An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMPC Final Intern Presentation Caitlynn Roy EMPC Projects Execution Intern 7 August 2014

  2. Agenda • Safety Moment • Background • Projects • Other Experiences Gained • Lessons Learned • Questions

  3. Safety Moment - H2S Detection • What is the proper monitor placement? • Always place monitor at or near your face as to detect any H2S presence • Make sure sensor is not obstructed by clothing and facing outward • What happened? • Goldsmith Tract 2 Gas Leak • H2S Monitor Alarmed • Awareness: • Be aware of your surroundings • Always know the wind direction • Test the monitor each time you use it

  4. Background • Born: Dover, Delaware • Hometown: America • School: New Mexico State University – May 2016 • Degree: Chemical Engineering • Past Experience: • NMSU Aggie Innovation Space • NMSU Reduced Gravity & Biomechanics Lab • Involvement: American Institute of Chemical Engineers, Tau Beta Pi

  5. Project Assignments - XTO • MPZ/ROZ Expansion • Field: Means • Location: Andrews, TX • Facility: Sub-Battery 228 • University Block 20 Expansion • Field: Monahans • Location: Wink, TX • Facility: University Block 20

  6. Means Field Well Work Plan • History • 1934 – Discovered • 1963 – Start Water Flood • 1983 – Start CO2 Flood • Main Pay Zone / Residual Oil Zone • Re-developing the MPZ • Expanding CO2 into ROZ • Expansion will increase oil production from 6,000bpd to 13,000 bpd • Cost • Total Investment: $635 Million ($440 already funded) SB 228 North Dome Expansion Phase 1 Other Expansion Areas

  7. XTO - MPZ/ROZ Expansion • Scope: • Determine capacity of current facility • Determine facility design required for forecasted rates • Findings: • Concluded that Sub-Battery 228 will experience bottlenecking due to the current piping • The forecasted gas production requires significant facility upgrades

  8. SB 228 - Present Plot Plan A Test A B 8’x20’ Test B To TB200 Test Production To GCF/MCS

  9. SB 228 - Proposed Plot Plan New 6” Test Header New 10” Vent Line New 10” Header C A Test A B New 10’x30’ Sep 8’x20’ Test B To TB200 To TB200 Test Production To GCF/MCS

  10. Deliverables – P&IDs & Plot Plans

  11. Deliverables - Sizing • Vessel • Retention Times • Gas Composition • Slender Ratio • Pressure Safety Valves • Total blocked flow • MAWP • Pipe Line • Pressure Drop • Moody Friction Factor • Reynolds' Number • Erosional Velocity

  12. Deliverables New Facility Design • AFE – Cost: $750k • Design Review • Cost Estimates • Scheduling • Next Steps: • Bill of Materials • Passing onto the facility engineer • Construction to complete in October/November New 10” Header Key: New Equip. New 6” Test Header Existing Equip. C Test B A Production To TB200 6’x15’ Test A To TB200 8’x20’ Sep 6’x15’ Test B To GCF To Vent New 10’x30’ Sep To 10” Vent

  13. XTO University Block 20 Expansion • History: • University Land • Drilling started 2 ½ years ago • Better production than expected • Plan: • 4 wells are planned • Additional separation and treating required to meet forecasted production • Scope: • Locate potential tie-ins • Determine appropriate sized vessels • Determine line sizing

  14. University Block 20 – Plot Plan Existing Block 20 Test Sep New Block 20 Test Sep Existing Block 20 Prod Sep New H/T Existing H/T New Block 21 Prod Sep Existing Block 21 Test Seps

  15. XTO University Block 20 Expansion • Proposed solution • (2) 5’x15’ Separators • (1) 6’x20’ Heater Treater • (1) Transfer Pump • Modified Headers • Deliverables: • P&IDs, Plot Plans • Sized vessels, lines, PSV, pumps • AFE – Cost: $575k • Commission – Mid September

  16. Deliverables - Sizing • Heater Treater • Nomograph • Sivall’s Manual on Crude Oil Treating • Transfer Pumps • 1 Stage • Size: 1x2 - 10 • Impeller Size: 8.875 in

  17. Other Experiences Gained • Opportunity to work with XTO and travel to Midland, TX • Fracking & Acid Job • Perforation Job • Fabrication Yard • Enerflex Compression Skids • TB 200 Construction

  18. Lessons Learned • Value of a hands on experience • Importance of traveling to the field • Efficiency of asking an expert • Importance of engaging operations during design • Unforeseen issues not yet considered • Learning to be aware of the larger scope

  19. Thank You, Any Questions? Take the attitude of a student, never be too big to ask questions, never know too much tolearnsomething new. -OgMandino