1 / 16

TRACECA PROJECT EVALUATION

TRACECA PROJECT EVALUATION. Construction of the bypass of 3 villages along the M3 National Road Chisinau- Giurgiulesti. Project objectives. The project main objectives

ezra
Download Presentation

TRACECA PROJECT EVALUATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRACECA PROJECT EVALUATION

  2. Construction of the bypass of 3 villages along the M3 National Road Chisinau- Giurgiulesti

  3. Project objectives The project main objectives to create a prerequisite for regional economic development trough agricultural markets extension, enhancing access to social services; to reduce transportation costs and travel time for international and national operators, and passengers; to allow employment of population; to direct heavy traffic out of the residential areas; to enhance environmental quality; and to enhance traffic safety on the corridor.

  4. Project location

  5. Regional CriteriaNetwork description One of the main roads giving direct access to EU and Ukraine. Provides the mostimportant and shortest link between Chisinauand Giurgiulesti International Free Port – giving access to theDanube and the Black Sea. TheM3 corridor is an integral part of theTRACECA Network and European Road E584 Poltava – Kirovograd –Chisinau –Giurgiulesti – Galati – Slobozia. Itprovides a link between TEN corridors IV andIX.

  6. Regional Criteria Part of TRACECA E584 AGR Access to TEN Corridors VII and IX Interconnects Moldova, Romania and Ucraine

  7. Regional Criteria Giurgiulesti International Free Port • Moldova's only port accessible to sea-going vessels, • situated on the River Danube in the South of Moldova. • benefits from its location on international trade and transportation routes - Rhine-Main-Danube waterway corridor which connects the Black Sea, 14 European countries and the North Sea; • European standard and Russian railway systems as well as the international road network.

  8. Regional CriteriaAlternatives Alternatives comparison Existing alignment Proposed alignment

  9. Technical Criteria • The project represents new construction of a 20.5 km long road section along the M3 Corridor. • As a section of the M3 corridor, the proposed project ensures connection with the International Free Port Giurgiulesti and rail terminals. • Beginning spring 2011 the Port will beneficiate from the dry cargo terminal, including a dedicated container terminal. This will allow intermodal freight transport. • The geometrical parameters and location conditions of the project will allow essential improvement of the traffic safety and security.

  10. Technical Criteria Travel cost savingsTravel time savings

  11. Economic Criteria • Feasibility study in place. • Detailed design and bidding documents ready at the end of June 2011. • Estimated project repayment time 9.5 years • Forecast years 20 years • Investment costs 15.6 m euro • Economic Internal Rate of Return 12.2% • At this stage no private investors interest in the project showed. After traffic flow will exceed 10000 aadt, concession or PPP will be possible. • The national legal framework allows concession and PPP

  12. Environmental Criteria • Pollution The environmental impact will be insignificant because the proposed alignment will not cross any settlements, the vehicles engine work will be optimum and the pollutant emissions will decrease.

  13. Environmental Criteria • Noise Sensitive receptors are the residential areas within villages and towns. Because the project avoids traversing any settlement area impact of this project is considered as low.

  14. Environmental Criteria • Energy consumption After the project implementation the energy consumption will considerably decrease due the smoother engine function.

  15. Environmental Criteria • Diversion from sensible areas (living areas, preserving natural resources, others) The project will not cross resident areas. Impact on soils, fauna, flora and vegetation, is considered high. Impact on ground and surface water is considered medium.

  16. Political Criteria • When to start? The anticipated begin of construction works in 2013/14. • Government Support The project is policy supported through the Land Transport Infrastructure Strategy for 2008-2017. • Dependance on other step/project Implementation of the proposed project doesn‘t depend on other projects.

More Related