An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ground Based Observatories (GBO)Program Schedule and StatusStewart Harris

  2. Approach to System I&T • Lab testing where necessary and possible • For instance, testing of temperature limits on cameras • Cold limit testing on commercial components • Get in the field early and often • Establish network of GBOs well before satellites launched • Prototype to be deployed winter ’03-’04 • ASI deployed with OSE in Calgary late Feb. • CSE deployed in Athabasca mid-Apr • GMAG (E/PO type) deployed in Athabasca mid-Apr • Original Deployment Schedule • 5 Units to be deployed by winter ’04-05 • Additional 15 Units deployed by winter ’05-06

  3. Current Deployment Schedule • Deployments scheduled between May and Oct in ’04, ’05, ‘06 • By Winter ’04-’05: 6 GBOs done • Summer ’04: deploy 4 in Canada, 2 in Alaska • By Winter ’05-’06: 14 GBOs done • Summer ’05: deploy 6 in Canada, 2 in Alaska • Demonstrate operational breadth of network • By Time of Themis Launch (Oct. ’06): 20 GBOs completed • Summer ’06: deploy final 6 in Canada • Complete the network, have all operating

  4. Schedule Summary Issues: 1) KAPU is missing a magnetometer 2) Magnetometer at Contwoyto Lake is ~140km from LGRA

  5. Schedule Detail(‘04)

  6. Status/Issues • GBO Production Procurement Status/Issues • ASI and OSE procurement is already in progress • Cameras, Lenses, Power components already in house • ASI Enclosure production is in procurement • Need to identify sites that require a Computer Enclosure • Ideally we purchase what we need in one order • Changes to design will likely cause some delay in fabrication • Open Issues • Enough magnetometers? • Computer selection • Sun shield design validation • Integration of Iridium is lagging • GMAG Linux software development and integration