Facility Construction Committee. Construction Status Report Presentation to the. by the. Facility Construction Department. February 11, 2002 8:30 PM. Projects Under Construction (as of February 2002). Campus Start Date
E N D
Facility Construction Committee Construction Status Report Presentationto the by the Facility Construction Department February 11, 2002 8:30 PM
Projects Under Construction(as of February 2002) Campus Start Date • Sta. Maria Elementary School Oct. 2001 • Farias Elementary School Oct. 2001 • Sanchez/Ochoa Elem. School Oct. 2001 • Dovalina Elementary School Oct. 2001 • Milton Elementary School Jan. 2002 • Nixon High School Jan. 2002
Santa Maria Elementary School • Architect: Cavazos & Associates Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $4,862,700.00 • Construction Start: Oct. 31, 2001 • Start of School: Aug. 15, 2002 • Completion Date: Aug. 31, 2002 • Change Order(s): Addition of Single Sex Restrooms at PK & K.
Santa Maria Elementary School LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02.
Farias Elementary School • Architect: Ashley Humphries, & Sanchez Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $4,926,997. • Construction Start: Oct. 31, 2001 • Days in Contract: 320 Calendar Days • Completion Date: Aug. 31, 2002 • Change Order(s): Addition of Single Sex Restrooms at PK & K.
Sanchez/Ochoa Elementary School • Architect: Sepulveda & Assoc. Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 5,132,719. • Construction Start: Oct. 31, 2001 • Number Contract Days: 320 • Completion Date: Sept. 16, 2002 • Change Order(s): None
Sanchez/Ochoa Elementary School LISD: All foundation excavation is complete. All reinforcing steel is on jobsite, all beam reinforcing steel is tied and ready for installation. All of zones “D” and “E” have been poured, 14800 sf of zone “B” poured. Zone “C” to be poured week 1-21-02 along with zone “A” and pending portion of zone “B”.Metal building delivery scheduled to commence 2-15-02.
Dovalina Elementary School • Architect: Design Group International, Inc. • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 2,801,900. • Construction Start: Oct. 31, 2001 • Number Contract Days: 304 • Completion Date: Aug. 31, 2002 • Change Order(s): None
Dovalina Elementary School LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02.
Milton Elementary School • Architect: Turner Hickey & Assoc. Arch. • General Contractor: To be determined • Asbestos/Demolition: M & M Contracting, Inc. • Contract amount: $ 183,978. • Construction Start: Jan. 27, 2002 • Number Contract Days: 47 Days • Completion Date: March 15, 2002 • Change Order(s): None
Financial Overview – MiltonM & M Contracting ContractAsbestos/Demolition
Construction Time – MiltonM & M Contracting ContractAsbestos/Demolition
J. W. Nixon High School • Architect: Cavazos & Associates Architects • Contractor: Leyendecker Construction, Inc. • Contract amount: $ 9,298,985. • Construction Start: Jan. 30, 2002 • Number Contract Days: 551 • Completion Date: August. 15, 2003 • Change Order(s): None
End of Presentation Question & Answer Session