Muon Campus MC-1 Building GPP Update Russ Alber FESS Engineering November 28, 2012

Muon Campus MC-1 Building GPP Update Russ Alber FESS Engineering November 28, 2012. MUON Campus Program. MUON Campus Program. MUON Campus Program. MC-1 Building GPP. MC-1 Building GPP Org Chart. General Plant Project (GPP) Approved: April 20, 2012. MC-1 Building GPP Funding Profile.

emera
Download Presentation

Muon Campus MC-1 Building GPP Update Russ Alber FESS Engineering November 28, 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Muon CampusMC-1 Building GPP UpdateRuss AlberFESS EngineeringNovember 28, 2012

  2. MUON Campus Program

  3. MUON Campus Program

  4. MUON Campus Program

  5. MC-1 Building GPP

  6. MC-1 Building GPP Org Chart • General Plant Project (GPP) Approved: April 20, 2012

  7. MC-1 Building GPP Funding Profile $1M transferred to FY14

  8. MC-1 Building GPP Current Costs

  9. MC-1 Building GPP Milestone Schedule

  10. MC-1 Building GPP Scope Construction split into two packages to expedite construction: Package A – MC-1 Building Site Prep ($1.096M FY13) Goal is to 1) relocate all utilities out of building excavation, and 2) perform all shutdown work during current shutdown Relocate/tap into utilities: Chilled Water Supply & Return (CHWS, CHWR) Domestic Water Supply (DWS) Gas (GAS) Industrial Cooling Water (ICW) Sanitary Sewer and new lift station (SAN) Electrical ductbank and manholes Communication ductbank and handholes Relocate Well Pond Road (shutdown work) Install cryo line supports and under-road piping (shutdown work)

  11. MC-1 Building GPP Scope • Package A – MC-1 Building Site Prep – CURRENT STATUS • Issue for Bids: November 20, 2012 Bids Due: December 13, 2012 • Bid documents are located here: • ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/6-10-20A - Issued for Bids/ • Notice of Intent & Storm Water & Pollution Prevention Plan (NOI & SWPPP) has been submitted to Illinois Environmental Protection Agency (IEPA) on November 1, 2012. Construction can begin December 1, 2012. • Revision No. 1 in process to incorporate entire Muon Campus including Mu2e. DRAFT out for review. • ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/NOI & SWPPP/ • Radiation Safety Drawings created for all work within the vicinity of the 8 GeVbeamline. Reviewed by AD/Radiation Safety and awaiting final approval for construction. • ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/Radiation Drawings/

  12. MC-1 Building GPP Scope • Package B – MC-1 Building ($4.0M FY13, $0.8M FY14) • 60% Review completed October 24, 2012 • Issue for Bids – February 2013 (est.) • Pre-procurements (FY13) • 1,500 kVA Transformer - $80K • (pad installed under building package for current and future transformers) • 15 kV Switch - $20K • 30 Ton Building Crane - $175K

  13. MC-1 Building – Site Plan

  14. MC-1 Building – First Floor Plan

  15. MC-1 Building – Second Floor Plan

  16. MC-1 Building – Cross Sections