110 likes | 123 Views
This session provides an overview of the anticipated programme activity for the replacement of UK Link, including stakeholder engagement, logical analysis, high-level design, detailed design, build, testing, and data cleansing. Please note that the timescales mentioned are indicative and subject to change as the programme progresses.
E N D
UK Link Programme Update to PNUNC June 17th 2013
Introduction • The aim of this session is to provide an overview of the anticipated programme activity for the replacement of UK Link • It should be noted that at present these timescales are indicative and as more information becomes available as the programme progresses formal updates will be provided. 2
Programme Indicative Path:Overview Logical Analysis HLD Detailed Design Cutover and go-live Build & Dev Test System & User Test Design R2 Cutover and go-live Build Test Data Cleansing Stakeholder Engagement Note: assumes a release based approach 3
Indicative Path:Stakeholder Engagement • Stakeholder Engagement Key Deliverables • Identify stakeholders • Understand Stakeholder Expectations • Analyse and Map Stakeholders (Involve / Influence) • Develop, maintain an effective communication plan (Review / Modify) • Increase Stakeholder cooperation and success in delivering overall objectives (Impact of Change, Testing phases) • Reduce the risk of misunderstanding the scope of work Stakeholder Engagement Note: assumes a release based approach 4
Indicative Path:Logical Analysis Logical Analysis • Logical Analysis Key Deliverables • Phase started 25th March 2013 • Develop Logical Process & Data Models for the requirements captured in the BRDs during Project Nexus and known future requirements • Undertake a detailed review of the Non-Functional Requirements. • Define and introduce Competency Centre to support delivery of future changes as an enduring service Note: assumes a release based approach 5
Programme Indicative Path:High Level Design HLD • High Level Design Key Deliverables • High Level Architecture Design, details the high level future state business processes and solution design • Security Architecture and Policies, details at high level the framework to protect all assets • Integration Architecture, details at high level, the integration framework between all systems, both internal to Xoserve and external • Test Strategy & Plan, defines the overall test approach and each test phase with corresponding timelines • Programme Delivery, definition and timescales of the remaining phases and indicative release plan Note: assumes a release based approach 6
Programme Indicative Path:Detailed Design • Detailed Design Key Deliverables • Detailed Architecture Design. • Detailed Security Architecture and Policies • Detailed Integration Architecture • Detailed Test Strategy & Plan, defines the overall test approach and each test phase with corresponding timelines • Programme Delivery, definition and timescales of the remaining phases and detailed release plan • Detailed Data Migration Plan Detailed Design Note: assumes a release based approach 7
Programme Indicative Path:Build Build & Dev Test • Build Key Deliverables • Technical Specification; • Batch Job Configuration; • Installation Guides • Training Content & Materials; • Test scripts • Cutover plan • Service Transition plan Note: assumes a release based approach 8
Programme Indicative Path:Test • Test Key Deliverables • Under take User and System Test • Review test results • Dev Test • System Test • Integration Test • Performance Test • User Acceptance Test • Technical / Operations Test • Industry / Regulatory • Transition handover document Cutover and go-live System & User Test Note: assumes a release based approach 9
Programme Indicative Path:Release 2 • Release 2 Key Deliverables • Same deliverables as Release 1, without High Level Design and potentially shorter timelines. Design R2 Cutover and go-live Build Test Note: assumes a release based approach 10
Programme Indicative Path:Data Cleansing & Migration • Data Cleansing Key Deliverables • Data Cleansing Strategy • Data Quality Metrics • Data Mapping Data Cleansing Note: assumes a release based approach 11