An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utility Permitting Overview Tim Pelotte, Field Technician, Region 2Mike Moreau, Utility Engineer

  2. Utility Accommodation • Maine Statutes (Title 35-A Chapter 23) authorize the use of highway corridors for various forms of utility accommodation. • Such accommodation is subject to the conditions and restrictions of the “Applicable Licensing Authority”.

  3. Permitting Jurisdiction • MaineDOT, as a designated “Licensing Authority”, issues “Utility Permits” in the following areas: • All State Highways outside of compact areas • All State-Aid Highways outside of compact areas • All controlled-access areas on state or state-aid highways, regardless of the compact limits • All state owned or maintained bridges, regardless of the compact limits

  4. Utility Permits • Location Permits – Provides legal authorization to locate a facility in a specific location within a highway corridor. Applications are typically submitted in the late planning or early design phase. Typically no cost. • Highway Opening Permits – Provides authorization to enter upon and excavate within the highway corridor. Applications are typically submitted in the late design or pre-construction phase. A 10% fee, based on the area impacted, is applicable. Larger projects will typically require an escrow.

  5. Governing Documents • Utility Accommodation Rule (17-229 CMR Chapter 210) • MaineDOT Highway Opening Policy • MaineDOT Standard Specifications

  6. Basic Accommodation Rules for Underground Utilities • All facilities constructed within the highway corridor must be permitted • Depth: 3 feet minimum • Horizontal Clearance: 3 feet minimum • Vertical Clearance: 1 foot minimum • Coordination with adjacent existing utilities for new utility construction is required. • A Dig Safe™ call is NOT coordination.

  7. Typical Application Requirements • Signed Application Form • General Location Map • Specific Location Plan(s) • Traffic Control Plan(s) • Documentation of Utility Coordination

  8. MaineDOT’s Web Site

  9. Web Site Resources • Policies, Rules and Specifications • Permit Application Forms • Important Links • MaineDOT’s Map Viewer, which includes: • Roads and Corridor Priorities • Compact Areas • Traffic Volumes • Work Plan Projects • Survey Information • And much, much more!

  10. Field Coordination