Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013. MUON Campus Program. MUON Campus Program. MUON Campus Program. MC-1 Building GPP. MC-1 Building GPP Org Chart. General Plant Project (GPP) Approved: April 20, 2012.

terra
Download Presentation

Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MuonCampus AIP ReviewMC-1 Building GPP UpdateRuss AlberFESS EngineeringJanuary 23, 2013

  2. MUON Campus Program

  3. MUON Campus Program

  4. MUON Campus Program

  5. MC-1 Building GPP

  6. MC-1 Building GPP Org Chart • General Plant Project (GPP) Approved: April 20, 2012

  7. MC-1 Building GPP Funding Profile $1M transferred to FY14

  8. MC-1 Building GPP Milestone Schedule

  9. MC-1 Building GPP Scope Construction split into two packages to expedite construction: Package A – MC-1 Building Site Prep ($742.5K FY13) Goal is to 1) relocate all utilities out of building excavation, and 2) perform all shutdown work during current shutdown Relocate/tap into utilities: Chilled Water Supply & Return (CHWS, CHWR) Domestic Water Supply (DWS) Gas (GAS) Industrial Cooling Water (ICW) Sanitary Sewer and new lift station (SAN) Electrical ductbank and manholes Communication ductbank and handholes Relocate Well Pond Road (shutdown work) Install cryo line supports and under-road piping (shutdown work)

  10. MC-1 Building GPP Scope • Package A – MC-1 Building Site Prep – CURRENT STATUS • Cost Estimate: $1.096M – Low Bid: $742.5K Whittaker Construction • Construction documents are located here: • ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/6-10-20A - Issued for Bids/ • Notice of Intent & Storm Water & Pollution Prevention Plan (NOI & SWPPP) has been submitted to Illinois Environmental Protection Agency (IEPA) on November 1, 2012. Construction can begin December 1, 2012. • Revision No. 1 to incorporate entire Muon Campus including Mu2e approved. • ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/NOI & SWPPP/ • Radiation Safety Drawings created for all work within the vicinity of the 8 GeVbeamline. Reviewed by AD/Radiation Safety and awaiting final approval for construction. • ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/Radiation Drawings/

  11. MC-1 Building GPP Scope • Package B – MC-1 Building ($4.0M FY13, $0.8M FY14) • 60% Review completed October 24, 2012 • 95% Review (Lab Wide) – February 1, 2013 (est.) • Issue for Bids – March 2013 (est.) • Pre-procurements (FY13) • 1,500 kVA Transformer - $125K • (pad installed under building package for current and future transformers) • 15 kV Switch - $20K • 30 Ton Building Crane - $175K

  12. MC-1 Building – Site Plan

  13. MC-1 Building – First Floor Plan

  14. MC-1 Building – Basement Plan

  15. MC-1 Building – Second Floor Plan

  16. MC-1 Building – Elevations

  17. MC-1 Building – Elevations

  18. MC-1 Building – Cross Sections