Overview. The ProcessMilestonesSource SelectionAssistanceProcurement IntegrityConclusionQuestions. . . . . . . . SAF/IEI. SPONSORING . MAJCOM. AF/ILE. AFCESA/AFCEE. PROJECT . BASES. . OVERSIGHT. DIRECTION. DIRECTION. TECH SUPPORT. ROLES/RESPONSIBILITIES. . . MAJCOMs/BASESIdentify NeedsImplement ProgramFollow Policy, Criteria, ProceduresFeedbackAF/ILEXAdvocacy, Policy/Program OversightGuidance /InformationAFCESATechnical Support Contract SupportAFCEEEnvironmen30755
E N D
1. AIR FORCE SPACE COMMAND UTILITY PRIVATIZATION Introduction to
Federal Contracting
For Utilities Privatization (UP)
2. Overview
The Process
Milestones
Source Selection
Assistance
Procurement Integrity
Conclusion
Questions
3. ROLES & RESPONSIBILITIES:
- INSTALLATION - pursue potential, identify, justify, assess
- MAJCOMs - primary execution responsibility; develop, evaluate and submit projects;
assess impact
- USAF/ILE - program management, policy development, funds advocacy, and guidance
- SAF/IEI - approval authority for transfers, Congressional notification
- AFCESA - provide contract/technical support to analysis of privatization candidates
- AFCEE - provide tech support to environmental requirements including baseline survey
- DESC - MOU for contracting support for Texas Regional Demo--potentially moreROLES & RESPONSIBILITIES:
- INSTALLATION - pursue potential, identify, justify, assess
- MAJCOMs - primary execution responsibility; develop, evaluate and submit projects;
assess impact
- USAF/ILE - program management, policy development, funds advocacy, and guidance
- SAF/IEI - approval authority for transfers, Congressional notification
- AFCESA - provide contract/technical support to analysis of privatization candidates
- AFCEE - provide tech support to environmental requirements including baseline survey
- DESC - MOU for contracting support for Texas Regional Demo--potentially more
8. This is the roadmap which an acquisition follows in the source selection process for a negotiated best value contract. I will discuss each of these steps in more detail.
Before starting this, however, I should first highlight some of the recent changes which affect this process.
AFPSC developed streamlined processes using single documents for all AFSPC sites including
Request for Information
Acquisition Strategy Panel
Acquisition Plan
Source Selection Plan
Core group of SSET and PRAG participants to minimize learning “ramp-up” time plus augmentees from bases
Helpful if same base personnel are involved through entire process
Using Median Source Selection Procedures
This is the roadmap which an acquisition follows in the source selection process for a negotiated best value contract. I will discuss each of these steps in more detail.
Before starting this, however, I should first highlight some of the recent changes which affect this process.
AFPSC developed streamlined processes using single documents for all AFSPC sites including
Request for Information
Acquisition Strategy Panel
Acquisition Plan
Source Selection Plan
Core group of SSET and PRAG participants to minimize learning “ramp-up” time plus augmentees from bases
Helpful if same base personnel are involved through entire process
Using Median Source Selection Procedures
9. Source Selection Organization--AFSPC A typical source selection is organized similar to this slide. The ultimate decision maker is the source selection authority; the single individual empowered to make the final selection. He is supported by a source selection advisory committee, a matrixed body of relatively high ranked experts who will oversee the process and prepare its findings for the SSA. The Source Selection EvaluationTeam is the matrixed body that does the real nuts and bolts evaluations of the proposals. It is broken down into functional specialty areas that look at the key discriminating factor and subfactors, cost and risk. The number of members is based on the type of acquisition and need for support. Advisors may augment the core team on an ad hoc basis.
Wing (Base) Participation after RFP closes:
Performance Risk Assessment Group (PRAG)
Wing Representative to Command the week prior to Source Selection Evaluation Team (SSET); Training
SSET Initial
Wing Representatives to Command for initial evaluation and discussions
Initial SSET Begins
SSET Discussions continue as needed
SSET Final
Wing Representative to Command
Final SSET Begins
Source Selection Advisory Council (SSAC) Representation
AFSPC and Wing Representatives
Wing CE participate in
Evaluating technical proposals and past performance information of offerors
Writing evaluation assessments and evaluation notices
Discussions with offerors
Provide data for SSET report
Provide data for Decision slides
Debriefings to offerors
Wing FM (Finance) will
Certify the Government Cost Estimate
Must understand the Economic Analysis Model
Work with AFSPC/FM on POM for contract costs beyond initial award and transition
Wing JA (Legal) will provide to AFSPC JA:
Base specific information regarding water, wastewater, natural gas, and electricity issues
Federal/state/local environmental issues
Provide advice/assistance during process where requested
A typical source selection is organized similar to this slide. The ultimate decision maker is the source selection authority; the single individual empowered to make the final selection. He is supported by a source selection advisory committee, a matrixed body of relatively high ranked experts who will oversee the process and prepare its findings for the SSA. The Source Selection EvaluationTeam is the matrixed body that does the real nuts and bolts evaluations of the proposals. It is broken down into functional specialty areas that look at the key discriminating factor and subfactors, cost and risk. The number of members is based on the type of acquisition and need for support. Advisors may augment the core team on an ad hoc basis.
Wing (Base) Participation after RFP closes:
Performance Risk Assessment Group (PRAG)
Wing Representative to Command the week prior to Source Selection Evaluation Team (SSET); Training
SSET Initial
Wing Representatives to Command for initial evaluation and discussions
Initial SSET Begins
SSET Discussions continue as needed
SSET Final
Wing Representative to Command
Final SSET Begins
Source Selection Advisory Council (SSAC) Representation
AFSPC and Wing Representatives
Wing CE participate in
Evaluating technical proposals and past performance information of offerors
Writing evaluation assessments and evaluation notices
Discussions with offerors
Provide data for SSET report
Provide data for Decision slides
Debriefings to offerors
Wing FM (Finance) will
Certify the Government Cost Estimate
Must understand the Economic Analysis Model
Work with AFSPC/FM on POM for contract costs beyond initial award and transition
Wing JA (Legal) will provide to AFSPC JA:
Base specific information regarding water, wastewater, natural gas, and electricity issues
Federal/state/local environmental issues
Provide advice/assistance during process where requested
13. Assistance Sources for Assistance:
Air Force Source Selection Policy
http://www.safaq.hq.af.mil/contracting/index.html
Air Force Civil Engineering Support Agency
http://www.afcesa.af.mil
Air Force Federal Acquisition Regulation (FAR) site
http://farsite.hill.af.mil (All Clauses)
http://www.arnet.gov/far (FAR Clauses only)
14. 10 USC 2688 – Congress wants the best value
What is best value?
Do we have separate FAR authority for Utilities Privatization?
Could we do it for less than 50 years?
What are the 3 bid amounts?
3 bid amounts
1 – monthly credit for purchase price, amortizing over a number of months at the proposed annual %
2- fixed monthly charge: cost of providing services, O&M, overhead
3 – monthly credit to gov for non-performance: routine, urgents, emergency
when contractor is unable to perform as required.
Can change for items beyond contractor control: fuel adjustments
10 USC 2688 – Congress wants the best value
What is best value?
Do we have separate FAR authority for Utilities Privatization?
Could we do it for less than 50 years?
What are the 3 bid amounts?
3 bid amounts
1 – monthly credit for purchase price, amortizing over a number of months at the proposed annual %
2- fixed monthly charge: cost of providing services, O&M, overhead
3 – monthly credit to gov for non-performance: routine, urgents, emergency
when contractor is unable to perform as required.
Can change for items beyond contractor control: fuel adjustments
15. Conclusion DoD emphasis on AFSPC fully evaluating UP systems for privatization
AFSPC doing everything possible to minimize workload on Wing (Base) personnel
Success is defined as SSA decision for Competitive RFPs by 30 Sep 05
16. Questions
Questions?
18. Milestones Key Dates are established by AF/ILEXO and AFCESA for each specific location and include dates:
Kickoff Meeting (Begin RFP) briefings include:
Wing senior leadership on entire UP program;
Wing Civil Engineers, Finance, Legal, and Contracting briefed on entire source selection process and needed support
Issue RFPs to Industry
Site Visit, Pre-Proposal Conference, One-On-One Discussions
Questions from offerors and Government answers posted to FedBizOpps
Close RFPs (RFP deadline dates for proposal submission)
Source Selection Authority (SSA) Decisions briefed to AF UP Executive Steering Group
21. Mission Capability Subfactor Rating Six Subfactors:
Service Interruption/Contingency
Quality Management
Capital Upgrades and
Renewals & Replacements
Operational Transition
Financial Capability
Small Business
22. Proposal Risk AFFARS 5315.305 (a)(3)(ii) Identification and assessment of Risk Associated with an offeror’s proposal approach
Rated as:
23. Past Performance Assessment of offeror’s present and past work record
24. The goal of the cost evaluation is to arrive at an evaluated price for each offeror. Whether the contract type will be fixed price or cost reimbursement, the evaluated price is always assessed to ensure it is reasonable. Generally, this is a go no-go factor for purposes of award-not a comparative selection factor.
Cost realism is essentially a risk assessment tool use to assess an offeror's ability to perform the contract at the offered price, given an offeror's unique approach and methods of performance. The structured review of cost ensures they are consistent with the technical approach and reflect good understanding of the complexity of the effort. The aim is to ensure costs are neither greatly exaggerated nor understated and that we don't run the risk of a large cost overrun.
Evaluating cost realism also helps develop the most probable cost estimate which adjusts proposed costs upward or downward to reflect the probable ultimate cost to the Government.The goal of the cost evaluation is to arrive at an evaluated price for each offeror. Whether the contract type will be fixed price or cost reimbursement, the evaluated price is always assessed to ensure it is reasonable. Generally, this is a go no-go factor for purposes of award-not a comparative selection factor.
Cost realism is essentially a risk assessment tool use to assess an offeror's ability to perform the contract at the offered price, given an offeror's unique approach and methods of performance. The structured review of cost ensures they are consistent with the technical approach and reflect good understanding of the complexity of the effort. The aim is to ensure costs are neither greatly exaggerated nor understated and that we don't run the risk of a large cost overrun.
Evaluating cost realism also helps develop the most probable cost estimate which adjusts proposed costs upward or downward to reflect the probable ultimate cost to the Government.
25. Discussions Negotiations conducted in a competitive environment after determination of competitive range
Objective: To maximize the Government’s ability to get the best value; to fully understand what was proposed; and share cost comparison with GCE
Evaluation Notices are issued to offerors in competitive range
Means to clarify and discuss proposals
Change Pages to Impacted Proposal Data Requested
Once discussions concluded, complete file must be reviewed by MAJCOM Contracting Personnel and Clearance granted prior to requesting Final Proposal Revisions
Reference: FAR 15.306(d)
Deficiency requests are issued when a requirement is not met. The effect of the deficiency should be documented in the narrative. (BB-306(a))
There are two type of CRs, significant CRs and Minor CRs. (BB-307) Minor clarifications are just that. They give the offeror the opportunity to correct minor informality or irregularities such as clerical mistakes. MCRs do not constitute discussion and the offeror does not have the opportunity to revise its proposal.
SCRs are truly clarifications. These are used when there are areas of the proposal where there is not enough information to determine if the standards have been met or where there are contradictions in the proposal needing clarification. SCRs constitute discussions.
MCRs can be sent prior to the competitive range subject to legal concurrence. (BB-307(a)(2)) However, this should only be done it award without discussion is anticipated. (AFSPC BB-307(a))Deficiency requests are issued when a requirement is not met. The effect of the deficiency should be documented in the narrative. (BB-306(a))
There are two type of CRs, significant CRs and Minor CRs. (BB-307) Minor clarifications are just that. They give the offeror the opportunity to correct minor informality or irregularities such as clerical mistakes. MCRs do not constitute discussion and the offeror does not have the opportunity to revise its proposal.
SCRs are truly clarifications. These are used when there are areas of the proposal where there is not enough information to determine if the standards have been met or where there are contradictions in the proposal needing clarification. SCRs constitute discussions.
MCRs can be sent prior to the competitive range subject to legal concurrence. (BB-307(a)(2)) However, this should only be done it award without discussion is anticipated. (AFSPC BB-307(a))
26. Awardability Other aspects of the proposal
Proposed Terms and Conditions
Pre-Award Surveys
Required Certifications
Responsibility Determination (FAR 9)
Must Be Below Government Cost Estimate (GCE) IAW 10 U.S.C. 2688