An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A Carbon Reduction Plan for Property Mark Jeffcote Environment Team Leicester City Council

  2. Council Targets • Reduce the Council’s CO2 emissions to 50% of the 2008/09 level by 2025/26 • Also applies to property portfolio

  3. The Council’s Carbon Footprint 11/12

  4. A Strategic Approach to Property Emissions? • Approx. 70% of council emissions • Yet no strategic plan for managing emissions from the property portfolio! • Simply a list of projects in the ‘Road Map’

  5. The Property Portfolio • Operational property - 490 • Schools - 110 • (Non-operational property – 500+) • (Council houses)

  6. Step 1 • Identify themes and responsibilities • Map projects and gaps/barriers • Additional ‘low cost’ project proposals

  7. Strategic Co-ordination – Policy Drivers, Resources, Timetable and Programme Management etc. BUILDING OPERATION UNDERLYING BUSINESS-AS-USUAL AND OTHER TRENDS LOCAL ENERGY SUPPLY INFRASTRUCTURE GRID SUPPLY NEW BUILD AND MAJOR REFURBISHMENT 1 BSF Energy Use Monitoring District Heating Green Supply Contracts Increased ICT Use Primary Schools Other Large Scale Low/Zero Carbon Technologies Larger Floor Areas Minor Upgrades - BSIP (-Decarbonisation) Corporate Projects(e.g. City centre accommodation strategy) Extended Opening Hours User Behaviour Control Setting Flexible Working Maintenance and Minor Upgrades – CMF, Buy-Back Asset Purchase/Disposal Environment Team Property Services ICT Energy Team 3 ICT 2 Diagram applies to: • Operational Property • City Centre • Neighbourhood • Schools 4

  8. Step 1 - Results • Lack of Strategic Co-ordination • Lack of standards (eg. specifications, BREEAM) • No acknowledgement of energy as a priority, lack of staff capacity for control setting, no funding for energy conservation. • No day-to-day explicit management support for schools. • (No work with large city-wide portfolio of non-operational property)

  9. Step 2 • Will the existing projects & new ‘low cost’ proposals achieve the 50% target?

  10. Step 2 - Results • Operational Property CO2 – 20 tonne shortfall • Schools CO2 – 7059 tonne shortfall

  11. Step 2 – Results for Operational Property

  12. Step 2 – Results for Operational Property

  13. Step 2 – Results for Schools

  14. Green Electricity from the Grid • ‘Buying Green’ and ‘Grid Decarbonisation’ • Would allow overall target to be met • But excluded from thinking!

  15. Green Electricity from the Grid • Only guaranteed for corporate buildings • No reduction in energy use or cost • No guaranteed supply • Potentially prohibitively expensive • Not accepted by government for emissions reduction • No renewables stimulation

  16. What Next? • Financial cost-benefit (ignoring the budget incentive mis-match!) • Secure (i) SCoRE (ii) engineer for control setting (iii) more energy sensitive CMF (iv) attention to BSF school operation • Schools a problem – Academies agenda? • Third-party solutions (eg. Non-domestic Green Deal, London Re:Made)

  17. DISCUSSION