Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 1, 2010
Agenda • Latest Completed Construction Projects • LAC Bldg. J – Theater lighting control panel replacement • LAC Bldg. E – Renovation upgrades • LAC CDC – new carpet installation • PCC Bldg. II – Added new landscaping around perimeter • Current & Upcoming Construction Projects • LAC Building A, Student Services Retrofit • LAC Math Technology Building • LAC Parking Structure • LAC Building O Complex • LAC Infrastructure Improvements and District Wide – Energy Efficiency Project • LAC Building I (Bookstore) • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Building CC Retrofit • District Wide – Electronic Signage Plan • LAC South Walkway Extension • LAC Building P FPP • Planned Phasing of Future Projects • Q & A
Current and UpcomingConstruction Projects LAC Building A – Student Services Retrofit Measure E 2008 • Awaiting DSA Final approval on Structural portion • Adds 6,500 Sq. Ft. to existing building • Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. • Estimated start of construction end of Fall 2010
Current and UpcomingConstruction Projects Completed Schematic Design Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction Winter 2013 LAC Math Technology Building – Measure E 2008
Current and UpcomingConstruction Projects LAC Parking Structure – Measure E 2008 • Spaces for 900 Vehicles • Photovoltaic Electrical Generation Array on top level • To be located Southeast corner of Lot J adjacent to the Verizon building • Outfitted with single-axis tracking system • Minimum 450 KW+ output • Curriculum building opportunity • Exhibit classroom • Construction started Summer of 2010 • Anticipated end of Construction Fall 2011
Current and UpcomingConstruction Projects LAC Building O Complex – Measure E 2008 • Two structures totaling 87,000 square feet • Current Occupants: • ERD, Foundation, Warehouse Facility, and one leasee • Future Occupants: • IITS and BMT • Start of construction of Building O1 began April 2010 • Anticipated completion October 2010
Current and UpcomingConstruction Projects LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 • Project to be completed in a phased construction schedule • Total annual estimated savings of 1.5 million Kwh • Project started Fall 2009; currently working on phase 6, 9, & 10 • Landscaping upgrades to be implemented in conjunction with infrastructure project phasing • Majority of existing building HVAC systems to be upgraded and connected to the Central Plant • Exterior lighting and controls upgrades in progress • Anticipated end of construction Winter 2011
Current and UpcomingConstruction Projects LAC Building I - Measure E 2008 • Received Final DSA approval • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • Currently in Bid Phase • Construction scheduled for Fall 2010 • Bookstore Swing Space relocated July 2010
Current and UpcomingConstruction Projects PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002 • Received Final State (DOF) approval • NTP issued on 7/29/10; Contractor mobilizing • Installed portables for swing space Summer 2010 • Anticipated start of MDAB construction Fall 2010 • Project to be completed in two phases
Current and UpcomingConstruction Projects PCC Building CC Retrofit - Measure E 2008 • Currently in DSA for plan check (Structural) • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space to be located on PCC Campus (Bldg. GG) • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction 2012
Current and UpcomingConstruction Projects District Wide – Electronic Signage Plan Measure E 2008 • District Wide Signage Plan complete for LAC & PCC • Daktronics digital signs currently in fabrication • Installation of footings to begin on 9/1 • Anticipated construction completion of Marquee Signs Fall 2010
Liberal Arts Campus Site Plan l i b e r a l a r t s
Pacific Coast Campus Site Plan p a c i f i c c o a s t
Planned Phasing of Future Projects • 2009-10 • Begin infrastructure construction – Fall 2009 • Master landscaping implementation will follow this project • Parking Structure – groundbreaking anticipated May 2010 • Building O2 occupancy scheduled • BMT and IITS – Fall 2010 • Install portables for swing space at PCC – Summer 2010 • Begin construction of Buildings DD and EE at PCC • Anticipating Fall 2010 start • Anticipating swing space move for Building A at LAC – Summer 2010 • Marquees complete – Fall 2010
Planned Phasing of Future Projects • 2010-11 • Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010 • Retrofit completion of Building Z – Spring 2010 • Begin construction of Building A at LAC – Fall 2010 • Begin Schematic Design for Buildings C and F at LAC • Submit plans to DSA no later than Summer 2011
Planned Phasing of Future Projects • 2011-12 • Infrastructure project complete at LAC – Summer 2011 • Submit plans to DSA for Math/Technology Building at LAC – Summer 2012 • Construction completion of Buildings DD and EE at PCC – Fall 2011 • Begin construction of Buildings AA, BB and CC at PCC – Fall 2011 • Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011 • Anticipated construction completion of Parking Structure at LAC – Spring 2012
Planned Phasing of Future Projects • 2012-13 • Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Summer 2012 • Anticipated Construction completion of Building A at LAC – Summer 2012 • Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012 • Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012 • Submit to DSA – Spring 2013 • Begin construction of Math/Technology Building at LAC – Winter 2013
Planned Phasing of Future Projects • 2012-13 (continued) • Begin Schematic Design for Building D and E renovations – Fall 2013 • Anticipated Construction completion of Buildings AA, BB and CC at PCC – Summer 2013
Planned Phasing of Future Projects • 2013-14 • Anticipated Construction completion of Buildings C and F at LAC – Fall 2013 • Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013 • Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013 • Schematic design for Performing Arts Building (G & H) and Building R at LAC – Spring 2014
Planned Phasing of Future Projects • 2014-15 • Anticipated Construction completion of Math/Technology Building at LAC – Summer 2014 • Begin construction on Buildings D and E at LAC – Fall 2014 • Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015 • Anticipate construction start – Spring 2016 • Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015 • Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015