An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NCSX Vacuum Vessel R&D and Manufacture Mike Viola, Phil Heitzenroeder, Paul Goranson and Mike Cole for the NCSX Engineering Team NCSX Preliminary Design Review

  2. Outline • Overview of NCSX’s Vacuum Vessel R&D • Manufacturing Plans • Risk Mitigation • Cost & Schedule • Summary NCSX Preliminary Design Review

  3. NCSX’s Vacuum Vessel Was Recognized as Unconventional Right from its Conception • Highly shaped • Forming of Inconel 625. Need for tight tolerances • Design has to accommodate assembly needs • Modular coils have to be positioned over the VV; this requires all ports except mid period ports to be welded in place after the coils are installed. • Vessel shape & size has to be compatible not only with plasma, but with divertors and space needed to “slide” the modular coils over it. NCSX Preliminary Design Review

  4. Consequently a Series of Manufacturing Studies Were Developed to Reduce Risk Completed • Phase I. Funded Studies in the Conceptual Design Phase. Goals: to obtain industrial inputs on the VV design, its specification, and cost and schedule. Vacuum Vessel Study Participants: • A Kharkov consortium. • Major Tool and Machine, Inc. • Hitachi • Mitsubishi • Atlas Foundry and Machine Co. / PCC Structurals The goals were well met. • Most importantly, we learned that the vessel can, indeed, be manufactured and manufactured by a variety of processes. • We also received a great deal of feedback on the design, specification, costs, and schedules. Our sincere thanks to all the study participants!! NCSX Preliminary Design Review

  5. Tolerances Were Originally Developed Jointly with Study Participants NCSX Preliminary Design Review

  6. Tolerances Were Further Developed with Prototype Suppliers • Profile tolerance on outer vacuum surface is bilateral i.e. .1875 either side of reference surface. • Material thickness tolerance shall be per requirements set forth in ASTM B443. The minimum thickness after forming shall be .338. Thinning below the stock thickness shall not occur over more than 10% of the total poloidal circumference of any cross-section. NCSX Preliminary Design Review

  7. The vacuum vessel has potential technical, cost and schedule risks; consequently a Risk Management Program is being developed. • Potential Technical Risk #1. The vessel will not permit a high quality vacuum (leaks, outgassing, etc.) • Addressed in the design, the procurement specification, and the manufacturing, inspection, and test plan. • minimum number of welds. • The welds will be full penetration with a GTAW root pass and GTAW or GMAW filler passes, with no SMAW welding permitted. • The vessel will be leak checked at the fabricator after multiple heating and cooling cycles. • The interior surfaces will be polished and cleaned according to accepted vacuum equipment standards. • The main assembly flanges between field periods is welded. • All the circular ports will have conflat seals. In addition to leak checking at the manufacturer, leak checking will occur after the port extensions are welded in place and prior to assembly of the three field periods. NCSX Preliminary Design Review

  8. Risk Management (continued) • Potential Technical Risk #2. The vessel will not have the correct shape • Mitigated by the 3-D CAD technology and the use of modern 3-D measurement equipment such as laser trackers and portable coordinate measurement systems. • The vessel can be continuously measured and corrections made during the fabrication process, and intermediate heat treatment will be provided to reduce residual stresses that could cause distortion during operation. • All the fabrication processes will be demonstrated and optimized during the R&D phase of the vessel procurement, where full scale, partial prototypes will be fabricated and measured. • A spacer is included between each field period subassembly that will be used to accommodate any misalignment between field period assembly flanges NCSX Preliminary Design Review

  9. Risk Management (continued) • Potential Technical Risk #3. The coils will not fit over the vessel • Mitigated by the 3-D CAD technology, the use of laser scanners and/or multilink measuring systems to verify geometry, and using accurate scale models of the vessel and coils during the design and development processes. • A 1/12 scale model of the present design verifies that the coils and vacuum vessel can be assembled as planned. • Potential Technical Risk #4. The vessel will fail mechanically • Mitigated by analysis and conservative design criteria. • Critical analysis, such as disruption load calculations, stress and deflection calculations and buckling analysis will be performed by independent groups using different codes and models. • The disruption loads are relatively small compared to a tokamak of similar size, so these are not expected to cause significant problems. The stresses will be compared to the ASME code allowables, which provide a safety factor of 1.5 on yield for primary membrane stresses at the operating temperature. NCSX Preliminary Design Review

  10. Risk Management (continued) • Potential Technical Risk #5. The vessel will not have adequate thermal performance • Mitigated by using the same temperature control system successfully used for the NSTX vessel. • The system provides twice the heating capability and eight times the cooling capability predicted by analysis. • Multiple redundant paths ensure that minor blockages or minor leaks will not affect overall performance. • Potential Technical Risk #6. The vessel will introduce static or transient field errors • Mitigated by the choice of material and the strict adherence to stellarator symmetry. • Inconel 625, has a relatively high electrical resistivity, about 50% higher than 300 series stainless steel. This results in an electrical time constant of less than 10 ms for the most persistent induced current path. In addition, the relative magnetic permeability of the material, even after forming and welding is very low, less than 1.01, so field errors due to induced magnetism should be negligible. Finally, the port locations and geometry are stellarator symmetric, so any currents that are induced in the vessel should also be stellarator symmetric. NCSX Preliminary Design Review

  11. Risk Management (continued) • Potential Technical Risk #7. The vessel will not permit sufficient access for inspection, maintenance or reconfiguration of internal components • Mitigated by providing as many ports as possible that are large enough for manned access. • The three neutral beam locations each have a 14 x 33 inch oblong port that is accessible even with the beams installed. On either side of the neutral beam port are hourglass shaped ports with an 13.75 inch minimum width and 36 inch height, providing a total of six more manned access ports. Finally, the large neutral beam port cover flanges can be removed in at least one location to provide a clear, diamond shaped opening of 28 x 38 inches. NCSX Preliminary Design Review

  12. Risk Management (continued) • Potential Cost and Schedule risks mitigated by: • Manufacturing studies were carried out during the conceptual design process to obtain advice from manufacturing engineers on ways to make the design easier or less expensive to fabricate. Five different studies of the vessel were carried out, and several fabrication processes were considered, including hot pressing, cold pressing, explosive forming, and casting. • Vendor input has been continued after the CDR with an extensive R&D program. This effort will be carried out concurrently with the vessel design process such that the results can be included in the final design. • Two different vendors are fabricating partial prototypes of critical region of the vessel. • The forming, welding, machining, polishing, port removal and reattachment, and inspection processes will all be demonstrated and optimized. • At the conclusion of the R&D phase, a fixed price contract will be awarded for the production vessel. • The two vendors that have been selected for the R&D phase will result in at least two qualified vendors for the production articles, and provides an extra incentive to keep production costs (and bids) low. NCSX Preliminary Design Review

  13. Phase II of the Manufacturing Studies Is Now Underway Goals: • To produce a prototype VV sector. • To provide experience in manufacturing prototypical parts so firm fixed price proposals can be developed which do not have excessive contingency built in. • Prototype consists of a 20 degree sector (chosen for good demonstration of shape forming) and a vacuum port assembly to demonstrate their ability to produce vacuum-quality welds. NCSX Preliminary Design Review

  14. Phase II of the Manufacturing Studies Is Now Underway Goals: • The two Prototype suppliers Major Tool and Rohwedder have submitted their MIT plans and were authorized for fabrication on August 7th. • Major Tool has begun fabrication of the dies and has one complete set. • Rohwedder is having resource difficulties with their subcontractor but has made a proposal to resolve the issue. NCSX Preliminary Design Review

  15. Phase II of the Manufacturing Studies Is Now Underway (Major Tool Die/Punch set) NCSX Preliminary Design Review

  16. Vacuum Vessel Phase II Manufacturing Studies / Prototype Fabrication Schedules and Costs NCSX Preliminary Design Review

  17. Phase III of the Vessel Fabrication Is Upcoming Goals: • To build the Vacuum Vessel within Specification, On Time & On Budget. • It is our intent to select one subcontractor for the vacuum vessel assembly (ie, 3 vessel sectors and all associated ports). The selection will be based on firm price/schedule proposals, evaluation of the prototypes, and our experience in working with them during these efforts. The earlier efforts will provide the technical and manufacturing experience base to make this possible. NCSX Preliminary Design Review

  18. Vacuum Vessel Phase III Fabrication Cost and Schedule NCSX Preliminary Design Review

  19. Summary • The Prototype Vacuum vessel is under construction. • The experience gained from this 20 degree segment will provide the experience and knowledge to build the Vacuum Vessel Subassembly with great confidence in the design and cost factors. NCSX Preliminary Design Review