An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PLANNING A SUCCESSFUL MANAGEMENT PROCUREMENT CalACT Spring Conference April 20, 2011 Roy Glauthier Transportation Planning and Policy v/fax: 949.650.5956 Email: rglauthier@aol.com Planning a Successful Management Procurement CalACT 2011 Spring Conference

  2. PLANNING A SUCCESSFUL MANAGEMENT PROCUREMENT Workshop Goal: To share tips, techniques and approaches that will improve your odds of carrying out a trouble-free procurement for contracted transit or paratransit management. Planning a Successful Management Procurement CalACT 2011 Spring Conference

  3. Overview of Procurement Process Sources of Procurement Guidance Terminology Contracting Market Should You Go To Bid? Setting a Realistic Procurement Timeline Expert Panel: Pitfalls and Problems Workshop Outline Planning a Successful Management Procurement CalACT 2011 Spring Conference

  4. Workshop Rules • Questions are welcome/encouraged. • No experts here, we’re all still learning, too. Any questions? Planning a Successful Management Procurement CalACT 2011 Spring Conference

  5. RFP development RFP release/publication Preproposal conference & question period Addenda/clarifications Proposal submission Evaluation Interviews BAFO/negotiations Selection/staff report Award Contract finalization Transition Start-up Month One Monitoring & management Repeat as needed Elements in the Procurement Process Planning a Successful Management Procurement CalACT 2011 Spring Conference

  6. Primary Sources for Procurement Guidance: • Federal Transit Administration Best Practices Procurement Manual Available at: http://www.fta.dot.gov/funding/thirdpartyprocurement/grants_financing_6037.html[do not print…. 694pp] • FTA Triennial Review Workbook http://www.fta.dot.gov/funding/oversight/grants_financing_10924.html • Your agency’s procurement policies. Planning a Successful Management Procurement CalACT 2011 Spring Conference

  7. CalACT/RTAP Contracting Workshops • 1-Day Workshops on Effective Contracting coming in July [Northern CA] and October [Southern CA] • Webinar on Effective Contracting [3, 2-hour sessions, timing tbd] Planning a Successful Management Procurement CalACT 2011 Spring Conference

  8. Critical Terminology • Bid versus Competitive Procurement -- Bid requires very clear specifications -- Competitive Procurement is intended to permit competition on quality and other factors, as well as on price Planning a Successful Management Procurement CalACT 2011 Spring Conference

  9. Critical Terminology Types of Procurements*: • Professional Services Agreement • Sole Source • Negotiated Procurement • Competitive Procurement *Depending on your agency’s procurement policies Planning a Successful Management Procurement CalACT 2011 Spring Conference

  10. Overview of the Contracting Market • Major National Firms • Regional Firms • Local Transportation Firms Planning a Successful Management Procurement CalACT 2011 Spring Conference

  11. Overview of the Contracting Market • Major National Firms • Regional Firms • Local Transportation Firms • Focus on performance-based specifications • Clearly indicate criteria for selection • Seek broadest possible participation in process Planning a Successful Management Procurement CalACT 2011 Spring Conference

  12. Step 1: Should you go to out to bid or not? • What does your existing contract say about contract term and options? • What objectives will be achieved by a competitive procurement? • Could these be achieved through negotiations with existing contractor? Planning a Successful Management Procurement CalACT 2011 Spring Conference

  13. RFP development RFP release/publication Preproposal conference & question period Addenda/clarifications Proposal submission Evaluation Interviews BAFO/negotiations Selection/staff report Award Contract finalization Transition Start-up Month One Monitoring & management Repeat as needed Step 2: Determining Your Procurement Timeline Planning a Successful Management Procurement CalACT 2011 Spring Conference

  14. Step 2: Determining Your Procurement Timeline • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  15. Step 2: Determining Your Procurement Timeline • Contract Award December 1, 2011 • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  16. Step 2: Determining Your Procurement Timeline • Evaluation and Interviews November 1-24, 2011 • Contract Award December 1, 2011 • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  17. Step 2: Determining Your Procurement Timeline • PROPOSALS DUE 5:00 pm PDT October 29, 2011 • Evaluation and Interviews November 1-24, 2011 • Contract Award December 1, 2011 • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  18. Step 2: Determining Your Procurement Timeline • Addenda and Answers Distributed October 22, 2011 • PROPOSALS DUE 5:00 pm PDT October 29, 2011 • Evaluation and Interviews November 1-24, 2011 • Contract Award December 1, 2011 • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  19. Step 2: Determining Your Procurement Timeline • Deadline for Submission of Questions October 15, 2011 • Addenda and Answers Distributed October 22, 2011 • PROPOSALS DUE 5:00 pm PDT October 29, 2011 • Evaluation and Interviews November 1-24, 2011 • Contract Award December 1, 2011 • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  20. Step 2: Determining Your Procurement Timeline • Voluntary Pre-proposal Conference October 13, 2011 • Deadline for Submission of Questions October 15, 2011 • Addenda and Answers Distributed October 22, 2011 • PROPOSALS DUE 5:00 pm PDT October 29, 2011 • Evaluation and Interviews November 1-24, 2011 • Contract Award December 1, 2011 • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  21. Step 2: Determining Your Procurement Timeline • Request for Proposals Issued October 1, 2011 • Voluntary Pre-proposal Conference October 13, 2011 • Deadline for Submission of Questions October 15, 2011 • Addenda and Answers Distributed October 22, 2011 • PROPOSALS DUE 5:00 pm PDT October 29, 2011 • Evaluation and Interviews November 1-24, 2011 • Contract Award December 1, 2011 • START OF SERVICEJanuary 1, 2012 Planning a Successful Management Procurement CalACT 2011 Spring Conference

  22. Step 2: Determining Your Procurement Timeline Critical Considerations in Setting Timeline: • Acquisition and Preparation of • Vehicles • Facilities • Computers and software, other equipment • Internal City/Agency Reviews and Approvals • Review and approval of RFP document by management, legal counsel, risk management, etc. • Council/governing body approval of RFP, selection, award • Practical Considerations • Holiday periods • Governing Board meeting schedule • Coordinating contract timing to fiscal year • Others? Planning a Successful Management Procurement CalACT 2011 Spring Conference

  23. Step 3: Fundamental Concepts of a Successful Procurement Process Guidelines: • Transparency • Define your process, then follow it • Fairness, level playing field • Establish Sole Point of Contact • Win/Win/Win -- Agency, Contractor, Public Planning a Successful Management Procurement CalACT 2011 Spring Conference

  24. Developing Your Request for Proposals • Start with a good sample RFP… or several Why reinvent the wheel? • Give yourself/your agency plenty of time • Get outside review Planning a Successful Management Procurement CalACT 2011 Spring Conference

  25. Major Parts of RFP Document • Solicitation • Terms of procurement, evaluation criteria and protest process, checklist of proposal contents • Sample contract • Scope of Work • Attachments -- Anticipate bidders’ requests: Copies of monthly reports, present wage scales and benefits, fleet schedule and mileages, detail on provided equipment, facilities and furnishings Planning a Successful Management Procurement CalACT 2011 Spring Conference

  26. Key Elements in Contract Document • Term of contract and any option periods Planning a Successful Management Procurement CalACT 2011 Spring Conference

  27. Key Elements in Contract Document • Term of contract and any option periods • Termination for cause and for convenience Planning a Successful Management Procurement CalACT 2011 Spring Conference

  28. Key Elements in Contract Document • Term of contract and any option periods • Termination for cause and for convenience • How compensation will be paid • Fixed Rate [per Rev Vehicle Hour, RVM, passenger] • Fixed and Variable – usually fixed payment per month for fixed cost reimbursement plus specified amount per hour or mile operated during billing period • Pass-through or Cost reimbursement – useful for cost items out of contractor’s control [e.g. fuel, facility rent, public phones] Planning a Successful Management Procurement CalACT 2011 Spring Conference

  29. Key Elements in Contract Document • Term of contract and any option periods • Termination for cause and for convenience • How compensation will be paid • Insurance Requirements Planning a Successful Management Procurement CalACT 2011 Spring Conference

  30. Key Elements in Contract Document • Term of contract and any option periods • Termination for cause and for convenience • How compensation will be paid • Insurance Requirements • Emergency response: • Expected actions • Terms of compensation Planning a Successful Management Procurement CalACT 2011 Spring Conference

  31. And, in case your project uses Federal funds….. Planning a Successful Management Procurement CalACT 2011 Spring Conference

  32. Exhibit 6.1 Required Third-Party Contract Clauses Required Certifications, Reports and Forms Other Required Items Exhibit 6.2 Applicability of Third-Party Contract Clauses [breaks down applicability by type of procurement & dollar value] Applicable Federal Clauses – See FTA Triennial Review Workbookhttp://www.fta.dot.gov/funding/oversight/grants_financing_10924.html Planning a Successful Management Procurement CalACT 2011 Spring Conference

  33. Key Elements in Scope of Work • Definitions • Description of services to be operated [hours, days, routes, service levels, policies] Planning a Successful Management Procurement CalACT 2011 Spring Conference

  34. Key Elements in Scope of Work • Definitions • Description of services to be operated • Performance standards, penalties/incentives, how defined and measured Planning a Successful Management Procurement CalACT 2011 Spring Conference

  35. Key Elements in Scope of Work • Definitions • Description of services to be operated • Performance standards, penalties/incentives, how defined and measured • Detailed Responsibilities of Agency and Contractor Planning a Successful Management Procurement CalACT 2011 Spring Conference

  36. Key Elements in Scope of Work • Definitions • Description of services to be operated • Performance standards, penalties/incentives, how defined and measured • Detailed Responsibilities of Agency and Contractor • Staffing: key positions, qualifications, retention/replacement and approval Planning a Successful Management Procurement CalACT 2011 Spring Conference

  37. Key Elements in Scope of Work -- Continued • Specifications for vehicles and equipment to be provided by contractor or supplied by agency Planning a Successful Management Procurement CalACT 2011 Spring Conference

  38. Key Elements in Scope of Work -- Continued • Specifications for vehicles and equipment to be provided by contractor or supplied by agency • If DAR, operating details Planning a Successful Management Procurement CalACT 2011 Spring Conference

  39. Key Elements in Scope of Work -- Continued • Specifications for vehicles and equipment to be provided by contractor or supplied by agency • If DAR, operating details • Fuel cost arrangements Planning a Successful Management Procurement CalACT 2011 Spring Conference

  40. Working With Your Contractor • Work to develop a partnership … both parties must succeed; • Manage, don’t micro-manage; • Don’t get between company and its employees; • Strive for consistency and clear direction; and • Be familiar with actual operations, employees, services. Planning a Successful Management Procurement CalACT 2011 Spring Conference

  41. Expert Contracting Panel • Dave Smith, MV Transportation Authority • Sandi Schmidt, Transportation Concepts Planning a Successful Management Procurement CalACT 2011 Spring Conference