130 likes | 317 Views
115kV Substation Design EE 491Spring 2013. Jane Peters. Matt Murphy. Jared Jasper. Riley Groves. Muzi Li. Setting the Stage. Sponsor: Burns and McDonnell Adviser: Dr. Ajjarapu Clarifications Educational purposes only Modified project plan. Project Description. What?
E N D
115kV Substation DesignEE 491Spring 2013 Jane Peters Matt Murphy Jared Jasper Riley Groves Muzi Li
Setting the Stage • Sponsor: Burns and McDonnell • Adviser: Dr. Ajjarapu • Clarifications • Educational purposes only • Modified project plan
Project Description • What? 115kV substation (switchyard) • Where? Hypothetical location on Iowa State campus • Why? To accommodate a hypothetical new wind farm • When? Immediately (utilizing tried and true current tech) • How? Act as a contract team
Strategy Development • Project plan document • Design document • GANNT Chart • WBS (Work Breakdown Structure) • Legend of symbols • Bill of materials These materials are provided on our website at: http://seniord.ece.iastate.edu/dec1303/index.html
Requirements • Design services • Layout will allow for future expansion • 125 Volt Station Battery supply for station service outage • Fiber-Optics communication between substations • The substation be designed with Iowa weather in mind • Safety • Clearance for emergency vehicles • Clearance for removal of defective parts • Ground grid capable of handling a fault • Follow industry and company standards
Deliverables • One-line diagram • Three-line diagram • Physical campus layout • Foundation layout • Grounding grid layout • Bus and insulator sizing • Component raceway • Service station transformer design • Control house layout • Control systems • Relay wiring • 125VDC battery design ADVISER:Role within system description
Constraints & Risks Project Constraints Project Risks Hierarchy of development dependency Learning curve Design validation • Burns and McDonnell expectations • Standards • Hierarchy of development dependency Solution: Design reviews
Project Resources • Software Tools • AutoCAD • WinIGS • Design Resources • Burns and McDonnell design team • Industry design standards • External Reference material
Team Breakdown • Jane Peters (Team Leader) • project documents, one-line, control building, three-line, section cuts, relay wiring • Jared Jasper (Team Webmaster) • website maintenance, site design, grounding layout, section cuts • Riley Groves (Communications Coordinator) • one-line, three-line, client communications, raceway, grounding layout, relay wiring • Matt Murphy (Grounding Expert) • one-line, three-line, raceway, grounding, control building, bus and insulator sizing • Muzi Li (Layout Expert) • foundation design, grounding layout, site design, bus and insulator sizing
Project Verification • Campus Resources • Dr. Ajjarapu • Dr. Christy • Weekly progress review meetings • Burns and McDonnell Design Team • Bi-monthly design review meetings
Current Status Implementation Researched Project Plan Design Document GANNT Chart WBS Symbology Software packages AutoCAD WinIGS • One-line: COMPLETEReviewed by Burns and McDonnell • Physical Campus Layout:IN PROGRESS • Seeking design guidance • Referencing design guides
Acknowledgements In conclusion, we would like to extend a, “thank you”, to the following resources for their help throughout this project: • Brad Jensen and Nathan Schares, Burns and McDonnell • Dr. Ajjarapu, Dr. Christy and Jason Boyd, Iowa State University • P. Meliopoulos, Georgia Institute of Technology
One Line Diagram One Line Diagram