190 likes | 366 Views
LINAC System Overview Jose Chan. Organization E-Beam Linac overview 2006 installations Problems and lessons learned 2007 installation status 2008 installation status CR Impact 6-Months Look-ahead. LCLS Injector/Linac Organizational Chart.
E N D
Organization E-Beam Linac overview 2006 installations Problems and lessons learned 2007 installation status 2008 installation status CR Impact 6-Months Look-ahead
LCLS Injector/Linac Organizational Chart Mechanical engineers matrix into Injector/Linac organization Installations are supported by different operation groups and/or contractors Jim Turner coordinates all safety concerns with Safety Overview committeesand has safety oversight for Linac Continue to support commissioning
LINAC System Overview Sector 21 Sector 20 2006 Installation Laser stopper BLM BC1 LX L1 Ins/SAB Wall
LINAC System Overview LTU/Dump Install First Spont. Light CF Early Occupancy e- beam & Photon Systems Checkout CD-4a S O N D J F M A M J J A S O N D J F M A M J J A S O N D 2007 2008 2009 PPS PPS Photon Flux Measurements Controls checkout Re-commission Inj/BC2 to SL2 LTU/Und/FEE Commissioning Linac/BC2 Commissioning BC2 & L3 Install FEL Commissioning
2006 Installation • Many designs were not completed on time for manufacturing and installation • Many components designed for 2006 installation are same as 2007/2008 installation • Implemented new BOM tracking schedule for 2007 and 2008 installations • There were some components and supports that did not fit during 2006 installation these were due to design error. • All drawings are checked for fit before installation • 2006 commissioning encountered many problems with diagnostic components • All components will be verified and signed off by mechanical engineer, control engineer, alignment and physicist before installation
2007 Installation Status • Linac system for 2007 downtime installations • Starts in September 4, 2007 thru December 3, 2007. • 12 weeks minus 2 weeks for PPS checkout and few days of power outages in sectors 24-30 • Divided in three areas • L2- minimal modification to the Linac • BC2 – last 3 girders of sector 24 • Modifying girders 24-7, 8 & 9 • L3- sectors 25 to 30 • Modifying girders 25-1,2,3 & 9; 27-6 & 9; 28-5 & 7; 29-4
BC2/L3 Status • BC2 Status • Design is complete except radiation shielding and seismic proofing of center movable magnet • All beam line components/supports are in MFD shop and outsourced • Delivery of first BX magnet on 7/9/07 • Completed SOW and purchase requisition for Davis Bacon installations • L3 Status • Design is complete • All beam line components/supports are in MFD • Completed SOW and purchase requisition for Davis Bacon installations • Cable installations for BC2 and L3 • Design complete • Out for vendor quote
2008 Installations • LTU (Linac to Undulator) Status • Early co-occupancy in December 2007 for installation • Divide in two areas BTH (Beam Transport Hall) west and BTH • Support stand purchase order placed, deliveries in September • Submitted SOWs to review committee for the support stand installations • e-Dump Status • 80% design complete awaiting RP for spot shielding requirements • 50% components in MFD or ready for installation (RFI) • BYD magnet design complete and is out for bid this week, expect delivery in April 2008
CR Impact • Past CR impact • No affect on BC2 and L3- design moved forward • LTU and E-Dump installations were more uncertain until March 2007. LTU design performance were affected by CR • Based on performance and schedule slip, cost impact: labor and material impact $263K • Future CR impact • No delays on LTU and E-Dump installations • Additional resources are needed to recover lost time (performance) $2.1M in TEC
6-Months Look-ahead • Complete fabrication of all BC2 and L3 components in October for September 2007 downtime installation • Complete design LTU and e-Dump • Manufacture LTU and e-Dump components • Install LTU component stands during co-occupancy