Implementation-Introduction. Field Season Strategic Planning Logistics—Terry Hannaford Drilling—Alan Elcheikh, Jeff Cherwinka Installation---Tom Ham Counting House Operations Liaison---NSF, RPSC Training of Seasonal Drillers, Installers Training Platforms—PSL (Madison).
E N D
Implementation-Introduction • Field Season Strategic Planning • Logistics—Terry Hannaford • Drilling—Alan Elcheikh, Jeff Cherwinka • Installation---Tom Ham • Counting House • Operations Liaison---NSF, RPSC • Training of Seasonal Drillers, Installers • Training Platforms—PSL (Madison) Mar 19-23, 2005 Berkeley
Drill Improvements2005-06—PSL Work Plan • Plans for getting there Issues People Resources Testing and training • Organization • Schedule • Stay focused on goals Mar 19-23, 2005 Berkeley
Goals for 2005-2006 • Set up as early as possible up to Dec 10 • 7 week drill/deploy period (Dec11, Jan 28) • Target drill speed 48 hrs/hole, including firn • Target deploy speed 24 hrs/hole • Use both towers to leapfrog • 2 strings per week • Drill and deploy 10-12 strings Mar 19-23, 2005 Berkeley
Drill performance issues • Speed limitations (deep drill and firn) • Second tower (shipped) • New crescent • Drill control software • Set up and hole-to-hole move • Fuel delivery systems • Generators Mar 19-23, 2005 Berkeley
Drill reliability issues • Motor drives and controls • Drill supply hose • Flow, temperature and pressures sensors • Heaters • Condensate pumps • E-stop false events • Weight stack • Load cells • Communication networks • Reels and reel brakes Mar 19-23, 2005 Berkeley
Now: Alan Elcheikh Jeff Cherwinka Terry Matt Mark Thoma Lee Greenler Brian Pechan Farshid Feyzi Jack Ambuel Ted Shultz Chuck Rentmeesters Harold Mattison Carl Baumann Phil Robl Robin Bolsey Dave Pernic Alan Rogers Dave Scott Jim Koehler Terry Hannaford Tom Ham Soon Dennis Duling New programmer Drillers Outside help Ice-water interface modeling UNICO solutions review Software assessment Bob Morse’s group Newt Ganugapati Varun Gopalakrishna Anupam Singh Personnel Students: • Peter Hoeft • Scott Haman • Terry Benson • Brian White • Aaron Kurth Mar 19-23, 2005 Berkeley
Resources • Full access to PSL shop and staff • EHWD test area is still available • EHWD test equipment • 250 ft deep hole for hose test Mar 19-23, 2005 Berkeley
Testing and Training • Setting up software development and testing facility at PSL • Setting up heater, pump, control and sensor facility at PSL • Set up communication network for above • Will use above for drill and repair training for drill crew • May move to MDS style unit in future Mar 19-23, 2005 Berkeley
Organization Build teams based on focus areas (first person leads team) 1. Drives, UNICOs, Motors: MT, TS, PR, TM (consultant) 2. E-stop, Network, Comm: TM, HM, PR, MT 3. Heaters, Condensate, Fuel, Switches & Sensors: JC, RB, CB, DD 4. Pumps, Sensors: BP, JC, RB 5. Software, Operations (simulator): HM, CR, JA, TS, AE, VG,AS, new hire,drillers 6. Speed Limit, Thermal, Dynamics: LG, JC, RM, TS,NG (consultant) 7. Drill Head, Weights, Nozzle, Sensors: JA, BP, LG, MT,DP 8. Procedures (SOP), Set Up: AE, RB, T Ham 9. Reels: BP, LG, JC,DP,CB,PR 10. Cables: PR,TM,JA 11. Hose, TOS, Crescent: JC, BP, AR,TB 12. Firn Drill: LG, DP,JC,AK 13. Training/testing: FF,RB,THam,JC,AE,drillers 14. Documents, Drawings: AR,TM,PR Mar 19-23, 2005 Berkeley
Schedule • We have started work already • Must ship all items so they get to SP when it opens • Organize shipments so parts are easily found • We have about 6 months--must be very careful on what we do Mar 19-23, 2005 Berkeley
Stay focused on goals • Priorities: • Thing we must do 1 • Things we should do 2 • Things that would be nice 3 • Eliminate dependencies among tasks • Keep an eye on how long it takes to do here • Keep another eye on how long it takes to implement at the pole • Keep both eyes on drilling 12 holes Mar 19-23, 2005 Berkeley
Drill Logging and Analysis Mar 19-23, 2005 Berkeley
Implementation--Introduction • Layout-surveying • Pilot holes—4” coring drill • Firn Drill---down to 60 meters—water pools • HW Drilling—straightness, depth, logging • String Deployment—depth, location, logging • Freeze-In—4-5 day monitoring-Counting House • Data Management—drillers, deployers • Off-line—real-time analysis, Pole, Madison Mar 19-23, 2005 Berkeley
Drilling Data • Drill Operations: depth, calipers, theta, vital parameters • Data updates at rate of 4 Hz (250 ms). • Data-Bridge—between drill net and SP-net. With updates every 5 minutes—1200 updates • Drill Monitoring: Off-line, Real-Time • Pole Monitoring---full analysis and logging • Madison Monitoring—full analysis and logging as the satellite permits. Mar 19-23, 2005 Berkeley
Off-line Real-Time AnalysisAt South Pole and Madison • Tension (cable and drill-head) • Depth (from winch payout and pressure) • Hole Diameter—Calipers • Drill-Angle—Straightness, Theta • Logging X-Y or “birds-eye” plots Mar 19-23, 2005 Berkeley
Mar 19-23, 2005 Berkeley
Hole # 1 ( 21) • First attempt at hole drilling Mar 19-23, 2005 Berkeley
HOLE 1 Mar 19-23, 2005 Berkeley
HOLE 1 Mar 19-23, 2005 Berkeley
HOLE 1 Mar 19-23, 2005 Berkeley
HOLE 1 Mar 19-23, 2005 Berkeley
Hole #1 Summary • 22 hrs—large tilt angle, buried drill? • 27-33 hrs—buoyant drill, buried drill, lost nozzle? • 40 hrs—buried drill, lost part of weights • 43 hrs—lost additional part of weight-stack • 45 hours buried drill • 33-50 hours, drill difficult to steer. • Difficulty controlling hole diameter Mar 19-23, 2005 Berkeley
Hole #2 (21-A) • Move tower by about 8 meters • Make 2nd attempt at hole drilling Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
Hole #2 Summary • More even drilling rate • Better control of drill straightness • Straightness—diameter correlation? Mar 19-23, 2005 Berkeley
Drill Oscillations • Lee Greenler’s talk Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
Drill Oscillations • Demonstrates need for fast-response instruments like drill load-cells, and cable/winch load-cells. • Possible need for additional instruments like accelerometers to actually determine drillhead’s instantaneous velocity and position. Mar 19-23, 2005 Berkeley
Hole #2 Logging –X-Y Plot Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
HOLE 2 Mar 19-23, 2005 Berkeley
Deployment • Kurt Woschnagg’s talk Mar 19-23, 2005 Berkeley
Mar 19-23, 2005 Berkeley