Marin Community College DistrictCampus Organizations’ Briefing Week of September 19-23, 2005
Demographics • Kentfield Campus (KTD) - Kentfield • Built – Original Buildings Date Back to 1926 • Acreage – 87 Acres / 373,806 sf / 18 Buildings • Parking – 1,774 • Indian Valley Campus (IVC) – Novato • Built – 1975 • Acreage – 333 Acres / 171,549 sf / 22 Buildings • Parking - 900 • Bolinas Marine Biology Center • Partial Modernization – 1964 • Acreage - .5 Acres / 4,178 sf / 3 Buildings & a Dock • District-wide • 6,943 Students • 4,049 Student FTES • 340 Faculty and Staff
Kentfield CampusTentative Project List • Modernization of Learning Resource Center – 66,000 gsf • Modernization of Harlan Center – 25,651 gsf • Modernization of Fusselman Hall – 14,717 gsf • Modernization of Science Center – 50,837 gsf • Modernization of Fine Arts Center – 79,636 gsf • Modernization of Student Center – 36,227 gsf • Modernization of Diamond Physical Ed Center – 36,392 gsf • Multi-purpose, Child Care & Support Facility – 75,000 gsf – New Construction • Liberal Arts Complex or Science Building - 75,000 gsf – New Construction • Facilities Maintenance Center 30,000 gsf – New Construction • Gateway Entrance Plaza – New Construction
Indian Valley CampusTentative Projects List • Modernization of Pomo Center - 47,494 gsf • Modernization of Administrative & Children’s Center - 19,588 gsf • Capital Renewal & Expansion of Central Plant - 2,000 gsf • Capital Renewal of Library – 14,280 gsf • Capital Renewal of Miwok Cluster – 28,410 gsf • Capital Renewal of Ohlone Cluster – 20,543 gsf • New Pedestrian & Bicycle Bridges (removal of (2) construction bridges) • Stream Erosion Mitigation
Bolinas Marine Biology Center • Modernization or New Construction – 3,333 gsf
District-WideTentative Projects List • Telecommunications • Infrastructure • Site • Parking & Roadways • Utilities (Sanitary, Storm, Electrical, Gas) • Fire Alarm Replacement • Access Controls / Security • ADA Accessibility • Wayfinding
Program Schedule • District-Wide Consultants • Assessment Studies - September 2005 to December 2005 • Systems Analysis - September 2005 to December 2005 • Space Inventory (update to Chancellor’s Office by 10/1/05) • Educational Master Plan (EMP) • Preliminary - November 2005 • Final - April 2006
Program Schedule (cont.) • Master Planning/District Standards - October 2005 to April 2006 • Environmental Review - January 2006 to November 2006 • Program Definition Document - September 2005 to April 2006 • Kentfield Campus Initial Project Programming • December 2005 to March 2006 • Indian Valley Campus Initial Project Programming • December 2005 to March 2006
District Architect • Campus Master Planning • Design & Drafting Guidelines • Interior & Exterior Finish Standards • Furniture, Fixtures & Equipment Standards
District Landscape Architect Services • Master Planning • District Standards • Design Guidelines
District Civil Engineering • Update all Surveys (Topographic & Boundary) • Locate, map, Identify, Inspect & Analyze all Utilities • Identify all Easements & Encumbrances on District Property • Create Accurate Electronic “As-Built” / Record Drawings that Record all Above Information • Develop District Standards and Design Guidelines
District Geotechnical Engineering • Collect and Synthesize all Existing Soils Testing and Analysis Information • Recommend and/or Perform Additional Soils Testing & Analysis • Perform Geologic Hazards Analysis • Provide Design parameters for Building and Infrastructure Design
Mechanical and Plumbing Engineering • Chilled Water Systems • Heating Hot Water Systems • Co-Generation / Central Plant Systems • Water Distribution Systems • Building and Site Mechanical Systems • Savings by Design • Building and Site Control Systems
Electrical Engineering • Substations • Co-Generation • Electrical Distribution Systems • Lighting • Savings by Design • Control Systems • MCC
California Environmental Quality Act (CEQA) • Provides review, analysis & studies to assess the District’s development plan and its impact on the environment in accordance with the California Environmental Quality Act. • Prepares & Produces Required Documentation • Negative Declaration • Mitigated Negative Declaration • Environmental Impact Report(s)
Next Steps • Board of Trustee Retreats • September 20th – Facilities Master Planning • October 11th – Program Controls • Facilities Workshop on Sustainability & Environmental Stewardship • September 30, 2005 – 9 A. M. to 3 P. M. • (Initial Sustainability Summit Held September 9th)
Next Steps • Campus Forums • Indian Valley Campus, October 25, 2005 • 2 PM to 3 PM, Pomo 188 • Kentfield Campus, October 27, 2005 • 2:30 PM to 3:30 PM, Olney Hall • Community Forums • Indian Valley Campus, November 1, 2005 • 7 PM to 8 PM, Pomo 188 • Kentfield Campus, November 3, 2005 • 7 PM to 8 PM, Olney Hall
Next Steps • Educational Master Plan – Road map to future • District Consultants • Design Guidelines • Building Standards • FF & E Standards • District Assessments and Surveys • Program Definition • Scope / Schedule / Budget
Next Steps • Projects in Design • Kentfield • Roof Repairs – Harlan Center and LRC (Oct to Nov 2005) • Partial Roof Replacement – Physical Education Building (Apr to Jun 2006) • Tree Trimming and Removal (Dec 2005 to Feb 2006) • Demolition of Larkspur Annex (Dec 2005 to Mar 2006) • Indian Valley • Wildfire Mitigation (Oct 2005 to Feb 2006) • Partial Gas Main Replacement (Nov to Dec 2005) • Tree Trimming and Removal (Jan to Mar 2006) • Stream Erosion Mitigation (May to Sep 2006)
Other Issues • Kentfield • Title 9 Compliance (PE Complex) • Indian Valley • Bridge Load Testing • Bolinas • Geologic Hazards Study
Questions & Answers Dave Kirn Program Manager (415) 884-3192 Dave.Kirn@marin.cc.ca.us José D. Nuñez Director of Modernization (650) 358-6936 Jose.Nunez@marin.cc.ca.us Elizabeth Tucker Senior Project Field Administrator (415) 884-3139 Elizabeth.Tucker@marin.cc.ca.us