1 / 33

LCLS Cavity BPM Status and Testing

LCLS Cavity BPM Status and Testing. In-Tunnel Electronics Block Diagram. Cavity BPM Development. R&D phase completed Testing phase II completed Entering production phase. 3-BPM Test First Article. Cold Test 1st Generation. ITS Test 2nd Generation. X-Band Cavity BPM Development.

eitan
Download Presentation

LCLS Cavity BPM Status and Testing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Cavity BPM Status and Testing

  2. In-Tunnel Electronics Block Diagram

  3. Cavity BPM Development • R&D phase completed • Testing phase II completed • Entering production phase 3-BPM Test First Article Cold Test 1st Generation ITS Test 2nd Generation

  4. X-Band Cavity BPM Development • Five X-Band Cavity BPM built and tested • Two qualified vendors for machined parts • Brazing procedure optimized to preserve tune • Tuning and testing procedures generated

  5. Port 1 Port 4 Port 2 Y-Port Port 3 Monopole mode X-Port Vertical dipole mode BPM Simulations • Cavity BPMs simulated in Microwave Studio, HFSS and Mafia • Test data indicates good agreement between simulated model and measured BPMs

  6. Prototype BPMs for 3-BPM test • 4 BPMs built and tested to support 3-BPM testing • Design and technology mature

  7. Cold Test After Brazing and Tuning

  8. New End Cap • End-cap design mechanically strengthen • Can retune once flange is installed • Tuning pins are protected against accidental mistuning • New end-cap designed and tested • Vacuum flange test prototype pending

  9. Cavity BPM Production Status • Cavity BPM machining contracts placed with parts expected 11/27/07 • Two vendors will provide a single machined First Article BPM for evaluation • Vacuum window first lot delivery 11/12/07 • Vendor for brazing BPM pending contract award

  10. Receiver Electronics Development • R&D phase complete • Test fixtures developed • Entering production phase

  11. Receiver Development • X-Band down-converter developed from existing Miteq product • Modified to meet LCLS requirements • 3 channel receiver with common LO • 4 first article packaged receivers delivered and presently being tested

  12. Prototype Receiver Specification

  13. X-Band Receiver Chassis • Line Replaceable Unit (LRU) design • Local status interface indicators for power, operational mode, gain range, self-test • Integral heat sink and EMI chassis design

  14. Receiver Production Status • Drawings updated and released • Specifications generated on receiver, local oscillation and filters • Vendor selection same as 3-BPM first article • Presently quoting production quantities

  15. Comprehensive BPM Test Program • Non-Vacuum Single BPM cold test unit complete 04/06 • (Phase I) test in APS Injector Test Stand complete 09/06 • (Phase II) 3-BPM test in APS LEUTL • Completed test matrix to prove compliance to specification • Production phase started

  16. 3-BPM Test at APS LEUTL • 2-axis translation stage installed and tested provide sub-micron controllable horizontal and vertical motion • Multiple experiments conducted to verify operation

  17. Test Parameters • Beam Energy – 400 MeV • Beam Charge/pulse – 0.2 to 0.5 nC • Beam Repetition Rate – 6 Hz • Beam Pulse Width – 2 ps FWTM (uncompressed) • Diagnostics: • LEUTL current monitor • Flags upstream and downstream of test setup • Quad doublet focusing/steering upstream of test setup

  18. 4 mm Wide Scan Data without removing beam motion 0.2 nC

  19. Single-Shot Resolution Test Procedure • Use calibration to get a list of horizontal and vertical positions for each BPM • Can do Model Independent Analysis (MIA) or Least Squares Analysis (LSA) • Predict position at middle bpm (BPM 2) using horizontal and vertical positions at BPMs 1 and 3. • Histogram the residuals for BPM 2 and standard deviation is the resolution

  20. Histogram residuals for BPM 2 Courtesy Nick Sereno

  21. 3-BPM Test Apparent Y resolution sY = 270 nm Courtesy Steve Smith

  22. 3-BPM Test Apparent X resolution sx = 360 nm Courtesy Steve Smith

  23. 1 Hour Stability Measurement Courtesy Nick Sereno

  24. Long Term Electronics Stability Testing

  25. LTU and Undulator BPM System Conformance Table

  26. LCLS Three-BPM Test Conclusions • Resolution spec met • Long term drift spec for 1 hour spec met • Gain stability spec met • 1 hour temperature stability spec met • 24 hour temperature stability spec met electronics with simulated beam

  27. Undulator System Layout Beam X-band receiver LRU

  28. Undulator System Layout

  29. LTU System Layout

  30. Deliverables per BPM • 1 Cavity BPM assembly • 1 X-band receiver • 3 Waveguides and 2 loads with assembly hardware • 1 Receiver mounting hardware assembly • 1 BPM mounting stage • Bellows and finger inserts

  31. Production Milestones • Production of 2 BPMs for LTU 01/08 • Production of 6 BPMs for undulator 02/08 • Production of 10 BPMs for undulator 03/08 • Production of 11 BPMs for undulator 04/08 • Production of 7 BPMs for undulator 05/08 • Spares 4 BPMs 05/08 • 40 sets of Electronics 07/08

  32. Summary • X-Band Cavity BPM • Development phase complete • Production procurement in place • First machined production units expected in November • Receiver Electronics • 4 First article prototypes assembled and tested with good results • 3-BPM testing prototypes incorporate receiver, local oscillator and filter first article packaging • Production procurement ongoing • Test Qualification • Successful collaborative effort testing and qualifying BPM system • Qualified system with the same ADC (PAD) as SLAC LINAC BPM upgrade to minimize risk of integration

  33. Production Risks • New End Cap design • New tuning scheme • Window plating problem • Unexpected integration problem • Unexpected vendor problem

More Related