL2005 21-26 August Stanford
What’s Next • Review Calendar • FAC TBD – May? • SAC TBD – May? • Lehman 8-10 June • OECM Audit of PMCS – September 2005
What’s Next Undulator hardware Undulator first articles Magnet Measurement Facility Sector 20 alcove Gun Laser Gun Magnets for linac SLC-aware IOC tests Gas attenuator design Damage tests at DESY CD-0, CD-1 for MIE Selection of Construction Mgr
What’s Next • Hires • ES&H Coordinator • QA Coordinator • Database managers • laser group leader • e-beam systems manager • commissioning team leader • ANL Undulator Systems Chief Engineer
What’s After What’s Next • Schedule • Must preserve funds for FY boundary BUT • Acceleration of 2006 procurements considered • Conventional construction – FFTB schedule • Linac Complete by end of 2006-2007 shutdown • Early 2008 FEL commissioning start
George Carlin • We have written a check to DOE with our Mouths… • Time to cash the check
European XFEL Facility – Present Cost Estimate ~ € 1B SLAC linac tunnel Funding: 50% from Germany, 50% from other European countries 2005: 8 Contributing nations have agreed to form a unified design effort 2012: On track to start of the commissioning of the X-ray laser.