PRASE Status Update May 2, 2012. Overview of PRASE PHASE II Status. Overall Status: GREEN o n the whole, the PRASE program is moving forward as per published plans and deliverables the exception:
E N D
PRASE Status Update May 2, 2012
Overview of PRASE PHASE II Status • Overall Status: GREEN • on the whole, the PRASE program is moving forward as per published plans and deliverables • the exception: • the development of the business case for printer rationalization which has been delayed to resource issues and the need for a revised approach to completing the business case • Moving forward, additional focus is required on: • program management • benefits framework and tracking • roles and responsibilities
Phase II Scope Finance/Procurement/HR/Services for Researchers–