An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06

  2. Design & Fabrication-Difficulties • Identify Injector / Linac problems! • Systematic and Specific • Review management actions to limit risk! • Answer reasonable questions!

  3. Design • LCLS Solid Modeling Solid Edge / Pro Engineering • First Large Project Experience at SLAC • Problems with: • General Organization • LCLS Hierarchy / Drawing Tree (Advanced Planning) • Large Model Assemblies • Lead Designer Control • Single Source / Multiple User / Revision Control • PDM System / Share Point • SLAC Staff • Uniform Supervision / Central Offices • Weekly group Meetings • Increased training • Checking Staff • Performance • Management / Software / Network & CPU Hardware

  4. Front End Water • Injector through BC1 • Large Change to Existing SLAC Facilities • Problems with: • LCLS CF Requirement • Multiple Circuits with tight regulation • Large Operating Bandwidth • Several Modes of LCLS / Linac Operation • Money & Schedule • Transferred Design Engineer with SLAC water experience • Validate proposals through SLAC CEF / AD • I/O interface with LCLS Controls

  5. LCLS Vacuum • Pressure Profile and Contamination • No problems with pressure profile • Issues with Contamination: • UHV at Injection Gun • Optics in vacuum • Adopted SLAC design and fabrication specification • Uniform equipment to assist Operations and Maintenance

  6. Installation • Installation and Schedule • Problems with: • New SLAC Operating Procedures • Soft Base – Constant Improvement • Partners with AD / MD /MFD / Klystron Manufacturing / Metrology • Davis-Bacon Contracting • Clear Instruction from LCLS Project Office • Inj / Lin “Fill In Mode” • Storage • Cleared MFD Bldg. 026 Rad Prep Storage • Instituted Bar Codes • MFD control procedures • QA • Share Point

  7. Installation • Distributed Fabrication • ANL / LBNL (OTRS1, Toroids, RF BPMs, Spectrometer Magnets) • Actual Delivery Schedule • Kathleen Ratcliffe – Expanded P3 Delivery Dates

  8. Mechanical / Control Interface • MPS, PPS, BCS, Cable Plant, AC Power • Problems with: • Schedule • Common understanding of P3 • Consistent Priority between groups. • Location and Cable Interface with mechanical hardware • Fuller interprets for LCLS Controls • Limited Hardware staff • Hamid has made great strides with staff and direction.

  9. Specific Components • Component of most concern: • Bunch Length Monitors in BC1 • GTL Fabrication • OTR /YAG Optics • BC1 Inter Bend Diagnostics

  10. Independent Tracking

  11. LTU • FY07 Installation • Remainder of the existing Linac • Linac to Undulator / Electron Dump • Increasing concern to articulate overall system • Schematic Released • Magnets moving forward • Instruments under general development • Tunnel Interface • Supports • Special Vacuum Chambers