JCN, Justice Cooperation Network. European T reatment and Transition Management of High Risk Offenders Helsinki, 30 October 2013 Steering Committee Meeting. The Project Activities. Work Stream 0. Management. Workstream 0.A) Actions Carried Out Planning and Organization 1/2.
E N D
JCN, Justice Cooperation Network European Treatment and Transition Management of High Risk Offenders Helsinki, 30 October 2013 Steering Committee Meeting
Work Stream 0 Management
Workstream 0.A) Actions Carried Out Planning and Organization 1/2 • 0.A.2) Participation in the Third Partners Meeting. All documents are available on the project website: http://jcn.pixel-online.org/info/meetings.php • 0.A.5) Progress Activities Reports. The form is available on the project website: http://jcn.pixel-online.org/info/activities.php
Workstream 0.A) Current situationPlanning and Organization 2/2 Progress Activity Report: • MJ: this activity is completed (info provided until 30 Sept) • TP: this activity is completed (info provided until 30 Sept) • IPS: this activity is completed (info provided until 30 Sept) • PIXEL: this activity is completed (info provided until 30 Sept) • JMMV: needs to update the report (info provided until 30 Sept) • EMAU: needs to update the report (info provided until 30 Sept) • CSA: No Activity Report produced NB: Only 1 WS form per partner, update the information within the same form. http:// jcn.pixel-online.org/info/activities.php
Workstream 0.C)Actions Carried OutDissemination 1/2 • 0.C.1.1) Creation of brochure in all languages http://jcn.pixel-online.org/information_brochure.php • 0.C.3) Creation of internal newsletters • This activity is so far completed • The next Newsletter has to be ready by 30 October 2013 The common template should be used for creating newsletters. It is available at: http://jcn.pixel-online.org/info/download.php# • Oct 2013
Workstream 0.C)Actions Carried OutDissemination 2/2 • Oct 2013 - Dec 2013 • Sep 2013 - Oct 2014 • Sep 2013 - Oct2014 • 0.C.4) Creation of external newsletters 1Missing External Newsletters: JMMV Next one due by Oct 2013 http://jcn.pixel-online.org/DSS_newsletter.php • 0.C.5) Publication of press articles Missing Press Articles: MJ http://jcn.pixel-online.org/DSS_press.php • 0.C.6) Speeches about the project in relevant events Missing Events Description: MJ , IPS http://jcn.pixel-online.org/DSS_events.php See template for the presentation of Events: http://jcn.pixel-online.org/info/download.php#
Workstream 0.D)Actions Carried OutEvaluation 1/2 • Quality Plan http://jcn.pixel-online.org/evaluation.php • First progress Evaluation Report http://jcn.pixel-online.org/evaluation.php
Workstream 0.D)Actions to Be Carried Out 2/3 Evaluation 2/2 • Oct 2013 • Sept 2014 • Second Progress Evaluation Reports Missing Second valuation Report due by Oct 2013: EMAU • Final Evaluation Report
Work Stream 1 Working out the Common Basis
Workstream 1Actions Carried Out 1/4 1.A) Minutes of the National Meeting re. WS1 http://jcn.pixel-online.org/workshop1_minutes.php 1.B) Organization of Transnational Workshop 1 (Estonia) http://jcn.pixel-online.org/workshop1.php
Workstream 1Actions Carried Out 2/4 1.B) Report on the Workshop http://jcn.pixel-online.org/workshop1_reports.php 1.C) Report entitled Common Understanding of Terms and Definitions http://jcn.pixel-online.org/reports.php 1.G) Translation into the national language of the Report (and language check) Missing Translations: TP / MJ Checkifthisis the finalversion to be translated
Work Stream 2 Comparison
Workstream 2Actions Carried Out 1/4 1.A) Minutes of the National Meeting re. WS2 • Minutes of the Irish meetings are missing http://jcn.pixel-online.org/workshop2_minutes.php 1.B) Organization of Transnational Workshop 2 (Ireland) http://jcn.pixel-online.org/workshop2_reports.php
Workstream 2Actions Carried Out 2/4 2.C) Report entitled TransnationalComparative Analysis of TransitionManagement Strategies http://jcn.pixel-online.org/files/workshops/02/Report%20on%20Transnational%20Comparative%20Analysis%20of%20Transition%20Management%20Strategies.pdf 2.H) Translation into the national language of the Report Checkifthisis the finalversion to be translated
Work Stream 3 Analysis
Workstream 3Actions Carried Out 1/4 3.A) Organization of Internal National Meetings + Minutes • Minutes of the Irish and German meetings are missing http://jcn.pixel-online.org/workshop2_minutes.php 3.B) Organization of a Transnational Workshop (Finland) + Report
Workstream 3Actions to Be Carried Out 2/4 • Dec 2013 • Jan 2013 3.C) Report entitled Best Practice Strategies... 3.G) Translation into the national language of the Report
Work Stream 4 Models and Standards
Workstream 4Actions to Be Carried Out 1/4 • Feb 2014 • Apr 2014 • May 2014 • 4.A) Organization of Internal National Meetings + Minutes • 4.B) Organization of a Transnational Workshop (Germany) + Report • 4.E) Development of a Model for handling high risk offenders(JMMV, De)
Workstream 4Actions to Be Carried Out 2/4 • May 2014 • Jun 2014 • 4.F) Production of a document identifying Standards and indicators as an integration to the model developed • 4.I) Translation into the national language of the Model and Standards
Workstream 4Templates and Tools 3/4 1.A) Guidelines for the production of the Minutes of the National Meetings 1.B) Guidelines for the production of the Workshop Reports
Work Stream 5 Final Conference
Workstream 5Actions to Be Carried Out 1/2 • Aug 2014 • Aug2014 • September 2014 • 5.A) Organization of Internal National Meetings • 5.B) Development of the contents of the CDs to be distributed to the Conference participants • 5.C) Organization of the Final Conference (Germany)
Workstream 5Expected Results 2/2 • Minutes of the Internal Meetings • 400 CD2 printed to be distributed to the Conference participants • Publication of Report on the Conference
Thank you for your Attention Questions?