1 / 25

Ken Davis Vice President Engineering & Operations

Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority. Ken Davis Vice President Engineering & Operations. KUA System Data. Serves approximately 64,000 customers in Osceola County Distribution 857 Miles of Distribution Lines

ffrick
Download Presentation

Ken Davis Vice President Engineering & Operations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Florida Public Service Commission2007 Hurricane Preparedness BriefingMay 23, 2007Kissimmee Utility Authority Ken Davis Vice President Engineering & Operations

  2. KUA System Data • Serves approximately 64,000 customers in Osceola County • Distribution • 857 Miles of Distribution Lines • 41 % Overhead • 59 % Underground • 9 Substations • 47 Feeder Circuits • 15,000+ Poles (majority wood)

  3. KUA System Data • Transmission • 72 Miles of Transmission Lines • 230 kV and 69 kV • 63% of Poles Concrete or Steel • 37% Wood (will reduce to 27% by 2008)

  4. 2004 Hurricane Experience • Charley • 100 % Customers Lost Power • Frances • 36 % of Customers Lost Power • Jeanne • 59 % of Customers Lost Power

  5. Lessons Learned • Hired James Lee Witt, Associates to Conduct Independent Assessment of Preparation for and Recovery From Storms • Improve Communications with Customers During Restoration • Can’t Rely Solely on Media for Communications

  6. Lessons Learned • Better Define Roles of All Employees • Closer Coordination with EOC for Restoration Priorities

  7. Hurricane Preparedness

  8. Construction Standards • Poles Designed to NESC Extreme Wind Loading • All New Construction • Major Expansions or Relocation Projects • Targeted Critical Structures

  9. Construction Standards • 27% of Wooden Transmission Poles to be Replaced with Steel and Concrete • Redundant Circuits to All Hospitals with Automatic Transfer Scheme

  10. Construction Standards • Selected Overhead to Underground Conversions • Underground Utilities Required in All New Subdivisions

  11. GIS/Outage Management • All Transmission & Distribution Facilities Tracked in GIS • Links to Outage Management System • Tracks Outages Down to Individual Customer Level

  12. Vegetation Management • Transmission Circuits • Inspected/Trimmed Annually • Distribution • Three Year Trim Cycle • Increased funding over 75% Since 2004

  13. Pole Inspection Program • All Wood Transmission Poles Inspected Every Two Years • Wood Distribution Poles Inspected on Eight Year Cycle

  14. Facility Inspection Program • Transmission System • Annual Visual Inspections • Annual Infrared Scanning • Distribution System • 5 Year Cycle on Inspections • Infrared Scans of All Circuits Annually

  15. Emergency Operations Plan • All Hazards Approach • Concentration on Hurricanes • Reviewed and Updated Annually • Follow National Incident Management System (NIMS)

  16. Emergency Operations Plan • All Employees Have Pre-assigned Roles • Defined Set of Activities for Each Phase of Storm Preparation, Response and Recovery • Pre-Defined List of Priority Facilities

  17. Emergency Operations Plan • Pre-Assigned Damage Assessment Teams • Circuits Pre-Assigned • Area Coordinators for Teams • Developing Electronic Reporting of Damage Assessment

  18. Emergency Operations Plan • Pre-Defined List of Restoration Priorities • Typical Top Priorities – Evacuation Shelters, Emergency Operations Centers, Hospitals, etc. • Priorities Can be Changed by Directive from EOC

  19. Annual Mock Disaster Drill • Full Scale Drill Practiced Annually (April 12, 2007) • All Employees Participate • Evaluation Teams Rate Performance • Post Drill Evaluation Conducted • Action Items – Changes to Processes, Facilities, Plan

  20. Storm Response and Recovery • Crews Assigned to Ride Out Storm at Selected Fire Stations • Assist First Responders with Wires Down Situations • Assist with Fire Calls for Power Disconnects

  21. Storm Response and Recovery • Personnel Assigned to EOC at All Times • Regular Status Updates Given to EOC • Close Coordination with EOC for Restoration Priorities

  22. Storm Response and Recovery • Mutual Aid Agreements • Florida Municipal Electric Association (Florida Municipal Utilities) • American Public Power Associations (National Municipal Electric Utilities) • Florida Coordinating Group (Florida Municipal, Investor Owned and Cooperative Utilities)

  23. Storm Response and Recovery • Pre-Arranged Agreements • Transmission and Distribution Line Contractors • Outside Engineering (damage assessment and construction management) • Vegetation Management (Tree Clearing) • Lodging, Catering, Laundry, etc.

  24. Customer Communications • Call Centers Fully Staffed 24/7 Throughout Recovery Process • Provide Status Updates to Customers • Emails • Voice Mails or Text Messages • Physically Place “Door Hangers”

  25. QUESTIONS? Kissimmee Utility Authority Ken Davis Vice President Engineering & Operations Phone: (407) 933-7777 Ext. 1210 Email: kdavis@kua.com

More Related