An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NDIA PMSC Baseline StabilityWorking Group May 2009 Neil Albert Pete Wynne

  2. Baseline Stability • Gerald Self - ITT • Marty Doucethe – EVM Services • Sondra Ewing – Lockheed Martin • Tom Tasker – General Atomics • Fran Fulton – Northrop Grumman • Neil Albert - MCR • Pete Wynne – Lockheed Martin • Joe Houser – KM Systems • Linda Nobel – Raytheon • Mary Ann Hale – General Dynamics • Walt Berkey – Lockheed Martin • Gary Robinson - Raytheon • Ed Silvia - Raytheon

  3. Baseline Stability Objective Adapt Program Performance Management to efficiently Integrate with the Acquisition Process given that change is inevitable. Goals • Integrate Existing Performance Management With Existing Acquisition Processes • Eliminate Waste and Reduce Re-Work in maintaining an integrated performance measurement baseline • Streamline the Program Performance and Acquisition interfaces • Minimize Deconstruction

  4. Baseline Stability Deliverables • Baseline Stability Definition • ANSI/EIA 748 EVMS Guideline Adaptability Assessment • Process Interface and Gap Analysis

  5. Attributes of Stable Baseline • Low Risk • Minimal volatility and fully defined requirements • Stable funding • Minimal changes to the contract • Milestones clearly defined • Proven/mature technologies • Committed resources to execute the plan • Predecessors meet their commitments within the boundaries of their schedule margin. • Experienced customer Work In Progress DRAFT

  6. Guideline Adaptability Assessment • G1 WBS – the minimum levels that are extended to identify the product-oriented control account(s). • G2 OBS – Adaptable to the needs of the Program life cycle. • G3 Integrate planning, scheduling, budgeting, work authorization and cost accumulation processes – Adaptable to the extent G1 and G2 are set. • G4 Identify the overhead organization – N/A • G5 OBS/WBS Integration– Adaptable to the extent G1 and G2 are set. • G6 Schedule – Adaptable from the perspective of rolling wave and/or integration. Work In Progress DRAFT