300 likes | 344 Views
PROJECT DELIVERY METHODS. (Refer to Chapter 4). INTRODUCTION. A project delivery method is a system used by an agency or owner for organizing and financing design, construction, operations, and
E N D
PROJECT DELIVERY METHODS (Refer to Chapter 4)
INTRODUCTION • A project delivery method is a system used by an agency or owner for organizing and financing • design, • construction, • operations, and • maintenance services for a structure or facility by entering into legal agreements with one or more entities or parties. • Project delivery method describes • how the participants are organized to interact, transforming the owner’s project goals and objectives into a finished facility.
INTRODUCTION (CONT.) • The owner usually considers the following factors to decide how project resources are to be organized: • Past practices, traditions, and experience; • The advice of consultants; • Funding sources and constraints; • The effective use of staff and working capital; • The interests of other project stakeholders.
OWNER-PROVIDED DELIVERY • Mostly applicable to projects where the scope of the work is within the owner’s range of skills, experience, and resources. • Owners perform some or all of the design services and construction work themselves. • e.g. simple modifications to an existing facility, projects with limited cost or complexity, repetitive projects.
DESIGN BID-BUILD (DBB) • DBB has been the most common method of project delivery for public projects, and for many private projects as well.
DBB • Design Bid-Build is effective on projects • where the owner needs both professional design services and construction services • where the designer does not require detailed knowledge of the means and methods of construction.
DBB • DBB provides the owner with a high degree of control. • Preferred project delivery system for owners who: • Wish to closely monitor projects • Are public owners and must account in detail for expenditures. • Are obligated by statute to procure professional design services by qualifications-based selection (QBS) regulations and constructors by competitive bidding.
DBB • The owner • defines project goals and objectives, • secures the financing, and • specifies the standards and contract terms. • The owner may perform • planning, conceptual design and full design, or may engage an outside design professional (designer) for some or all of these tasks. • During this planning and preliminary stage, owner and designer work as a team to obtain required permits and conduct necessary site investigations.
DBB • The designer provides • Complete architectural and engineering design services • Complete construction bid documents • Prospective contractors prepare their bids from these complete and specific bid documents. • The bidders submit their proposals to the owner (often w/ designer) , who determines the most responsive (typically the lowest) bid meeting project requirements. • In certain circumstances, owner may select a contractor outright and negotiate contract terms directly.
DBB • Advantages • Known quantity to all parties • Well-defined contractual relationship • Firm fixed-price contract • Contains considerable contractual protection to owner • Insulated from many of the risks (e.g. cost overrun, labor inefficiency, etc.) • Disadvantages • Quality of constructor may not be assured • Usually more time consuming • Lack of coordination among participants
CONSTRUCTION MANAGEMENT (CM) • Many owners engage construction managers (CMs) to assist in developing bid documents and overseeing project construction. • CM: • A professional or a firm trained in the management of construction processes. • Generally interposed between the owner and some or all of the other participants.
CM • Two general types • Agency Construction Managers (ACM) • Construction managers-at-risk (CM-at-risk)
CM • ACM acts as an agent of the owner and extends the owner’s internal capabilities in performing traditional owner responsibilities. • The level of service by the ACM can range from on-call advice to full project management. • In some cases, the owner hires the ACM before design begins and ACM may participate in the selection of and contracting with the designer or might even be the designer.
CM • CM-at-risk typically contracts with the owner in two stages. • Manages and undertakes services during conceptual & preliminary design phases with the design professional. • On completion of design, owner and CM-at-risk then agree on a price and schedule for the completion of the construction work.
CM • Advantages • Reduced change orders and claims • Owner approval of subcontractors • Good communication among all parties • Disadvantages • Higher cost to owner due to reduced competition
DESIGN-BUILD (DB) • A single entity to provides both design and construction services. • Contract may either be negotiated with a single design-builder or result from competitive proposals.
DB • Selection can be based on low price or on a set of value criteria (experience, staff, bonding capacity, etc.) or both. • Provides the owner with a single point of contact for project responsibilities, eliminating the need to assist in resolving designer-contractor disputes.
DB • Costs are typically defined and maintained to a higher degree. • Coordination of fast-track management to achieve early completion is greatly simplified. • Makes many decisions that owner would make under DBB, due to delegation of increased authority.
DB • Advantages • Better communication among all parties • Allows construction input early in design phase • Easier incorporation of changes, if any • A clear understanding and documentation of design-build processes enhances the quality of design-build projects • Disadvantages • Initial cost may be higher due to increased contractor risk • Lack of checks and balances
CONTRACT TYPES • Purchase of actual construction service • Lump sum • Single fixed price • Unit price • Price per unit of the different elements of the construction project • Reimbursable • Cost plus fixed fee • Guaranteed maximum price (GMP) • Cost plus percentage fee
DESIGN-BUILD VARIATIONS • Funding Option Variations • Turnkey • Developer Financed Projects • Turnkey Variations
Funding Option Variations • Private capital and developer participation offer private owners several variations on design-build. • Lease-develop-operate arrangement: • The owner gives a private operator a long-term lease to use, operate, and expand an existing facility. • Public-private partnership or wrap around: • Ownership of or fiduciary responsibility for a project is assigned to a private party. • That party designs, builds, and may even own, operate and maintain the new facility.
Turnkey • Turnkey adds to the design-builder’s responsibilities the operation and/or maintenance of the completed project. • Turnkey delivery has the potential for bringing a new project on line more quickly. • Three forms of turnkey project delivery: • Design-build-operate-transfer • Design-build-operate-maintain • Design-build-own-operate-transfer
Developer-Financed Projects • For highly specialized projects and circumstances, financing from a private or public developer or other third parties can offer additional variations on design-build and turnkey project delivery, each with new roles for owners, designers, and contractors.
Turnkey Variations • Variations on turnkey add financing as a key component. While financing arrangements are unique for each project, developer financed projects generally resemble one of the turnkey delivery methods: • FDBT (Finance, design, build, transfer) • FDBOT (Finance, design, build, operate, transfer) • FDBOOT (Finance, design, build ,own, operate, transfer) • In each case, the transfer of the project occurs only after the developer’s interests and financial obligations have been satisfied.
FAST-TRACKING • Fast-track approach compresses the schedule by sequencing the start of construction on underlying project elements (e.g. foundation, basic supporting structures) before final design is complete for interior or adjacent elements. • Fast-tracking is not a method of delivery, rather, it’s a management strategy within delivery methods. • While often successful in achieving schedule reductions, problems on fast-track contracts can create a domino effect on follow-on contracts for the project. • Fast-track is more successful on projects that are straightforward and have a high level of predictability.
Current Trends • DB is the predominant delivery method in Europe and Japan • Steady increase in United States and Canada (graph) • Contractor-led has 95% of the market