POCANTICO HILLS CENTRAL SCHOOL. BOARD OF EDUCATION PROJECT UPDATE AUGUST 6, 2009. Schedule. SED Approval………………… Within 2 weeks Health Dept Approval……. Within 2 weeks Bidding/Award..………………….. Sept 2009 Construction ………. Oct 2009 – Feb 2011 Closeout …………………………….. Mar 2011
E N D
POCANTICO HILLS CENTRAL SCHOOL BOARD OF EDUCATIONPROJECT UPDATEAUGUST 6, 2009
Schedule • SED Approval………………… Within 2 weeks • Health Dept Approval……. Within 2 weeks • Bidding/Award..………………….. Sept 2009 • Construction ………. Oct 2009 – Feb 2011 • Closeout …………………………….. Mar 2011 *Approval times are estimated based on past history
Design Status • Pool • Presentation of rendering • Recommending removal of slide and water feature • Gymnasium • Added locker room toilets and showers as alternate