Highway 1 HOV Lane Widening Estimated Project Milestones. Public Information Meetings September 20, 26, 27, 2006 Complete Technical Studies Fall 2007
E N D
Highway 1 HOV Lane WideningEstimated Project Milestones • Public Information Meetings September 20, 26, 27, 2006 • Complete Technical Studies Fall 2007 • Public Review of Draft Environmental Document Winter 2007/2008 • Review & Respond to Public Comments Received Spring 2008 • Preferred Alternative Selection Summer 2008 • Publish Final Environmental Document Winter 2009 If funding is secured • Final Design & Specifications /Right of Way Acquisition 2010 - 2012 • Construction 2011 - 2015