1 / 16

Q20 and Injection Studies MD Floating MD

Q20 and Injection Studies MD Floating MD. ABT-BTP, OP-LHC, ABP-LIS. Q20. 1 hour delay: Previous MD was supposed to finish at 12:00 (beam dumped) while a new ramp started at 12:25  beam dumped at 13:10  pre-cycle

eugene
Download Presentation

Q20 and Injection Studies MD Floating MD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Q20 and Injection Studies MDFloating MD ABT-BTP, OP-LHC, ABP-LIS

  2. Q20 • 1 hour delay: • Previous MD was supposed to finish at 12:00 (beam dumped) while a new ramp started at 12:25  beam dumped at 13:10  pre-cycle • We were not allowed to start set-up in the SPS during LHC ramp because of high-rad-mat operation (High-rad-mat cannot work while LHC is injecting) • On top of that: communication glitch when preparing for a quick access in ATLAS  beam for Q20 only at 15:00 • No time left for testing the tool for automatic set-up of TCDI (injection studies part) • Please Respect MD schedule!

  3. Q20 • Injection phase corrected by +15 units for both beams • Switched polarity on one MDAV.610013 • Steering: • Beam 2: • MCIAH.87408       -8.47 MCIAV.86304       7.47 • Beam 1: • MCIAH.25804       9.54 MDLH.610104       11.06 MCIAV.28504       -6.20 Beam 1

  4. Q20 • Injection phase corrected by +15 units for both beams • Switched polarity on one MDAV.610013 • Steering: • Beam 2: • MCIAH.87408       -8.47 MCIAV.86304       7.47 • Beam 1: • MCIAH.25804       9.54 MDLH.610104       11.06 MCIAV.28504       -6.20 Beam 2

  5. Q20 • Injection with: • PILOT • INDIV (11 in total) • Emittance measurements • BSRT: some problem with data logging (communication)  manual acquisition + data saving

  6. Q20 Data analysis ongoing • Injection with: • PILOT • INDIV (11 in total) • Emittance measurements • BSRT: some problem with data logging (communication)  manual acquisition + data saving • Wirescanner: in SPS and LHC (any blowup/mis-match?). Some non clear dependence on order of measurements (first horizontal and then vertical or vice versa) • 3E11 protons bunch injected: • Losses: ~8% to dump threshold • Emittance measurements LHC B2 Vert. SPS Vert.

  7. Q20 • Dispersion measurements with pilot, 3 sets of measurements with: 0 Hz, -300 Hz, -600 Hz, + 300 Hz and 600 Hz frequency trim

  8. Q20 • Dispersion measurements with pilot, 3 sets of measurements with: 0 Hz, -300 Hz, -600 Hz, + 300 Hz and 600 Hz frequency trim Beam 1

  9. Q20 • Dispersion measurements with pilot, 3 sets of measurements with: 0 Hz, -300 Hz, -600 Hz, + 300 Hz and 600 Hz frequency trim Beam 2 Quite big mismatch

  10. Q20-Q26 Dispersion in TI8

  11. Supercycle dependence – injection losses LHC filling supercycle Wrong supercycle composition 11/5/2012 Supercycle composition: SFTPRO + LHC1 → Injection losses very high: dumped at injection • MD: Removed CNGS before LHC1 cycle to check effect under controlled conditions L. Drosdal V. Kain

  12. MD result: Nominal cycle:Beam 2144 bunches LHC cycle directly after SFTLONG: Beam 2 144 bunches L. Drosdal V. Kain

  13. MD result: Nominal cycle:Beam 2144 bunches LHC cycle directly after SFTLONG: Beam 2 144 bunches • B1: Losses are the same • B2: Losses only slightly increased • Effect smaller than scraping and shot-by-shot stability • Phenomenon of 11/5/2012 not reproduced • Position of LHC cycle in supercycle could be less important than previously thought

  14. Floating MD

  15. 25 ns Floating MD Plan • Before MD: • SPS: 1.05e11 ppb, ~2.5-3 mm emittance, scraping (~10%) • Extraction of 12 bunches of 25 ns up to the downstream TED • During MD: • Steering with 6-12 bunches of 50 ns (for injection oscillations and beam losses at the TCDIs if needed)  copy settings to 25 ns. • 25 ns Beam setup: • Fast setup of ADT, RF, Chromaticity (15 units) with single bunch • Inject 12 bunches of 25 ns and steer if needed • Injection of 24 bunches of 25 ns into the LHC • Increase intensity: • When 24 bunches OK  inject 48b  72b  144b (max. for B2) 288b (only for B1) • In case steering is needed  go back to12 bunches injection • Ideally take few shots per intensity to investigate TL stability and consequent losses in the injection region • If possible, accumulate some batches for longitudinal losses investigation • Recovery • revert all settings to 50 ns ones • revert all interlock thresholds to 50 ns ones, and separate cross-check • test injection of 6b at 50 ns still OK.

  16. Q20 Optics for High Pile-up Floating MD • Single bunch high intensity (3E11) • Parallel measurements: • Emittance in SPS and LHC (BSRT, Wire Scanner) • Dispersion (if re-matched)

More Related