June 12, 2012 Mc meeting

June 12, 2012 Mc meeting. DENNIS ROBINSON Market Operations. Timeline Adjustments for the Clearing of the DAM & RAA. Moving the Day Ahead Market & Reser ve Adequacy Assessment Clearing Times . Outline – Moving DAM & RAA Timelines. Why? - Operational Reliability Concern How it Works Today

elma
Download Presentation

June 12, 2012 Mc meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. June 12, 2012 Mc meeting DENNIS ROBINSONMarket Operations Timeline Adjustments for the Clearing of the DAM & RAA Moving the Day Ahead Market & Reserve Adequacy Assessment Clearing Times

  2. Outline – Moving DAM & RAA Timelines • Why? - Operational Reliability Concern • How it Works Today • What? – Propose Moving the DAM & RAA Clearing timelines • Next Steps - schedule

  3. WHY? - Operational Reliability Concern Current commitment timelines do not provide timely information regarding fuel availability for gas fired generation that allows for ISO operations to commit longer lead time resources. Why has this become a problem?

  4. WHY? - Operational Reliability Concern • Increased Reliance on Natural Gas Fired Generation: • In 1990, Gas Fired Generation accounted for approximately 5% of energy • Currently, Gas Fired accounts for approximately 50% of energy with oil accounting for approximately 0.5% • Increased Dependency on Gas Fired Generation will continue in the future • Economic & Environmentally Attractive • Counterbalancing the Variable Energy Resources (i.e. Wind) • Majority of Gas Fired Generators are not Firm Customers of the Pipelines • Pipelines becoming more strict (OFOs, shut off valves) • 1/24 hour by hour level take

  5. WHY? - Operational Reliability Concern • No Longer Just a Cold Weather Concern • Interrupted Fuel Supply (Sable Island) • Hot Temperatures Coupled with Pipeline Maintenance • Pipelines Forcing Generators Offline • Unable to accommodate when delivery is not scheduled properly • Jeopardizing pipeline reliability -Current ISO timing provides inadequate time to properly pack and schedule pipeline • Late Notification of Commitment • Gas fired Generation may be unable to procure fuel • Late Communication/Notification to Control Room results in being unable to call on longer lead time oil fired generators

  6. How It Works Today

  7. How It Works Today- Current ISO - NE Process Daily Initial & Evening Nomination Effective Flow 10:00 Gas Day-1 Intra-Day 1 Effective Flow 18:00 Gas Day-1 Intra-Day 2 Effective Flow 22:00 Gas Day Intra-Day 1 Effective Flow 18:00 Gas Day -2 Gas Day -1 Gas Day Gas Day vs. Electric Day Timelines 10:00 AM 10:00 AM Daily Initial Nomination Deadline 12:30 Evening Nomination Deadline19:00 Gas Day -1 Intra-Day 1 Nomination 11:00 Gas Day -1 Intra-Day 2 Nomination 18:00 Gas Day Intra-Day 1 Nomination 11:00 Electric Day -2 Electric Day -1 Electric Day 12:00 AM 12:00 AM 12:00 AM 22:00 (D-1) - 24:00 (D)Resource Adequacy AssessmentHourly SchedulingCurrent Operating Plan5-min. Dispatch 18:00 Reoffer Period Closes 22:00 RAA Complete 12:00 DAM Closes 16:00 DAM Clears

  8. Gas Nomination Timing– NAESB Standards * Start of Gas Day / (All times are in Eastern Time (ET))

  9. How it Works Today – NAESB Standards

  10. What? – Propose Moving the DAM & RAA Clearing timelines • Produce DAM & Initial RAA Results/Schedules by 11:30 AM on the Day Prior to Operating Day • Pros • Generators would know their schedules from both the DAM & initial RAA prior to the 12:30 EST Timely Nomination Deadline • Better utilize the gas pipeline capability • Firm –up the fuel supply for gas generators (particularly those that cycle or needed intermittently)–ensuring reliable commitment • Allow Control Room to call on long lead time replacement generators for units who are unable to procure fuel or commit supplemental units for reliability after knowing market response • Cons • Clearing Occurs Further Away from Operating Day (Load Forecast, Outage information) – More Risk • Price Certainty on Offers – Offer Window closes prior to price discovery – More Risk

  11. What? – Propose Moving the DAM & RAA Clearing timelines • Other considerations as part of this proposed modification • Alignment of Mitigation Rules (review of rules) • Information /Communication requirements

  12. Schedule • Markets Committee • July Summer Meeting: ISO Proposed Timeline/Discussion • August: Proposed Rule Changes • September: Vote Market Rule Changes • Participants Committee • October: Vote Market Rule Changes