www.kdheks.gov. KDHE – BAR Air Permitting Update. Marian Massoth, P.E. Chief, Air Permitting Section KDHE - Bureau of Air and Radiation March 5, 2008. KDHE BAR - Permitting Organization. Permit Section – Marian Massoth Three Permit Units Power Plants VOC Sources
E N D
www.kdheks.gov Our Vision – Healthy Kansans living in safe and sustainable environments.
KDHE – BARAir Permitting Update Marian Massoth, P.E. Chief, Air Permitting Section KDHE - Bureau of Air and Radiation March 5, 2008 Our Vision – Healthy Kansans living in safe and sustainable environments.
KDHE BAR - Permitting Organization Permit Section – Marian Massoth Three Permit Units • Power Plants • VOC Sources • Agricultural and Natural Resources Technical Resources – Ralph Walden BAR Technical Assistance Wyandotte County – Bruce Anderson Our Vision – Healthy Kansans living in safe and sustainable environments.
3 Air Permitting Units 1/3 John Ramsey, Supervisor Bert Buckland Terry Tavener Sergio Guerra (Vacancy) • Ethanol Plants • Cement Plants • Mineral Products Industry • Incinerators • Grain Industry Our Vision – Healthy Kansans living in safe and sustainable environments.
3 Air Permitting Units 2/3 David Peter, Supervisor Rasha Allen Justin Cunningham (2 Vacancies) • Chemical Processing Plants • Aerospace Industry • Fertilizer Plants • Fiberglass Industry • Foundries • Refinery Transition Our Vision – Healthy Kansans living in safe and sustainable environments.
3 Air Permitting Units 3/3 Mindy Bowman, Supervisor Rick Bolfing Jason Heitman (Vacancy) • Power Plants • Landfills • Government Facilities • PSD Dispersion Modeling Transition Our Vision – Healthy Kansans living in safe and sustainable environments.
Technical Resources Ralph Walden, Supervisor Dana Morris Mike Parhomek • Technical Assistance to Bureau • Technical Training for Staff • Natural Gas (NSR Reform/Streamline) • Refineries (transition) • PSD Modeling (transition) Our Vision – Healthy Kansans living in safe and sustainable environments.
Wyandotte County, Dept. of Air QualityPermitting Contacts • Bruce S. Andersen, Director bandersen@wycokck.org • Andrew Beard, Environmental Engineerabeard@wycokck.org • Katrin Ravenscroft, Environmental Engineerkravenscroft@wycokck.org • Amber Davis, Environmental Engineeradavis@wycokck.org Our Vision – Healthy Kansans living in safe and sustainable environments.
EPA Air Permitting and EnforcementNew Contacts • Mark Smith • Chief of the Air Permitting & Compliance Branch (formerly JoAnn Heiman) • Patricia Scott • Air permits coordinator for Kansas (formerly Jon Knodel) Our Vision – Healthy Kansans living in safe and sustainable environments.
Considerations for Obtaining a Timely Permit: • Pre-application meetings with KDHE • Completeness of application • Timely response to agency’s comments during review • Minimal changes to application • Applicant-hosted public information meetings • Concurrent notices for public notice and public hearing • Environmental Protection Agency enforcement issues • Retaining permit engineers (salary disparity between state and private industry) Our Vision – Healthy Kansans living in safe and sustainable environments.
KDHE Steps toStreamline Permit Process • Applicant provides electronic copy of permit application and a proposed draft permit • Public notice for the draft permit and tentative public hearing is published concurrently • Informational meeting with the proposed facility to discuss project details requirements Our Vision – Healthy Kansans living in safe and sustainable environments.
Ethanol Permits EPA Region VII Assistance • User-friendly manual • Identifies environmental regulatory rules and requirements for construction and operation of ethanol production facilities http://www.epa.gov/region07/priorities/agriculture/ Our Vision – Healthy Kansans living in safe and sustainable environments.
BAR Permit Regulatory Timelines Regulatory timeline - 18 months after receipt of application • In accordance with Kansas Statute KSA 3008b(h)3 • Construction Permit application timeline begins when application is deemed complete • Operating Permit application must be submitted within 6 to 18 months prior to permit renewal date. Source may continue to operate if permit expires prior to renewal date Our Vision – Healthy Kansans living in safe and sustainable environments.
BAR Permit Goals • 180-days for PSD construction permits, other complex permits, & Class I operating permits • 60 days for regular construction permits and Class II operating permits • 30 days for approval construction documents • 10 days for standard construction permits/approvals and responses Our Vision – Healthy Kansans living in safe and sustainable environments.
Air Permits and Approvals Processed in 2007 BAR also processed 143 additional applications which resulted in responses. Our Vision – Healthy Kansans living in safe and sustainable environments.
Air Permits and Approvals Processed in 2006 BAR also processed additional 213 applications which resulted in responses. Our Vision – Healthy Kansans living in safe and sustainable environments.
Bureau of Air and Radiation Air Permits Issued - 2007 • Productivity: 2007 • 650 Permits, Approvals and Responses • 84% processed within goal timelines 2006 • 576 Permits, Approvals and Responses • 75% processed within goal timelines Our Vision – Healthy Kansans living in safe and sustainable environments.
Bureau of Air and Radiation Customer Satisfaction • Survey results from permit sources regarding service provided by BAR permitting section (from fiscal year, 2007): • 118 Surveys Sent • 70 Surveys received • 95% of Surveys were Satisfactory or above Our Vision – Healthy Kansans living in safe and sustainable environments.
Marian MassothBureau of Air and RadiationKansas Department of Health & EnvironmentCurtis State Office Building1000 SW Jackson, Suite 310Topeka, Kansas 66612www.kdheks.govvoice 785.296.0616fax 785.291.3953mmassoth@kdhe.state.ks.us Our Vision – Healthy Kansans living in safe and sustainable environments.
www.kdheks.gov . Our Vision – Healthy Kansans living in safe and sustainable environments.