1 / 11

The Linac 4 RF System - overview

The Linac 4 RF System - overview. O. Brunner/AB/RF L.Arnaudon, C. Rossi, M. Vretenar, M. Timmins, D. Parchet, P. Baudrenghien,... (Linac4 MAC – Jan’08). RF power layout – boundary conditions. Initial configuration:

finnea
Download Presentation

The Linac 4 RF System - overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Linac 4 RF System - overview O. Brunner/AB/RF L.Arnaudon, C. Rossi, M. Vretenar, M. Timmins, D. Parchet, P. Baudrenghien,... (Linac4 MAC – Jan’08)

  2. RF power layout – boundary conditions • Initial configuration: • 13 klystrons 1.3 MW, 6 klystrons 2.5 MW, 3 modulators 1.3 MW, 11 modulators 2.5 MW • Final configuration (at the end of the stock of LEP klystrons, if allowed by cavity stability): • 3 klystrons 1.3 MW, 11 klystrons 2.5 MW, 3 modulators 1.3 MW, 11 modulators 2.5 MW • future upgrades: • LP(SPL), SPL

  3. Layout – RF power building • klystron racks (local control): • focus p.s., power meters, temp measurements, RF drive amplifiers...) • space for additional PIMS & power equipment: • equipment must be integrated now.. PIMS CCDTL DTL • Faraday cages: • Low level • Main PLC • diagnostic RFQ Power converters (enough space for SPL needs) M. Timmins

  4. Layout – close look (PIMS) • Very dense • can everything be installed? • hope to get ride of klystron garages (local shielding only) • Need detailed 3D integration: • supports • cable trays • water cooling • phase shifters needed? M. Timmins

  5. Layout – waveguides • Very tight • no margin to adjust WG length • RF power layout imposed by RF elements in the machine • RF & control cable • 2 passages/WG hole M. Timmins

  6. Status Equipment • Available: • more than 25 1MW LEP klystrons • Thales/EEV/Philips/Valvo • 5 – 35khours • Issue: HV connections (power converter to klystron)? • about 20 1MW LEP Circulators • AFT/ANT • Need new TCU (temperature control unit) • most of waveguides (except HH bends) • To be purchased: • 6 2.6MW klystrons (+spares) • 6 2.6MW circulators (+spares) • 13 1MW RF ferrite loads (+spares) • 12 2.6MW RF ferrite loads (+spares) • 140 HH waveguides bends • RF drivers, focus power supplies etc • simulation to be done: • half height WG ok @ 1MW? • full height WG (magicT’s) ok @ 2.6MW?

  7. Operation of the LEP CW Klystrons in pulsed mode • tests were made in 2002 to show that LEP klystrons could be re-used for future proton linacs (H. Frischholz&D. Valuch) • condition of test: • LEP modified modulator (in order to pulse HV) • RF pulse-lengths of 5 ms • pulse repetition rate of 50 Hz • peak power level of 850kW • will be tested soon in 3MeV test stand (see C. Rossi’s talk) • influence on cathode lifetime? (M-type cathodes) • 10kV between pulses? • reliability? Shape of the RF pulses

  8. new 2.6MW RF power equipment • 2.6MW klystrons: • contacts with Thales / CPI / Toshiba • preliminary design specifications: • frequency: 352MHz • peak power: 2.6MW • duty cycle: 5% • RF pulse width: 1ms • beam voltage: 110kV • beam current: 50A • RF gain: 35 – 37 dB • DC -> RF efficiency: 45 – 50% • klystron heater? • power converter – klystron cabling? • delivery time: • 12-14 months after the order is placed • delivery schedule (LHC): 1 tube/2months • 2.6MW circulators and RF loads • contacts with AFT • delivery time (6-8 months after the order is placed)

  9. Interlock module Slow Controls Structure • based on LHC RF control system • “proto” installed in 3MeV test stand L. Arnaudon

  10. conclusions • RF power integration: • lots of work done: overall layout looks fine (Faraday cages, RF power, WG, racks, cable routing) • basically compatible with future upgrades (for SPL) • need detailed 3D integration of: • RF power equipment for the PIMs • WG support system (from surface to machine) • cable routing (from RF structure to Faraday Cage) • additional PIMS & related equipment • is it ok to feed 2 RF structure with 1 klystron? do we need “active” phase shifters? • RF power equipment • 1.3MW system: tests will start soon in 3MeV test stand • 2.6MW RF system: • final specs to be written / call for tender / order to be placed • need simulation of the WG system, in particular for the Magic’T • slow control system • based on LHC slow control system • “proto” ready for the 3MeV test stand

More Related