ROB & MCM production status and planning. David Emschermann Physikalisches Institut Universität Heidelberg. David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005. ROBs and MCMs. 15. 14. 13. 12. 11. 10. 09. 08. 07. 06. 05. 04. 16. 03. 02.
E N D
ROB & MCM production status and planning David Emschermann Physikalisches Institut Universität Heidelberg David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
ROBs and MCMs 15 14 13 12 11 10 09 08 07 06 05 04 16 03 02 01 00 17-18 MCMs are used per ROB type David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
ROB types – C1 chambers FIBRE 4A 3A 1A 1A HCM + OASE 4B 3B 2B 1B HCM + OASE DCS FIBRE there are 7 different ROB types in total David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
ROB types – C0 chambers FIBRE 3A 1A 1A HCM + OASE 3B 2B 1B HCM + OASE DCS FIBRE 5 out of 7 ROB types used on small ROCs David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
ROB PCB preseries production • Readout Boards (7 types total, 50pc each): • Type 1A – submitted, back 11/05 • Type 1B – delivered this week • Type 2B - delivered • Type 3A – designed, back 12/05 • Type 3B – designed, back 12/05 • Type 4A – submitted, back 11/05 • Type 4B – submitted, back 11/05 • Aim to have all 7 ROB types (at least • 1 per type) equipped till Xmas 2005. David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
ROB production numbers Readout Boards for 60% TRD : Type 1A 1B 2B 3A 3B 4A 4B MCMs 17 17 17 18 18 17 17 PCBs 680 340 340 340 340 235 235 Σ2510 Equipping 600 300 300 300 300 230 230 Σ 2260 MCMs used for equipping : Σ 39020 David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
MCM production • MCMs : • For 60% TRD we need ~40000 MCMs • => @ rate of 3000 MCMs/month= 13 months • => @ rate of 2000 MCMs/month= 20 months • Need 5000 MCMs till end of 2005 • Start of stable MCM production scheduled • for November 2005 (at latest) • Continuously need 2100 MCMs per month • for equipping in the company • MCM series production rate still unknown !! David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
ROB status • ROBs for first 2 layers are made in KA • ROBs for layers 2-5 done by company • Preseries equipping of ROBs starting now • in two companies (10 ROBs each) • => ROBs will return early December • equipping of ROBs for layers 2-5 will • start late December David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
ROB planning • before starting the ROB PCB series • production, need a 2 layer test in SM01 • (best case : GO by end of Feb 2006) • start integration of SM02 and switch • integration site to MS in June/July 2006 • at production rate of 2100 MCMs/month • 1+12 lots for ROB equipping necessary • => finish by June 2007 David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005
Cable boards cheaper offer (for 100% TRD) has arrived David Emschermann Intl. Workshop TRD Present & Future – Cheile Gradistei – 27/09/2005