Progress and Plan for Superconducting RF Cavity. RF Group. Progress in Last Year. Transport two SC cavity modules and couplers from harbor to IHEP by air-suspended truck Leak check after transportation (instructed by Prof. Mitsunobu, MELCO send a Supervisor to check all of things)
E N D
Progress in Last Year • Transport two SC cavity modules and couplers from harbor to IHEP by air-suspended truck • Leak check after transportation (instructed by Prof. Mitsunobu, MELCO send a Supervisor to check all of things) • Evacuate niobium cavity cell and insulation vacuum vessel, high pressure rising up of helium vessel and nitrogen cooling channel. • Do leak test for niobium cavity cell and insulation vacuum vessel. • Prepare clean work environment • Design and construct clean room of class 10’000 for cavity assembly in RF hall of building six. • Design and construct clean booth of class 100 for HOM damper assembly. • Design and construct clean cap of class 100 for coupler assembly.
Progress … con’t (1) • Assembly of beam taper, RF bellow, gate valve and ion pump, as well as vacuum gauge and mass analyzer together. It include two SBP and two LBP module • Ultrasonic washing, ultrapure water rinsing for each beam taper. • Connected all components on to the beam taper. • Leak test and high temperature baking. • HOM damper baking (Prof. Furuya, a S.V from MELCO) • Ferrite surface check. (There exist a remarkable cracking on the ferrite of the SBP2 HOM damper, KEK borrowed their spare one to us via Melco) • Connect HOM damper on the beam taper. • Baked four HOM damper by heated cycle water around 45 Celsius degree for two months.
Progress … con’t (2) • Assembly of the No.2 SCC module (Prof. Mitsunobu and Furuya, a S.V from MELCO) • Slow leak cavity, coupler and HOM damper in sequence. • Mount coupler on the cavity module. • Connect SBP and LBP HOM damper on to the both side of cavity module separately. • Evacuate whole module and do leak test. • Ion pump baking. • Move the No.2 SCC module to the horizontal test room • Preparation for final performance test (Furuya, a S.V from MELCO) • Locate and adjust module to the right site in test room. • High power waveguide connection. • Connect cryogenic transfer line and safety valve, some modification will be done. • Test the cooling air and water for doorknob and coupler. • …
Plan for next • 2006/4/26~29. Assemble the No.1 SCC module. After assembly, it will be stored in the clean room of building 6 (Prof. Mitsunobu, a S.V from MELCO) • 2006/4/30~5/2. Room temperature aging for the No.2 SCC coupler (Prof. Furuya, a S.V from MELCO) • 2006/5/8~5/31. Performance test for the No.2 SCC (Prof. Furuya, a S.V from MELCO) • Cooling down. • Coupler aging at cold stage. • Performance test (Q0~Eacc, Emax, static loss, tuning range, Qext for the coupler port and etc.) • Warm up.
Plan … Con’t • 2006/6/1~8/31. Tunnel installation for the No.2 SCC (Prof. Mitsunobu a S.V from MELCO) • Move to tunnel, locate and align this module • connect both side gate valve with vacuum chamber. • Prepare and test for LLRF, Interlock, WG, Transfer line, Cooling water, Gas line for G.V, etc. • 2006/6/7. Move the No.1 SCC to the horizontal test room • 2006/6/8~7/7. Preparation for performance test for the No.1 SCC • 2006/7/8~7/31. Horizontal test for the No.1 SCC (Prof. Mitsunobu a S.V from MELCO) • 2006/8/1~8/31. Tunnel installation for the No.1 SCC • 2006/9/1~9/24. RF co-adjustment and signal check with other system • 2006/9/25~… Beam commissioning
Assembly of beam taper, RF bellow, gate valve, ion pump, vacuum gauge and mass analyzer
Request … • Ask vacuum group to fabricate a section of substitution beam pipe for SC Cavity module. • Set a quick valve to isolate linac and storage ring in emergency to protect the SC cavity from a severe vacuum leak. • Prepare some spare key components and one whole spare cavity module. >>>>THANKS<<<<<