An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FIRE Vacuum Vessel and Remote Handling Overview B. Nelson, T. Burgess, T. Brown, D. Driemeyer, H-M Fan, K. Freudenberg, G. Jones, C. Kessel, P. Ryan, M. Sawan, M. Ulrickson, D. Strickler, D. Williamson FIRE Physics Validation Review March 31, 2004

  2. Presentation Outline • Vacuum Vessel • Design requirements • Design concept and features • Analysis to date • Status and summary • Remote Handling • Maintenance Approach & Component Classification • In-Vessel Transporter • Component Replacement Time Estimates • Balance of RH Equipment • Design and analysis are consistent with pre-conceptual phase, but demonstrate basic feasibility of concepts FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  3. FIRE vacuum vessel FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  4. Vacuum vessel functions • Plasma vacuum environment • Primary tritium confinement boundary • Support for in-vessel components • Radiation shielding • Aid in plasma stabilization • conducting shell • internal control coils • Maximum access for heating/diagnostics FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  5. Vacuum vessel parameters • Configuration: Double wall torus • Shielding water + steel with 60% packing factor • Volume of torus interior 53 m^3 • Surface Area of torus interior 112 m^2 • Facesheet thickness 15 mm • Rib thickness 15 - 30 mm • Weight of structure, incl ports 65 tonnes • Weight of torus shielding 100 tonnes • Coolant • Normal Operation Water, < 100C, < 1 Mpa • Bake-out Water ~150C, < 1 Mpa • Materials • Torus, ports and structure 316LN ss • Shielding 304L ss (tentative) FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  6. Vessel port configuration FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  7. Divertor piping Cryopump Divertor Midplane port w/plug Vessel ports and major components FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  8. Nuclear shielding concept • Vessel shielding, port plugs and TF coils provide hands-on access to port flanges • Port plugs weigh ~7 tonnes each as shown, assuming 60% steel out to TF boundary FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  9. Active and passive stabilizing sys. • passive plates ~25 mm thick copper with integral cooling Active control coils, segmented into octants IB and OB passive stabilizing conductor FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  10. Passive conductor is also heat sink VV splice plate • Copper layer required to prevent large temperature gradients in VV due to nuclear heating, PFCs • Passive plates are required in most locations anyway • PFCs are conduction cooled to copper layer • Reduces gradient in stainless skin • Extends pulse length Cu filler (can be removed to allow space for mag. diag.) Cu Passive stabilizer VV PFC Tile Gasket FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  11. FIRE and ITER first wall concepts similar • BE, Cu, SSt • Detachable FW panel • Cooling integral with FW panel (requires coolant connections to FW) ITER • BE, Cu, SSt • Detachable FW tiles • Cooling integral with Cu bonded to VV FIRE FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  12. VV octant subassy w/passive structure Outboard passive conductor Inboard passive cond. Vessel octant prior to welding outer skin between ribs FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  13. Vessel octant subassembly fab. (2) • Octant-to-octant splice joint requires double wall weld • All welding done from plasma side of vessel • Splice plates used on plasma side only to take up tolerance and provide clearance • Plasma side splice plate wide enough to accommodate welding the coil side joint FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  14. Vessel analysis • Vessel subjected to numerous loading conditions • Normal operation (gravity, coolant pressure, thermal loads, etc.) • Disruption (including induced and conductive (halo) loads • Other loads (TF current ramp, seismic, etc.) • Preliminary FEA analysis performed • Linear, static stress analysis • Linear, transient and static thermal analyses • Main issues are disruption loads, thermal stresses FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  15. Vacuum vessel mechanical loads FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  16. Disruption effects on VV • Disruptions will cause high loads on the VV due to induced currents and conducting (halo) currents flowing in structures • Direct loads on vessel shell and ribs • Direct loads on passive plates • Reaction loads at supports for internal components • Divertor assemblies and piping • FW tiles • Port plugs / in-port components (e.g. RF antennas) • Dynamic effects should be considered, including: • Transient load application • Shock loads due to gaps in load paths (gaps must be avoided) • All loads should be considered in appropriate combinations e.g. Gravity + coolant pressure + VDE + nuclear / PFC heating + Seismic + … FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  17. TSC runs confirm induced currents will concentrate in passive structures • Several TSC disruption simulations prepared by C. Kessel • VDE simulation used as basis for further analysis FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  18. VDE analysis based on TSC runs • TSC output used to create drivers for Eddycuff model of VV • Peak loads applied to ANSYS model of VV • Halo loads from TSC mapped directly onto VV model Inner Face Sheet Outer Face Sheet Copper Plates EDDYCUFF EM Model ANSYS Structural Model FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  19. I (A) 10-ms 300-ms 301-ms Reduced Filament Model (EDDYCUFF) TSC Filaments 301.6-ms 302.6-ms Plasma Evolution (TSC), from earlier data FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  20. Typical Induced Eddy Currents Constant Current Vectors Proportional Current Vectors FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  21. Current vs Time, Slow VDE (1 MA/ms) FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  22. Typical EM loads due to Induced Current • Max force = -1 MN radial, +0.7 MN vertical per 1/16 sector (~11 MN tot) FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  23. 1 MA/ms VDE FZ F(lbs) FR Case 2 Case 1 t(s) Total Force vs time, induced + halo currents FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  24. Typ. EM Force distr. due to Halo Current • Mapped directly from TSC to ANSYS, Halo current = 12-25% Ip • Max force = +0.13 MN radial, +1.2 MN vert. per 1/16 sector FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  25. Y Z Pin 1 Reaction Fx=12662 Fz=10708 Lug 1 Reaction Fx=35121 Fy=40107 Fz=6987 X Pin 2 Reaction Fx=-22147 Fz=6614 Lug 2 Reaction Fx=-32540 Fy=-36384 Fz=-6473 Forces are in pounds Divertor loads from current loop • Loads based on PC-Opera analysis *ref Driemeyer, Ulrickson FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  26. Combined stress, with VDE • Stresses due to gravity, coolant pressure, vacuum, VDE • VDE load includes direct EM loads on vessel (induced current and halo) and non-halo divertor loads Stress is in psi 1.5Sm = 28 ksi (195 Mpa) Stress is in psi VV Torus Ports FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  27. Divertor attachment local stresses • Global model not adequate for analysis • Detailed model indicates adequate design Extended pins through the ribs and attached them to the outer shell Reinforced pins near connection points Increased hole Diameter to 0.7” Modified rib thickness to correct values 1.5Sm = 28ksi (195 Mpa) Stress is in psi FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  28. Nuclear heating and thermal effects • Vacuum vessel is subject to two basic heat loads: • Direct nuclear heating from neutrons and gammas • Heating by conduction from first wall tiles (which in turn are heated by direct nuclear heating and surface heat flux) • A range of operating scenarios is possible, but the baseline cases for analysis assume: • 150 MW fusion power • 100 W/cm^2 surface heat load assumed on first wall, • 45 W/cm^2 is current baseline (H-mode) • > 45 W/cm^2 for AT modes • pulse length of 20 seconds (H-mode - 10T, 7.7 MA) • Pulse length of 40-ish seconds (AT mode - 6.5T, 5 MA) • Vessel is cooled by water • Flowing in copper first wall cladding • Flowing between walls of double wall structure FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  29. Heat loads on vessel and FEA model • Fusion power of 150 MW • Surface heat flux is variable, 0, 50,100, and 150 W/cm2 analyzed C B D A Double wall Vac Vessel Cu cladding Tile, (36 mm) FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  30. 2-D temp distr (100W/cm2 surface flux) Inboard midplane Outboard midplane 20 s pulse 383 C 377 C 40 s pulse Be limit ~ 600C 619 C 622 C FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  31. Peak Be temp vs heat flux, pulse length Be limit FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  32. Nuclear heating distribution* Neutron wall loading Volumetric heating: plasma side, ss coil side, ss divertor * Ref M. Sawan FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  33. Typical 3-D temp distribution in VV FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  34. VV thermal deformation and stress Stress is in psi Peak High stress region localized Stress < 3xSm ( 56 ksi) Typical Deformation FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  35. Combined stresses, 40 s pulse Stress is in psi • Nuclear heating, gravity, coolant pressure, vacuum Max Stress = 23 ksi, < 3Sm (56ksi) Max Deflection = 0.041 in. FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  36. Combined stress, 10T, 7.7MA, 20 s pulse, with VDE is worst loading condition • Nuclear heating, gravity, coolant pressure, vacuum, slow VDE Stress is in psi Stress is in psi 3xSm Max Stress = 58 ksi, > 3Sm (56ksi), but very localized FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  37. Combined stress, 6.5T, 5 MA, 40 s pulse, with VDE – not as severe as high field case • Nuclear heating, gravity, coolant pressure, vacuum, slow VDE Stress is in psi Max Stress = 46 ksi, < 3Sm (56ksi), also very localized FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  38. Preliminary VV stress summary (1) Normal, High field (10T, 7.7 MA), 20 s pulse operation – O.K. FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  39. Preliminary VV stress summary (2) High field (10T, 7.7 MA), 20 s pulse with VDE – a little high FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  40. Preliminary VV stress summary (3) Normal, Low field (6.5T, 5 MA), 40 s pulse operation – O.K. FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  41. Preliminary VV stress summary (4) Low field (6.5T, 5 MA), 40 s pulse with VDE – O.K. FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  42. Conclusions of vessel analysis • Can vessel achieve normal operation? YES • Can vessel achieve pulse length? YES • 20 second pulse appears achievable • 40 second pulse should be achievable but depends on surface heat flux distribution and Be temperature • Can vessel take disruption loads? ITS CLOSE • Some local stresses over limit, but local reinforcement is possible • Additional load cases must be run FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  43. What analysis tasks are next? • Optimized geometry and refined FEA models • Dynamic analysis with temporal distribution of VDE loads • Fatigue analysis, including plastic effects • Seismic analysis • Plastic analysis • Limit analysis FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  44. Longer term issues for FIRE • Refine design • Develop design of generic port plug • Optimize divertor attachments for stress, remote handling • Design internal plumbing and shielding • Re-design / optimize gravity supports • Perform needed R&D • Select/verify method for bonding of copper cladding to vessel skin • Select/verify method for routing of cooling passages into and out of cladding • Develop fabrication technique for in-wall active control coils • Perform thermal and structural tests of prototype vessel wall, with cladding, tubes, tiles, etc. (need test facility) • Verify assembly welding of octants and tooling for remote disassembly/reassembly (need test facility) FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  45. Remote Handling Overview FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  46. Remote Handling* • Maintenance Approach & Component Classification • In-Vessel Transporter • Component Replacement Time Estimates • Balance of RH Equipment *ref T. Burgess FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  47. Remote Maintenance Approach • Hands-on maintenance employed to the fullest extent possible. Activation levels outside vacuum vessel are low enough to permit hands-on maintenance. • In-vessel components removed as integral assemblies and transferred to the hot cell for repair or processing as waste. • In-vessel contamination contained by sealed transfer casks that dock to the VV ports. • Midplane ports provide access to divertor, FW and limiter modules. Port mounted systems (heating and diagnostics) are housed in a shielded assembly that is removed at the port interface. FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  48. Remote Maintenance Approach (2) • Upper and lower auxiliary ports house diagnostic and cryopump assemblies that are also removable at the port interface. • Remote operations begin with disassembly of port assembly closure plate. • During extended in-vessel operations (e.g., divertor changeout), a shielded enclosure is installed at the open midplane port to allow human access to the ex-vessel region. • Remote maintenance drives in-vessel component design and interfaces. Components are given a classification and preliminary requirements are being accommodated in the layout of facilities and the site. FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  49. Class 1 Class 2 Class 3 Class 4* Divertor Modules Limiter Modules Midplane Port Assemblies - RF heating - diagnostics First Wall Modules Upper and Lower Horiz. Auxiliary Port Assemblies - cryopumps - diagnostics Vacuum Vessel Sector with TF Coil Passive Plates In-Vessel Cooling Pipes - divertor pipes - limiter pipes Toroidal Field Coil Poloidal Field Coil Central Solenoid Magnet Structure Remote Handling,Classification of Components * Activation levels acceptable for hands-on maintenance FIRE Physics Validation Review: Vacuum Vessel and Remote Handling

  50. In-Vessel Remote Handling Transporter Cantilevered Articulated Boom (± 45° coverage) • Complete in-vessel coverage from 4 midplane ports. • Local repair from any midplane port. • Handles divertor, FW modules, limiter (with component specific end-effector). • Transfer cask docks and seals to VV port and hot cell interfaces to prevent spread of contamination. FIRE Physics Validation Review: Vacuum Vessel and Remote Handling